HomeMy WebLinkAboutODELL BREWING COMPANY EXPANSION - MOD - 17-08 - CORRESPONDENCE - (4)3.2.2(D)(3). Please contact Dana Leavitt, 221-6750 for further.
information.
25. Please provide a letter stating the company's recycling policy and
processes as this should be sufficient to meet the requirements of 3.2.5
Trash and Recycling Encloses section of the Fort Collins Land Use Code
(LUC).
26. In addition to providing bike racks near the tap room entrance, you may
want to consider adding bike racks around the detention pond to
accommodate the number of bicyclists that visit the brewery on Saturdays
and holidays.
27. Fort Collins native plant material will be required to be planted within
buffer zones. We would also like to encourage the applicant to consider
planting native plant material for landscaping.
28. We would like to encourage the applicant to consider contacting Gary
Schroeder, 221-6395 to explore utilizing the City's Design Assistance
Program to help design an energy efficient/sustainable building.
6
Transportation Impact Study. The evaluation of the request is made by
the Engineering Department and is not forwarded to the Hearing Officer..
16. The scope of the aforementioned T.I.S. should be determined by Traffic
Operations Department. Please contact Ward Stanford, 221-6820, for
further information.
17. No new right-of-way is needed for Lincoln Avenue. But, as an arterial
street, the applicant is required to provide the ultimate design of the fully
improved roadway to ensure that improvements along the property's
frontage will tie in with future improvements to the east and west. In
particular, the vertical design is most important to make sure that there is
positive drainage along the roadway. The extent of this design is 1,000 in
both directions.
18. As the developer, Odell Brewing is required to improve the frontage along
the Lincoln Avenue. Or, at the determination of the City Engineer, these
improvements may be escrowed for future roadway improvements along
Lincoln to be constructed in a more comprehensive manner than just the
subject property's frontage.
19. Any discussion regarding diagonal or parallel parking along Lincoln
Avenue would involve meeting with staff from Engineering, Transportation
Planning and would follow the direction of the Downtown River District
Plan.
20. At the time of submittal for the Major Amendment, the applicant will be
assessed the Transportation Development Review Fee. This fee is based
on a formula. Please contact Randy Maizland, 221-6605 for an estimate
of this fee.
21. New construction will be assessed two transportation related fees
collected at the time of Building Permit issuance. First is the City's Street
Oversizing Fee and second is Larimer County's Road Impact Fee. For an
estimate of these fees, please contact Matt Baker in the City's Engineering
Department at 221-6605.
22. A plat or replat will not be required but only so long as the improvements
north of the existing platted lot line do not consist of a building.
23. The normal Utility Plans, Development Agreement and Development
Construction Permit will be required.
24. 1 have enclosed a copy of the Administrative Interpretation which allows
for porous concrete to satisfy the paving requirements of Section
5
actually have the LID committee review and suggest BMPs to use on the
site. There is a possibility that the Stormwater Utility would assist
financially if there.was a BMP that was more "experimental" in nature.
The Utility is interested in assisting in the implementation of various BMPs
to evaluate the effectiveness and maintenance required. The applicant
needs to involve the Utility and the LID Committee early on in the design
stage.
9. A revised drainage and erosion control report and construction plans are
required and must be prepared by a Professional Engineer registered in
Colorado. The design of this site must conform to the drainage basin
design of the Dry Creek Master Drainage Plan as well the City's Design
Criteria and Construction standards.
10. The city wide development fee is $4,420/acre ($0.1015/sq.ft.) for new
impervious area over 350 sq.ft. No fee is charged for existing impervious
area. This fee is to be paid at the time each building permit is issued.
11. The site is in the Cache La Poudre 500-year floodplain now because the
Oxbow levee took it out of the 100-year floodplain. The previous
variances for the site related to Dryland Access and the floatable materials
(delivery trucks) which are no longer needed because either the
regulations changed (Dryland access no longer required) or the mapping
changed and the regulation no longer applies (floatable materials). The
only restriction in the 500-year floodplain is no life -safety and emergency
response critical facilities. For further information, please contact Glen
Schlueter, 221-6700. .
12. Water/Wastewater comments: Existing mains: 16-inch water main in
Lincoln, 8-inch sanitary sewer in Lincoln (East 1/3 of site). There is an
existing 2-inch domestic water service and a 6-inch fire line providing
service to the building.
13. As.a part of the expansion, provide a sampling/monitoring manhole on the
sewer service for testing the strength of the process wastewater.
14. No change to the existing water service is planned at this time. For further
information, please contact Roger Buffington, 221-6700.
15. Lincoln Avenue is classified on the Master Street Plan as a four -lane
arterial street. The proposed driveway that would serve the west parking
lot does not meet the 460-foot driveway separation required for arterial
streets. As shown, it is too close to Third Street, the east parking lot
entrance, and driveways across the street. A variance to this Street
Standard would be required. Such a variance must be supported by a
4
Hearing Officer as an Administrative Review. Or, the Modification may be
considered concurrently with the Major Amendment.
4. A maximum number of .75 spaces per employee are allowed. This
standard may be slightly increased to provide parking for shift overlap or
other factors unique to the operation of the facility. Section 3.2.2(K)(3)
allows for the number of spaces to be increased as an Altemative
Compliance provision. In order to take advantage of this provision, and to
allow an increase in parking on the west side for the tap room, please
provide information regarding public usage of the tap room.
5. The parking lot should be screened from the west property line in a
manner that may incorporate berming, landscaping, low screen walls or
any combination of sufficient opacity to block at least 75% of the light from
vehicle headlights [Section 3.2.1(E)(4)(b)].
6. Electrical power is available along Lincoln Avenue. Presently, the building
is served by a 150 kva transformer. For the addition, please provide a
Commercial One ("C-1 ") Form and a One -Line Diagram, prepared by the
electrical contractor, to determine if the existing transformer is adequate.
Normal site and development charges will apply to the new construction.
Be sure that the Major Amendment clearly delineates a phasing line
between current and future improvements to the north so that Light and
Power fees and charges are assessed accordingly. For further
information, please contact Rob Irish at 221-6700.
7. In the Dry Creek basin, the two year historic release rate is 0.2 cfs/acre.
There are issues with the capacity of the Lincoln channel which is the
outfall for this site. Please contact Rex Burns (498-5721) at the Larimer
County Engineering Department for any requirements they may have.
There are properties to the east that are flooded frequently so the County
has required special release rates or delayed release into the channel.
Any Low Impact Development (LID) measures used will lessen the impact
on the Lincoln Channel.
8. If there is an increase in imperviousness greater than 1000 square feet,
onsite detention is required with a 2 year historic release rate for water
quantity. Parking lot detention for water quantity is allowed as long as it is
not deeper than one foot. If there is less than 1000 but more than 350
square feet of new imperviousness, a site grading plan is all that is
required. Water quality treatment is also required as described in the
Urban Storm Drainage Criteria Manual, Volume 3 — Best Management
Practices (BMPs). Extended detention is the usual method selected for
water quality treatment but all BMPs are encouraged and can reduce the
water quality capture volume for extended detention. The Stormwater
Utility is willing to work with the applicant on "experimental' BMPs and
3
CONCEPTUAL REVIEW STAFF COMMENTS
City of Fort Collins
ITEM: Odell Brewery Expansion — 800 East Lincoln Avenue
MEETING DATE: May 12, 2008
APPLICANT: Odell Brewing Company, 800 East Lincoln Avenue,
Fort Collins, CO 80524 c/o Mr. Bruce Hendee, B.H.A.
Design, 1603 Oak Ridge Drive, Fort Collins, CO
80525.
LAND USE DATA: Request to expand the brewery by adding
approximately 20,000 to 25,000 square feet for all aspects of the brewing
operation. This includes expansion of the fermentation tanks, cooler facilities,
warehouse and offices. In addition, a new customer parking lot for approximately
78 spaces on the west side of the building is proposed to serve the new entry to
the tap room. A new truck dock at the northwest corner of the expanded building
would be provided.
COMMENTS:
The site is zoned I, Industrial. The brewery operation is considered light
industrial which is permitted in the Industrial zone. The request would be
processed as a Major Amendment. Since the new structure is less than
50,000 square feet in gross leasable area, it is subject to Administrative
Review (Type One) review. Although a city -sponsored neighborhood
information meeting is not required, contacting the surrounding property
owners prior to the public hearing is recommended.
2. An.Overall Development Plan will be required. This O.D.P. can be
submitted and reviewed concurrently with the Major Amendment.
3. A minimum of 80 feet of buffer is required along the west property line. A
Request for Modification to reduce this buffer may be submitted as a
stand-alone application prior to consideration of the Major Amendment.
As with the Major Amendment, the Modification will be forwarded to the
2
COMMUNITY PLANNING AND ENVIRONMENTAL SERVICES 281 N. College Ave. P.O. Box 580 Fort Collins, CO 80522-0580 (970) 221-6750
PLANNING DEPARTMENT
i
fo
Comm. Ay Planning and Environmen. Services
Neighborhood Services
May 16, 2008
Mr. Bruce Hendee
BHA Design
1603 Oak Ridge Drive
Fort Collins, CO 80525
Dear Bruce:
For your information, attached is a copy of the Staffs comments for Odell
Brewing Company Expansion, which was presented before the Conceptual
Review Team on May 12, 2008.
The comments are offered by staff to assist you in preparing the detailed
components of the project application. Modifications and additions to these
comments may be made at the time of formal review of this project.
If you should have any questions regarding these comments or the next steps in
the review process, please feel free to call me at 970-221-6750.
Sincerely, l
07i
41-OUA
Ted Shepard
Chief Planner
Xc: Project Planner
File
281 N. College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (970) 224-6046 • FAX (970) 224-6050