HomeMy WebLinkAboutEAST RIDGE - FDP - 33-98F - CORRESPONDENCE - (9)RECEIVED co 22 May 2008 Mr. Todd Rand TST Inc. 748 Whalers Way, Building D Fort Collins, Colorado 80525 Re: East Ridge Utility Plans: 2nd Review Dear Mr. Rand: (6 MAY 2 3 2008��� Plans for the East Ridge development were received at Boxelder Sanitation District (District). District staff have reviewed and redlined the drawings. The following comments are to further clarify redlines. Note that comments below are not included for all redlines on the drawings. Sheet # Comment All Use updated signature block — updated version emailed to Keith Sheaffer on 19 Sheets May 2008. Plat Add the plat language for sewer easements — emailed version to Keith Sheaffer she 1 on 19 May 2008. of 10 i 51 See redlines, need to revise location of MH NM10010 so that it is more accessible. 64 Easement for sewer is called out as 25-ft, plat shows 30-ft. District requires 30-ft as called out on plat. Please return these redlines with future submittals to aid in our back -checking of the revised drawings. I hope these comments and the redlines are clear enough to be easily addressed in a revision to these plans. If there are questions, please contact me at 970-498-0604. S:\DEVELOPMENT\Basins\West_Basin\Cooper_Slough_lnterceptor_Subbasin\East Ridge\Design Review\2008-5-22-2nd- review.doc 3201 East Mulberry, Unit Q - P.O. Box 1518 • Fort Collins, Colorado 80522 Phone (970) 498-0604 9 Fax (970) 498-0701 • Email bsd@verinet.com BA s'9/?,F X�EC:EIV +' 9 m MAY 2 3 20008 22 May 2008 Jim Sell Design, Inc. 153 West Mountain Avenue Fort Collins, Colorado 80524 Re: East Ridge Utility Plans: 2nd Review - Landscape Jim Sell Design: Plans for the East Ridge development were received at Boxelder Sanitation District (District). District staff have reviewed and redlined the landscaping drawings. The District is concerned with the close proximity to the sanitary sewer line of some trees as shown on drawings L6 and L7. The District has redlined those drawings indicating trees it believes are problematic. The driplines of large trees (e.g. cottonwood, hackberry, etc.) must not overlap that of the sanitary sewer so that the potential from root intrusion into the sewer is minimized. Root intrusion leads to more frequent maintenance by the District and even with increased maintenance, can result in sanitary sewer backups. Please return these redlines with future submittals for our use in back -checking the revised drawings. Please review the redlines. If there are questions, please contact me at 970-498-0604. S \DEVELOPMEN-nBasins\West_Basin\Cooper_Slough_lnterceptor Subbasin\East Ridge\Design Review\2008-5-22-2nd- review-la ndscape.doc 3201 East Mulberry, Unit Q - P.O. Box 1518 • Fort Collins, Colorado 80522 Phone (970) 498-0604 0 Fax (970) 498-0701 • Email bsd@verinet.com give the issue contact as Susan Joy. Please change this contact department to PFA and also contact person to Carie Dann. Department: Stormwater-Water-Wastewaterlssue Contact: Basil Hamdan Topic: Erosion Control Number: 283 Created: 5/27/2008 [5/27/08] Please provide an erosion control construction schedule for each phase. Please provide a cost estimate and a security amount for each phase in the report. All disturbed areas within Phase 2 construction or off -site sewer construction should be re -vegetated. Please add notes to that effect. Topic: Storm sewer analysis Number: 284 Created: 5/27/2008 [5/27/08] It seems that in the 100 year there will water backing into the street from the inlets at a couple of locations. Please correct if possible or provide a variance request. Topic: Utility Plans Number: 285 Created: 5/27/2008 [5/27/08] Please move line raw water irrigation line (ST-RW) 5 foot to the north in order to provide as much room as possible to the future outlet pipe from the pond. Another round of review is necessary before City staff will consider asking for mylars of the plans. Be sure and return all red -lined plans when you re -submit. If you have any questions regarding these issues or any other issues related to this project, please feel free to call me at (970) 221-6341. Yours Truly, eve Olt City Planner cc: Susan Joy East Ridge of Fort Collins, LLC TST Engineers Current Planning file #33-98F Page 17 Number: 265 Created: 5/10/2007 [5/30/08] Please see earlier comment regarding the need to place the exhibit in the utility plans. [5/10/07] See sheet 159 Topic: Utility Plans - Water Line Plan & Profiles Number: 232 Created: 5/10/2007 (5/29/08] Please add the city's street cut note to all sheets that have a street cut. The limits were shown in this round but the note still has not been added. [5/10/07] Need to show approximate limits of all street cuts and add the city's street cut note. Number: 234 Created: 5/10/2007 [5/29/08] See the comment regarding the variance request. [5/10/07] See earlier comments regarding minimum cover requirements within the city's street section. Department: PFA Issue Contact: Carie Dann Topic: fire Number: 177 Created: 4/4/2007 [5/28/08] EMERGENCY VEHICLE ACCESS Thank you for sheet 159 of 192 "Street Plan and Profile Emergency Access Road." However, in addition to what is shown on this page, you will also need to implement/show the fire apparatus travel path on the EAE. Please contact me if you need a truck template. [4/4/07] STREET ACCESS: Per applicant response and previous meetings with Ron Gonzales of PFA, an Emergency Access Easement will be dedicated on the plat, meeting the requirement for various phases of construction, for an acceptable second point of access for emergency vehicles. When and if connectivity to adjoining property is available, access can be taken from those connecting streets, if they meet PFA standards for separation distance. The EAE shall be visible by painting and/or signage, a minimum of 20 feet wide, and maintained unobstructed at all times. Some type of barricade probably will be needed at each end of the EAE, to prevent use by non -emergency vehicles. Contact Carie Dann for specifics on signs, barricades, etc. Number: 178 Created: 4/4/2007 [5/28/08] STREET NAMES Because neither Hawker nor Katana are acceptable street names, I will need to review the two new, proposed street names prior to the project going to mylars. Mylars is too late to be able to review the new names. [4/4/07] STREET NAMES: Hawker and Katana are too close to existing street names and are not permitted. Number: 290 Created: 5/28/2008 [5/28/08] Comments regarding Emergency Access (such as comment 20) dated April 4, 2oo5; August 2, 2005; November 22, 2005; and April 12 and May 10, 2007, Page 16 emergency access does not work in the ultimate condition, then Phase 2 building permits will not be issued until an acceptable second point of access is provided. [5/10/07][4/12/07] Please provide the exhibit below and extend the profile on the plan and profile sheets out at least 50' to show how it will tie into the existing. [11/22/05] Ron Gonzales has requested a separate exhibit with the EA drive profile overlayed with their truck template to make sure their trucks can negotiate the sags and crest curves. [8/2/05] Repeat. The emergency access easement shown or its proposed location does not meet PFA's minimum requirements. As stated below, this development is required to design and construct a second point of access acceptable to PFA in both the interim and ultimate conditions if you want to pull building permits for the entire site. In order to determine if the EA drive works in both the interim and ultimate, enough preliminary horizontal AND -vertical design is required on the plans before going to public hearing. Please provide a plan and profile of the EA road as well as a plan and profile and show how it ties into Timberline in both the interim and ultimate. If you can not show that the EA drive will work in the ultimate, than only half the site will be allowed to pull building permits and this site would have to be phased or done in separate filings (please see comment 21). [4/20/05] This development as shown with is out of fire access. A second point of access is required per Ron Gonzales with PFA. He has agreed to a temporary emergency access lane off the north west side of the property in the interim BUT this may go away if the over/under pass is constructed. If and when that happens, another acceptable secondary point of access will be.required prior to the release of future phases. Number: 223 Created: 5/10/2007 [5/28/08] Please include in the emergency access road typical section what the grading is like on either side. The grading sheets don't show a swale on either side to handle the drainage and the road appears superimposed on the contours. You'll need to grade specifically for this road plus deal with the drainage somehow. (5/10/07] Please provide a cross section, a plan and profile and identify all materials for the proposed 12' access road along the southern property boundary if this is meant to be for PFA. If not, and its more of a maintenance road, then just give the cross section and identify the materials its to be constructed out of. Thanks. Also, the access road has to be within 10 degrees of 90 for the first 25' off Dassault. Number: 260 Created: 5/10/2007 [5/29/08] The EA drive still does not show grading outside the drive limits. Must match the grading sheet. [5/10/07] See sheet 149 - Provide a typical cross section for the emergency access drive, a CL profile and call out what it is constructed out of. Page 15 Topic: Utility Plans - Storm Sewer P&P Number: 240 Created: 5/10/2007 [5/29/08] Keeping this open until the variance request has been properly resubmitted and the appropriate info called out on the plans in all locations that minimum cover is not met. [5/10/07] Minimum cover issues here as well. Number: 318 Created: 5/30/2008 [5/30/08] Sheet 99 - Please show where the easement is on the profile plus station it so they know where it is the field. Number: 319 Created: 5/30/2008 [5/30/08] Please provide the proposed International profile on sheet 99 so that we can determine that the minimum cover requirements can be met. Number: 320 Created: 5/30/2008 [5/30/08] Please remove all unnecessary information off the plan view. Topic: Utility Plans - Street Section Details Number: 275 Created: 5/10/2007 (5/30/08] Still need 1606. (5110/07] Please provide drawings 706, 707, 1601, 1606. Topic: Utility Plans - Striping Plan Number: 266 Created: 5/10/2007 [5/29/08] Why has the bike lane been reduced to 6'? Please see Ward/Traffic Engineering and Denise Weston in Transportation Planning. A variance request completed per 1.9.4 will be required for their review and approval if not the standard 8. [5/10/07] See sheet 160 for redlines. Need to start taper earlier, reverse the bike and right turn lane and adjust the one lane width circled. Wouldn't hurt to meet with Matt, me and Ward or something to iron this out for you so you don't have to keep messing with it. A 5' temp asphalt sidewalk is called out, should say 6'. Need a ramp to get the bikes from the sidewalk to the onstreet bike lane. Topic: Utility Plans - Timberline Ultimate Grading Number: 264 Created: 5/10/2007 [5/29/08] Still need to show property lines and label property owners. [5/10/07] Please label contours for existing grades. Label existing features like the ditch, property lines, etc. Topic: Utility Plans - Ultimate EA Road Number: 20 Created: 4/20/2005 [5/28/08] 1 have not received this exhibit to date and after talking to PFA, it was determined that this exhibit needs to be shown on the utility plans, sheet 159. If the Page 14 gutter on the east side. Correct the typical street section so that the sidewalk on the east side is labeled as future, to be built by others. Topic: Utility Plans - RW Irrigation P&P Number: 241 Created: 5/10/2007 [5/29/08] Keeping this open until the variance request has been properly resubmitted and the appropriate info called out on the plans in all locations that minimum cover is not met. [5/10/07] Minimum cover issues here too. Number: 321 Created: 5/30/2008 [5/30/08] Please remove all unnecessary information off the plan view. Number: 322 Created: 5/30/2008 [5/30/08] Please add the city's street cut note. Number: 323 Created: 5/30/2008 [5/30/08] Sheet 103 - Refer to sheet number where referencing a detail. Topic: Utility Plans - Sanitary Sewer/International Blvd P&P Number: 239 Created: 5/10/2007 [5/29/08] Keeping this open until the variance request has been properly resubmitted and the appropriate info called out on the plans in all locations that minimum cover is not met. [5/10/07] Minimum cover not being met in several areas. Number: 317 Created: 5/30/2008 [5/30/08] Note number 5 needs to reference the sheet number the cut off wall detail is shown on. Correct this note on all sheets. Topic: Utility Plans - Sanitary Sewer/Peakview Number: 235 Created: 5/10/2007 [5/28/08] See comment 230. [5/10/07] Again, who is constructing this? You or Peakview? Please provide more information in order to build this and let me know about the timing of the whole thing. Number: 236 Created: 5/10/2007 [5/28/08] Peakview plans have not been approved as of yet so there are no construction plans on file with the County. Either that set needs to be approved and on file or this set of plans will need to design it and the Peakview folks will need to sign off on them prior to final approval of mylars. [5/10/07] Are you constructing this line, placing the manholes at existing grade and then Peakview is raising them later? Peakview's plans may need to be revised in order to reflect this. Page 13 Number: 250 Created: 5/10/2007 [5/29/08] Please carry the profiles out at least 50' past the matchline on all plan and profile sheets. [5/10/07] Yeager St, sheet 117 - not enough overlap between sheets, missing information. Number: 252 Created: 5/10/2007 [5/30/08] This has not been done. [5/10/07] Take all profiles out to the CL of the street being intersected. Number: 253 Created: 5/10/2007 [5/29/08] Please label all curb types in the plan view. Only some blocks are labeled with this round. Please label all typical street sections with the appropriate street section on all sheets where more than one section is shown. [5/10/07] Label the transition from VC to Rollover or where one ends and the other starts at a curb return or something like that. Number: 314 Created: 5/30/2008 [5/30/08] Need full design for both interim and ultimate to the property line where all streets stub out to the future International Blvd (see comment 25). You can combine this information on the existing profiles and label as interim and ultimate. Number: 324 Created: 5/30/2008 (5/30/08] Sykes Drive - Not enough information is shown to construct the median. If the median infall gutter stays, we will need a profile for that plus an inlet to handle the drainage. If you change to outfall gutter, you can drop the 3% cross slope to 2% and provide more spot elevations so that it is clear how to build it and how it will drain. Please provide a separate detail for the ped refuge area showing enough spot elevations and cross slopes to construct it (all grades must meet ADA requirements). Number: 325 Created: 5/30/2008 [5/30/08] Missing spot elevations in the intersections. See details 7-27 and 7-28. 1 did not go through every intersection looking for every missing spot - please do so and resubmit. I will review when all information is present. Number: 326 Created: 5/30/2008 (5/30/08] Typical street sections must match the profile labeling. Call out as east and west versus left and right. Number: 327 Created: 5/30/2008 [5/30/08] Sheet 126 - need to call out interim and ultimate improvements. Number: 328 Created: 5/30/2008 [5/30/08] Delozier is showing that curb, gutter and sidewalk is to be installed in the future by others. This is incorrect. This development must construct the curb and Page 12 Topic: Utility Plans - Overall Utility Plan Number: 227 Created: 5/10/2007 [5/29/08] The crossing table only provides the depth and clearance information. Is this sufficient? Do you need to reference specific lines or sheets? [5/10/07] Note 17 says to see sheet 185 for crossing table. No such table provided on 185. Number: 229 Created: 5/10/2007 [5/29/08] [5/10/07] Sheet 42 - The access road is called out on this sheet for the first time as a 12' nature trail/sewer maintenance road. You will need to provide additional easements in order to allow this use to occur. Number: 233 Created: 5/10/2007 [5/29/08] The approximate limits have been shown, however the street cut note has not been added. Please review section 25.7 of LCUASS for street patch requirements to make sure that the limits shown meet our standards. Please add the following statement to all sheets that show a street cut: Limits of street cut are approximate. Final limits are to be determined in the field by the City Engineering Inspector. All repairs to be in accordance with City street repair standards. [5/10/07] Need to show approximate limits of all street cuts and add the city's street cut note. Topic: Utility Plans - P&Ps Number: 244 Created: 5/10/2007 [5/29/08] Repeat. Please identify the transition length as required by 7-27 and 7-28. [5/10/07] Need to identify the point of transition to remove the crown at all intersections, minimum 30' from FL - see figures 7-27 and 7-28. Number: 247 Created: 5/10/2007 [5/30/08] This may need to happen yet. [5/10/07] If the plan view starts to get too cluttered to meet the scanning requirements, you could make a separate sheet(s) for the intersection details. That way you could make the spot font a little bigger and it won't make the P&P sheets too hard to read. Just a suggestion... Number: 248 Created: 5/10/2007 [5/29/08] Repeat. Please clearly identify both interim asphalt sidewalks beginning and end and label with ultimate concrete sidewalks to be installed with future development OR when temp asphalt sidewalks are not required, install/label with type III barricades. [5/10/07] Please provide Type III Barricades (and detail on the detail sheet) for all dead end sidewalks and street stub outs unless the street is ending in a temp turnaround. Need to show on the grading and utility sheets too. Page 11 Topic: Utility Plans - General Notes Number: 297 Created: 5/30/2008 [5/30/08] Line 48 of the General Notes needs to state the code, what it requires and what the variance was granted for. Please do not refer to a letter as this info needs to be part of the plan set. Topic: Utility Plans -Grading Number: 226 Created: 5/10/2007 [5/28/08] Repeat comment. The grading sheets must match the plan and profile sheets. [5/10/07] Please provide grading sheets for all offsite work for tying into the Peak View project. Need enough information to construct it as well. Number: 230 Created: 5/10/2007 (5/28/08] The plans now label the offsite waterline to be constructed by Peakview and the sanitary sewer line to be constructed by Eastridge. That is fine, however, BOTH lines need to be constructed before the issuance of the first building permit in Eastridge. This could potentially hold up your project. [5/10/07] Sheet 43 - this ties into an earlier comment. Who is this work proposed by? If constructing with this project, please provide a full design for it and any necessary offsite easement in order to do it. If the work is being done by others and this development depends on it, then their timing will affect your ability to start your project. We might want to talk about this more. Topic: Utility Plans - Grading Phasing Plan Number: 224 Created: 5/10/2007 [5/28/08] [5/10/07] Need more overlap between sheets. Scanning is a problem here as well. Number: 310 Created: 5/30/2008 [5/30/08] Please move all text off proposed grading as it hides what is proposed to be constructed. It appears that some of the grading shown in Phase 2 is actually under Phase 1 as overlot and detailed grading necessary to support Phase 1 until Phase 2 is constructed. Please update the plan to reflect that accurately. Number: 311 Created: 5/30/2008 [5/30/08] The temporary turnaround is called out with 6" gravel base course. The requirement is that it must be an all weather surface. Please make sure this material complies with PFA's definition of an all weather surface. Topic: Utility Plans - Master Grading Sheets Number: 217 Created: 5/10/2007 [5/29/08] Please see John Pedas in Tech Services prior to the next submittal. [5/10/07] These sheets probably won't scan. Perhaps reducing the pen width might help make the lines and text less fuzzy. Page 10 Number: 212 Created: 5/10/2007 [5/28/08] This still remains an issue. Please provide enough design information past the matchline so that each lot is shown in its entirety on at least one sheet. [5/10/07] There is not enough overlap at the matchlines.... missing as much or more than an entire lot between the sheets. Number: 219 Created: 5/10/2007 [5/28/08] [5/10/07] Please label all easements dedicated by separate document with the reception number. Number: 222 Created: 5/10/2007 [5/28/08] Scannability has improved with this round but there are still scanning issues with the set. [5/10/07] Lots of scanning issues with the plan set. Need to correct all line over text, reduce some pen widths so that the text isn't blurry and make sure you're meeting minimum font sizes. Please see JR or John Pedas in Tech Services if you have any questions. Number: 225 Created: 5/10/2007 [5/29/08] The lots listed below may only take driveway access off Dassault unless temp turnarounds are provided for the street they wish to take access off of. This requirement will go into the DA and a note stating such must be placed on the site/landscape/utility plan grading and street plan and profile sheets so that it is very clear to any potential owner of these lots where their drive must take access from. [5/10/07] Must provide temp turnarounds in order to pull building permits for lots 1, 2, 27-29 off Dassault between Katana and International. Cannot pull a permit at all for lot 2 unless entire street frontage is constructed. Number: 255 Created: 5/10/2007 [5/30/08] Please provide detail D10, 11, 12 or 13 (whichever appropriate) and refer to detail/sheet number on all P&P and grading sheets. Please design in accordance with said detail. This applies to any sidewalk chase in public row whether they appear on alleys or public streets. Please remove detail 709 on sheet 189 and replace it with the appropriate detail(s). [5/10/07] Alleys - Label all sidewalk chases and drainage pans and label detail #, sheet'. Number: 277 Created: 5/10/2007 [5/29/08] [5/10/07] Please check each sheet for comments as I'm not 100% sure that I typed every one out and I did not put a post -it note on each sheet that have comments. Thanks very much. Number: 316 Created: 5/30/2008 [5/30/08] Larimer County must review and approve all sheets that show construction taking place for the offsite Peakview improvements. Please add a county signature block to the cover sheet and all other appropriate sheets. Page 9 when you call out riprap or a sidewalk chase, etc, label with both the detail and sheet numbers. This would apply to any sheet, not just the grading. Number: 304 Created: 5/30/2008 [5/30/08] Not enough overlap at matchlines. Please show enough info past the matchline so that each lot is shown in full on at least one sheet. Number: 305 Created: 5/30/2008 [5/30/08] Please label all slope ratios. Number: 306 Created: 5/30/2008 [5/30/08] Please call out all sidewalk culverts referencing detail and sheet number. Please label all crosspans with dimensions. Number: 307 Created: 5/30/2008 (5/30/08] Please see the comment under Emergency Access Drive regarding the grading in this area. Topic: Utility Plans - Erosion Control Plan Number: 211 Created: 5/10/2007 [5129/08] Please clearly indicate which, if any, erosion control improvements are to be done with Phase 1 that are shown in Phase 2's area. There is a note on the plans stating that there was to be a symbol corresponding to the legend what gets installed with each phase but there was no symbol provided. [5/10/07] Please provide an erosion control plan for Phase 2. Currently only showing a plan for Phase 1. Number: 312 Created: 5/30/2008 [5/30/08] Please see John Pedas regarding scanning requirements. Number: 313 Created: 5/30/2008 [5/30/08] Not enough overlap at matchlines. Topic: Utility Plans - General Number: 209 Created: 5/10/2007 [5/28/08] Please resubmit the variance request to clearly state each location where the minimum cover requirements are not being met along with the proposed depth. The utility plans need to dimension the depth from top of pipe to finish grade on the applicable plan and profile sheet. Each location can then be evaluated, approved, approved with conditions or denied. The updated variance along with all affected plan and profile sheets can be turned in prior to the next submittal for our review and approval so that we don't have to waste another round of review on this issue. [5/10/07] Minimum cover requirements are not being met per section 12.2.2. 1 did not review the plan and profile sheets in any detail as the grades will probably change with the next submittal to fix the cover problem. Page 8 Topic: Utility Plans - Cover Sheet Number: 296 Created: 5/30/2008 [5/30/08] Please see redlines on cover sheet. This is an extremely large set of plans so it is very important that the sheets be ordered in a logical manner. Please label the grading sheets individually and in order in the index (ie..existing/demo, master, phasing and then detailed). The drainage plan has been added as sheet 1 of 2 and 2 of 2 on the end of the plan set and labeled as for reference only. If this information is required to construct this project then it is not for reference only and needs to be part of the plan set. Also, Phase 1 shown but not Phase 2. Please add Phase 2. Please remove all sheets that are not part of this project. Topic: Utility Plans - Cross Sections Number: 270 Created: 5/10/2007 [5/30/08] Your response indicates that you have labeled and shown this information as "typical" in one section, which is fine, but remaining cross sections still need to show the UE lineweight and label. No need to dimension as the typical cross section has done so. Please include all offsite easements where necessary on the cross section so that it is clear that the proposed work is being completed within the easement. [5/10/07] Dim roadway width and UE. Number: 272 Created: 5/10/2007 [5/29/08] Some sections have been updated but some have not. Some sections are still missing slope info completely. [5/10/07] Label all slopes to row as a ratio, not percent. Number: 329 Created: 5/30/2008 [5/30/08] Future sidewalks must still be fully designed and shown in the cross sections... just label as future. , Number: 330 Created: 5/30/2008 [5/30/08] Cross sections are still incomplete. Will review and comment in detail when all information is shown. Topic: Utility Plans - Demo Sheet Number: 267 Created: 5/10/2007 [5/29/08] The demo sheet seems to be missing with this submittal. Demo or existing conditions sheets are added from another unrelated project. ? [5/10/07] Please provide the city's street cut note on the demo sheets. Topic: Utility Plans - Detailed Grading Plan Number: 221 Created: 5/10/2007 [5/28/08] The sheet called out for the swale sections do not have the detail promised. Please correct on each sheet. [5/10/07] Comment #218 applies to these sheets as well. Also, anytime something is labeled with "see detail xx" then you need to refer to the sheet it appears on. Or Page 7 Number: 331 Created: 6/2/2008 [6/2/08] From Technical Services: 1. Boundary and legal close. 2. Name of Plat is inconsistent. Make sure it matches the "name" in the dedication statement. 3. Plat needs a note as to what are the permitted uses in the wetland buffer. 4. Street Names: Hawker and Katana are no good per PFA. Topic: Site Plan Number: 281 Created: 5/10/2007 [5/28/08] [5/10/07] See comments under other sections that will affect this plan set. Please coordinate with the other plan sets so that everything matches. Number: 282 Created: 5/10/2007 [5/28/08] Minor scanning issues this time, please remove the shading within the sight distance easement and correct all line over text. See redlines. You might want to meet with John Pedas in Tech Services - one of the pen widths seems pretty thick on the smaller font and I'm not sure it will scan. [5/10/07] Scanning continues to be a thorn for you, I know, but we'll work through it. Just need to get the plan sets scannable by mylars. Number: 291 Created: 5/28/2008 [5/28/08] There is an easement missing on sheet 2 at the north end of Navion Lane up to the RR tracks. There are lots of easements shown on the subsequent sheets that are not labeled. Number: 292 Created: 5/28/2008 [5/28/08] The all weather drive on the east side of Yeager is shown as "future" but the temp turnaround is not shown. Please show the interim condition as well. Please correct the site plan to match the utility plans. Topic: Utility Plans Number: 43 Created: 4/20/2005 [5/29/08] The wrong detail has been used. Please remove 709 and use details D10, D11, D12 or D13 as appropriate, call out which detail and sheet at each location a sidewalk culvert is used on both the grading and street P&Ps. Please design all chases in accordance with the correct detail - those shown are too close to the curb returns. [4/12/07] [11/22/05] Final Compliance - call out the appropriate detail for the sidewalk culverts from the alley to the street (D10-13) on sheet xx. [812/05] No more than 500sf of surface area may drain over a public sidewalk. [4/20/05] Will need sidewalk culverts at all Alley intersections to take the drainage out to the street. Cannot drain over sidewalk. Page 6 Topic: Plat Number: 204 Created: 5/10/2007 [5/28/08] Please remove all zoning information from the tract table. Please include who owns and maintains the private easements. [5/10/07] Please provide a tract table listing who owns and maintains all tracts and private easements. Need to state what each of the tracts are being dedicated for as well. Number: 205 Created: 5/10/2007 [5/28/08] [5/10/07] Please see comments under other sections as some of them will effect the plat. Number: 206 Created: 5/10/2007 [5/28/08] (5/10/07] Please see Appendix E6 for all scanning requirements. Number: 214 Created: 5/10/2007 [5/30/08] [5/10/07] See redlines for other comments. Number: 216 Created: 5/10/2007 [5/28/08] [5/10/07] Please provide a copy of all easements dedicated by separate document and label them on the plat with the reception numbers. Number: 298 Created: 5/30/2008 [5/30/08] Note 4 does not match the tract table. Please correct. Number: 299 Created: 5/30/2008 [5/30/08] Please define Landscape Buffer and Park Easement. Number: 300 Created: 5/30/2008 [5/30/08] Please correct the misspelling in Note 7. Number: 301 Created: 5/30/2008 [5/30/08] Depending on the timing of the city's purchase of the park area, the city may or may not need to sign off as an owner. If this plat is recorded prior to the transfer of the property to the city, then the city will not have to sign. If the property transfers after, then the city will have to sign. Number: 302 Created: 5/30/2008 [5/30/08] Please spell out all abbreviations or provide a legend that lists and defines them. Number: 303 Created: 5/30/2008 [5/30/08] Please use hatching to indicate what is being vacated on sheet 9 & 10 as shading does not meet our scanning requirements (because it does not scan). Page 5 just the larger volume streets. I strongly suggest doing this as it will also help with the scannibility of the plan sets. [5/9/07] Street stubs to the south will require barricades AND a sign clearly stating that this street is to connect through so that there will be no misunderstandings with the future residents. Number: 295 Created: 5/28/2008 [5/28/08] All street naming issues must be resolved and the plan sets updated prior to the next submittal. We cannot let this issue linger until mylars as there are too many sheets that are affected and there is a huge potential that the mylars may not be correct at mylars. I would hate to have to reject them. Number: 309 Created: 5/30/2008 [5/30/08] There is a new 12' all-weather road shown on the south sides of the lots that are on the south side of Crusader. No lots may take access off this drive unless it is paved as a private drive or built to public alley standards. If you decide to not pave it, then a note must be clearly labeled on the site, landscape and utility plans stating this restriction so that future homeowners and builders are aware of it. Topic: Landscape Plans Number: 91 Created: 4/25/2005 [5/28/08] Please remove the shading within the sight distance easement for scannability. [5/9/07] There are still scanning issues with the plan set. Some lineweights are very light and probably won't scan. Other lineweights are "fuzzy" and probably won't scan well either. Please see JR in Tech Services if you have any questions. [11/22/05] Final Compliance - the plans look much better but it wouldn't hurt to meet with JR in Tech Services before going to mylar when we're ready for that. [8/5/05] [4/25/05] Please see Appendix E6 for scanning requirements. These sheets will not scan well and will not be accepted. Number: 280 Created: 5/10/2007 [5/29/08] [5/10/07] See comments under other sections that will affect this plan set. Please coordinate with the other plan sets so that everything matches. Number: 293 Created: 5/28/2008 (5/28/08] Please label all easements. Number: 294 Created: 5/28/2008 [5/28/08] Sheet 6 has labeled a hatched area representing a 20' landscape clear zone for future regional detention pond outlet yet no hatched area is shown. Please clarify. Page 4 of roadway adjacent to buildable lots will need to be constructed in accordance with Section 24-95 of the City Code and Section 3.3.2(D)(6) of the Land Use Code. Estimates for the escrow amounts must be submitted by a license professional engineer for the City's review and approval and those amounts will be added into the Development Agreement. [4/20/05] This development is responsible for the design and construction of International along its frontage. Need an interim and ultimate design for your street stubs to it. Will need to provide an estimate for the construction of the street stubs to the property line for our review and approval. That amount will go into the DA. Number: 35 Created: 4/20/2005 [5/28/08] 1 have asked that John Pedas in Tech Services be routed all plan sets on the next submittal for his review as there are still scanning issues with the plan set. [4/12/07] Still have some problems with overlapping text on the utility plans... I've highlighted most of it in pink so you can see where the problems are. Some of the spot elevations were hard to read and because the street elevation may change due to minimum cover issues over the utilities, thought I would hold off on reviewing the spot elevations until the next round. [11/22/05] Final Compliance. Please see E6 and visit with JR in Tech Services to discuss the scannability of the plan sets. [8/2/05] [4/20/05] See Appendix E6 for all scanning requirements. Number: 143 Created: 11/22/2005 [5/28/08] Please see Transportation Planning regarding the TIS and ped los. There are several areas that may not meet ped level of service requirements in the interim and will require temp asphalt sidewalks until the permanent concrete sidewalks are installed with future development. In areas that can remain without sidewalks installed, type III barricades are required where all permanent sidewalks terminate. All plan sets must clearly label interim and ultimate - as it stands right now, it is not clear where sidewalks are beginning and ending. [5/9/07] [11/22/05] Final Compliance - We don't want the sidewalks and street trees installed along any undeveloped tract and in FC, we'll want the various plan sets to be clearly labeled as such and we'll need an estimate for the uninstalled items for our review and approval. Once agreed upon, that amount will need to go in the DA and escrowed prior to the first building permit. For phasing within the developed areas, we'll want both sides of the street fully constructed, including landscaping and sidewalks. Please adjust your phase lines to show that. Number: 203 Created: 5/9/2007 [5/29/08] The signage plan was combined with the plan and profile sheets making it difficult to see the project as a whole. Transportation Planning and Traffic Engineering may require that this information be presented on a separate striping and signage plan for all local streets instead of only providing separate sheets for Page 3 Topic: Utility Plans - Sanitary Sewer/International Blvd P&P Number: 289 Created: 5/27/2008 [5/27/08] Randy Siddens of the Boxelder Sanitation District indicated that they have no major issues. Please see the red -lined plans and comment letters from the district. Topic: Utility Plans - Water Line Plan & Profiles Number: 287 Created: 5/27/2008 [5/27/08] Darwin Williams of the East Larimer County Water District (ELCO) indicated that their comments are being made on red -lined utility plans being returned to the developer's engineer. Department: Engineering Issue Contact: Susan Joy Topic: Barker Agreement Number: 308 Created: 5/30/2008 [5/30/08] The Barker agreement needs to be recorded and the reception number placed on the plan sets. Please provide Engineering with a fully signed and executed agreement prior to the final signing of mylars. Number: 315 Created: 5/30/2008 [5/30/08] The Barker agreement must include all necessary easements to construct the berm and be recorded. Please label the reception number on all sheets where this area is shown. If the agreement does not contain the easements necessary to construct the improvements shown, then separate easements by separate document must be dedicated and recorded. Please provide copies if separate easements are required. Please provide Basil Hamdan in Stormwater a copy of the easement for his review. There may be additional easements required by Stormwater that must be dedicated to the City and may not be covered under this agreement. Topic: General Number: 25 Created: 4/20/2005 [5/28/08] (4/12/07] [11/17/05] Just keeping the comment open through Final Compliance. [8/2/05] The City agrees that the developer can provide an escrow for the cost of final design and construction of that portion of International Blvd from its SE corner west to a point representing the easternmost 1/3 of the wetland. The developer will be given the option to credit this cost against the payment from the City for Timberline ROW costs. The developer does not need to provide a final design for this roadway at this time, but does need to provide a preliminary design of this roadway so that drainage patterns and roadway grades for the three street stubs that tie into International Blvd will be accommodated. The city also agrees that the developer shall provide interim and ultimate designs for the three street stubs to International Blvd and escrow the costs to construct the portion of the roadways that will not be constructed with the development. It needs to be clarified that the portion Page 2 STAFF PROJECT REVIEW Cityof Fort Collins Jim Sell Design, Inc. Date: 6/4/2008 c/o Matt Blakely 153 West Mountain Avenue Fort Collins, CO 80524 Staff has reviewed your submittal for EAST RIDGE, FINAL PLANS — TYPE 1, and we offer the following comments: ISSUES: Department: Current Planning Issue Contact: Steve Olt Topic: General Number: 286 Created: 5/27/2008 [5/27/08] Craig Foreman of Parks Planning indicated that they have no problems with this current submittal for the East Ridge - Final Plans. Number: 332 Created: 6/4/2008 [6/4/08] See red -lined Site & Landscape Plans from Current Planning that contain some minor comments. Department: Current Planning Issue Contact: Dana Leavitt Topic: Grading Plan Number: 181 Created: 4/5/2007 [5/27/08] LOD incorrectly labeled. Revise to read "Limit of Development." [4/5/07] Show Limits of Development on Grading Plans, Erosion Control Plans and Phasing Plans. Topic: Site Plan Number: 182 Created: 4/5/2007 [5/27/08] LOD incorrectly labeled. [4/5/07] show Limits of Development on Site Plans. Topic: Utility Plans Number: 183 Created: 4/5/2007 [5/27/08] Not shown on plans. Can be added to General Conditions & Specifications Sheet, if desired. [4/5/07] Add notes to Grading and Erosion Control Notes: Stockpiling of wetland soils per the Wetland Mitigation Report. Include a maximum height of stockpiles. Department: Current Planning Issue Contact: Steve Olt Topic: Utility Plans -General Number: 288 Created: 5/27/2008 [5/27/08] Don Kapperman of Comcast Cable TV indicated that they have no problems with this current submittal for the East Ridge - Final Plans. Page 1