City of Fort Collins Stormwater department agrees to proceed with the expansion of the
Manhattan detention pond in compliance with and subject to the foregoing requirements
and conditions.
City of Fort Collins Utilities/Stormwater Department
By:
Jim Hibbard, Director of Stormwater Date
cc: Pete Wray, Current Planning; Don Bachman, Engineering; John Stokes, Natural
Resources; Kevin Wilson, Poudre Fire Authority
owner or property management company to get all furnace and water heater and
pilot lights promptly re -lighted as necessary.
11. Parking Lot Stormwater Outflow Drain and Pipe - The City shall install a parking
lot drain and outflow pipes under the berm releasing water into the detention
pond, consistent with our project's storm drainage plan (i.e. at the location and
elevation specified in the plan), with the foregoing all at the City's sole expense.
12. Replacement Trees — The City will replace any trees that the City removes from
the property along the perimeter of our property. Any trees that are removed from
our property will be replaced around our detention pond. This may or may not be
along the perimeter of our property.
13. Erosion and Air Quality Mitigation — In addition to complying with all City
requirements, the City shall control blowing dirt by watering down the disturbed
soil up to two times per day, Monday through Saturday, as reasonably
necessary.
14. Landscaping — City shall repair lawn and irrigation system on both sides of the
new parking lot access driveway and elsewhere where existing landscaping is
disturbed.
15. Departmental Approvals — Stormwater commits to us that it has received all
Current Planning,. Engineering, Natural Resource, Poudre Fire Authority and
other necessary approvals for their planned detention pond construction work.
Sincerely,
Jon
Pres
J P/ks r
provided (half of the existing road for gravel/road base on grade). The City is
authorized to proceed in this fashion.
The old driveway shall be saw -cut to create an approximate 90-degree turn from
the roadway to the new driveway, and all asphalt removed from the premises and
disposed of and road base backed up against the cut edge to deter the asphalt
from raveling.
4. East Approximate 10 Feet of Parking Lot — Provided paragraph 15 is complied
with:
To be saw -cut along property line, including asphalt and concrete (curb and
gutter). Asphalt shall be removed, road base shall be packed up against the cut
asphalt edge to deter asphalt from raveling. All concrete shall be removed and
disposed of by City, all of the foregoing at the City's sole expense. We authorize
the foregoing. However, if this violates City,parking lot standards, City must
obtain a written variance for this parking lot so it may continue to serve existing
8-plex both now and subsequent to its renovation.
5. Electric — The City's Electric Department shall abandon the portion of their
electric lines that conflict with City's proposed construction, while maintaining
service to the residents of the existing 8-plex and maintaining electric lines and
transformers, if any, which are able to serve our proposed development.
6. Water — City's Water Utilities Department shall relocate any water mains that are
in conflict with City's proposed construction, while maintaining service to the
residents of the existing 8-plex and maintaining water lines which are able to
serve our development.
7. Sewer — City will adjust manholes on City property, up or down, to match the new
grade established by City construction. These adjustments will have no effect on
our project property or on sewer service to either the existing residence or our
development.
8. Gas — The City will coordinate with Excel Energy to relocate any gas lines that
are in conflict with City's proposed construction while maintaining service to the
residents of the existing 8-plex and maintaining lines which can serve our project.
9. Telephone and Cable — City shall coordinate with Qwest and Comcast to assure
that City's proposed construction is not in conflict with their lines.
10. Service Interruption to Existing 8-Plex - All of the foregoing abandonment and
relocation of utilities shall occur with minimum impact on the apartment/house
residents. Ideally, there would be no interruption of any utility service through the
apartment/house. However, if interruption is necessary, it will be for not more
than two hours. City will also coordinate with public service and the apartment
October 25, 2005
Mark Taylor
Jim Hibbard
Stormwater Department
P. O. Box 580
700 Wood Street
Fort Collins, CO 80522
Re: Manhattan/Letter of Agreement
Dear Mark and Jim:
Following up my letter of August 19th and our recent meeting, Mark, this is our letter of
agreement with the City and authorization for the City to proceed with its stormwater
detention pond construction subject to the following terms and requirements and
approvals of the below indicated signatories.
1. Tennis Court — The City shall deactivate power -to the tennis court lights, remove
tennis court asphalt, light poles and fencing, and all related materials, and
dispose of same at the City's sole expense. We authorize the City to proceed
with the foregoing.
2. Street Partial Removal — Provided paragraph 15 is complied with:
We approve the removal of that portion of Fir Ct. which is on City property
provided that that portion of this public right-of-way (not yet vacated) which
remains be in compliance with all City statutes and requirements as they relate to
access to the existing 8-plex and its renovation.
3. Twenty- Foot Driveway — Provided paragraph 15 is complied with:
We authorize the City to put a new 20 ft. driveway in from the access road to the
existing parking lot, compaction of sub -grade, road base as necessary, at least 2
inches of asphalt, no curb or gutter or other concrete along edge, align with drive
aisle of parking lot, landscape sprinkler line to be relocated under this driveway
and new sprinkler heads as necessary installed. This driveway will be installed
at least one week prior to ripping out the full driveway, and in the course of
construction of same, alternative access for tenants ingress and egress will be
3950 JFK Parkway, Bldg 12, Fort Collins, CO 80525 • (970) 226-5000 • Fax (970) 226-5125