HomeMy WebLinkAboutFOX POINTE PLAZA - PDP - 16-06 - CORRESPONDENCE - (3)Number: 3 Created: 6/27/2006
[6/27/06] Please estimate building square footages for restaurant and general office use
(indl. Coffee drive up) and provide max. parking requirements and actual parking numbers.
Office = 50%, Retail = 35%, Restaurant = 15%
Number: 4 Created: 6/27/2006
[6/27/06] Include in plant notes that no Certificate of Occupancy can be issued without
landscaping completion or financial securement in the amount of 125% of the value of the
landscaping. Agreed.
This represents staff (and outside reviewing agencies) review and comments at this time.
Additional comments and red -lined plans may be forthcoming. Another round of staff review
is determined to be necessary. This proposal is subject to the 90-day revision re -
submittal requirement (from the date of this comment letter, being July 7, 2006) as set
forth in Section 2.2.11(A) of the Land Use Code. Be sure and return all red -lined plans
when you re -submit. The number of copies of each document to re -submit is shown on the
attached Revisions Routing Sheet.
If you have any questions regarding these issues or any other issues related to this project,
please feel free to call me at 221-6341.
Yours Truly,
Steve Olt
City Planner
Page 9
Number: 54 Created: 7/3/2006
[7/3/06] The intersection of Boardwalk/Landings/Post Office should be considered as a
single -lane roundabout. The intersection has been problematic since it was constructed and
continues to worsen. A traffic signal is not an option at this location. Does not apply to this
project.
Department: Transportation Planning
Topic: General
Number: 61
[7/5/06] No issues or comments. OK
Department: Stormwater-Water-Wastewater
Issue Contact: David Averill
Created: 7/5/2006
Issue Contact: Wes Lamarque
Topic: Stormwater
Number: 55 Created: 7/4/2006
[7/4/06] Off -site flows along boardwalk need to be quantified to determine if these flows
would affect the building. Since the building is below the street, this is especially important.
Done
Number: 56 Created: 7/4/2006
[7/4/06] Please show and label the retaining wall with TOW and BOW elevations. Done
Number: 57 Created: 7/4/2006
[7/4/06] An off -site drainage easement may be required for the outfall storm sewer if this
area is off -site. It is not clear where the property boundary is. The acquisition of this
easement is in progress. Property line along south side of property coincides with southerly
most drainage boundary line. It can be identified more clearly on Sheet 4 of the Utility Plan
Set.
Number: 58 Created: 7/4/2006
[7/4/06] Please label the drainage pan and slope along the swale. The swale needs to
carry 1.33 times the 100-year flow. Done
Number: 75 Created: 7/7/2006
[7/7/06] A drainage easement is required for the limits of the detention pond. A 20-foot
drainage easement is also required for the outfall pipe. The acquisition of the drainage
easement for the outfall pipe is in progress.
Department: Stormwater-Water-Wastewater Issue Contact: Roger Buffington
Topic: Water/WW
Number: 59 Created: 7/5/2006
[7/5/06] Provide overall utility plan showing all water/sanitary sewer mains and services to
provide service to the site. Done
Department: Zoning Issue Contact: Gary Lopez
Topic: Zoning
Number: 2 Created: 6/27/2006
[6/27/06] Indicate bldg. dimensions and distance to property lines on site plans. Done.
Page 8
Department: Natural Resources Issue Contact: Doug Moore
Topic: General
Number: 60 Created: 7/5/2006
[7/5/06] No issues. OK
Department: PFA Issue Contact: Carle Dann
Topic: Fire
Number: 62 Created: 7/6/2006
[7/6/06] AUTOMATIC FIRE SPRINKLERS: The office/retail building shall be equipped with
an approved, automatic fire sprinkler system. Agreed.
Number: 63 Created: 7/6/2006
[7/6/06] FDC: The Fire Department Connection for the office/retail building sprinkler system
shall be mounted in a location approved by PFA, to ensure fire apparatus have adequate
access to the FDC. Agreed.
Number: 64 Created: 7/6/2006
[7/6106] KNOX BOX: A Knox Box is required to be mounted at the main entrance of any
building equipped with an automatic fire sprinkler system. Agreed.
Number: 65 Created: 7/6/2006
[7/6/06] FIRE LANE: A fire lane is required. This fire lane shall be visible by painting and
signage, and maintained unobstructed at all times. A fire lane plan shall be submitted for
approval prior to installation. The fire lane is required to be designated on the plat as an
Emergency Access Easement. The fire lane shall be a flat, hard, all-weather driving surface.
The owner shall maintain the required minimum width of 20 feet throughout the length of the
fire lane. Contact Carie Dann for specific fire lane location. OK
Number: 66 Created: 7/6/2006
[7/6/06] WATER SUPPLY: Every building must be within 300 feet of a fire hydrant that is
capable of flowing a minimum 1,500 gpm at 20 psi residual pressure. OK
Number, 67 Created: 7/6/2006
[7/6/06] ADDRESSING: In addition to the address kiosk, address numerals shall be posted
on each building, with numerals a minimum 6 inches high. The buildings shall be addressed
off Boardwalk, so the numerals must be mounted on the Boardwalk side of the buildings.
Agreed.
Number: 68 Created: 7/6/2006
[7/6/06] TURNING RADII: Minimum turning radii throughout the fire lane is 25 feet inside,
50 feet outside. OK
Department: Traffic Operations Issue Contact: Eric Bracke
Topic: Traffic
Number: 53 Created: 7/3/2006
[7/3/06] The Traffic Study is acceptable. I do have concerns with the n/ro and the slopes
coming into the site. I wait for the utility plans to review. OK
Page 7
Number 14 Created: 6/28/2006
[6/28/06] All attached sidewalk shall conform to current standard width of 8 feet. Show new
8 foot wide sidewalk transition from JFK and along Boardwalk. Done.
Number: 15 Created: 6/28/2006
[6/28/06] Show any proposed retaining walls on the site plan labeled with wall height. See
engineering plans.
Number: 16 Created: 6/28/2006
[6/28/06] ADA access ramps across the pork chop in the right turn lane access should line
up as straight as possible. You may need to cut though the pork chop to meet minimum
ADA slope requirements instead of ramping up and down over it. OK
Number: 17 Created: 6/28/2006
[6/28/06] Please use a bold line type for the proposed utility connections and the north
arrow. Fixed.
Topic: Technical Services
Number: 69 Created: 7/6/2006
[7/6/06] The Landscape Plan and Site Plan are not acceptable for scanning purposes.
Please see redlines for scanning quality related comments. Should be better.
Number: 70 Created: 7/6/2006
[7/6/06] Boundary and legal close. Please correct small typo in the legal description. Done
Number: 71 Created: 7/6/2006
[7/6/06] The Basis of Bearings statement does not match the Plat. Done.
Number: 72 Created: 7/6/2006
[7/6/06] Please provide documentation showing how JFK and Boardwalk were dedicated.
OK
Number: 73 Created: 7/6/2006
[7/6/06] This is a re -plat of a portion of Observatory Heights. Please show and state this
OK
Number: 74 Created: 7/6/2006
[7/6/06] Show additional ROW dedication along Boardwalk to back of proposed sidewalk
along entire frontage. This ROW dedication will cover and replace the existing utility
easement. No additional utility easement behind the ROW will be required. See utility plans
for clarification. OK
Department: Light & Power Issue Contact: Doug Martine
Topic: Electric Utility
Number: 1 Created: 6/20/2006
[6/20/061 The developer will need to coordinate power requirements, a location for a pad
type transformer, and electric development charges with Light & Power Engineering
(970)221-6700. Transformer pad location has been coordinated with City Staff.
Pal,c 6
Number: 21 Created: 6/28/2006
[6/28/06) A temporary construction easement, by separate document, will need to be
provided by the Post Office prior to permit issuance. Please provide a copy of the recorded
document for reference. OK
Topic: Rt Turn Lane Plan
Number: 28 Created: 6/28/2006
[6/28/061 Show and label limits of new proposed R.O.W. Done
Number: 29 Created: 6/28/2006
[6/28/06] Show new 8 foot wide attached sidewalk along Boardwalk. Done
Number: 30 Created: 6/28/2006
[6/28/06] The proposed street drainage and concrete pan flow line shown will not be
approved. All street drainage from Boardwalk shall be conveyed to the gutter and a drain
inlet installed near the access. See redline comments. Provide flow line elevations and new
typical cross section. Provide a detail for the inlet. Done
Number: 31 Created: 6/28/2006
[6/28/06] The right out egress "pork chop" should be skewed more to deter anyone from
trying to make a left turn onto Boardwalk, per the City Traffic operations engineer. Done
Number: 32 Created: 6/28/2006
[6/28/061 ADA ramps across the pork chop should line up better with the corner ramps.
Show more street design elevations (flow line, top of curb etc... ) on the plan. Some
additional detail has been added to plans, additional detail will be added to Site Layout Plan
which is currently in progress.
Number: 33 Created: 6/28/2006
[6/28/061 Add the City standard street cut note, attached, to the plan sheet. Done
Topic: Site Plan
Number: 10 Created: 6/2812006
[6/28/06] Standard parking stall size is 9 x 19 feet. Please dimension all drive isles. We
have 9' x 17' stalls with a 6' walk on the north side and landscape to the south.
Number: 11 Created: 6/28/2006
[6/28/061 Due to the addition of the right turn lane and relocation of the sidewalk, a right-of-
way dedication will be required along Boardwalk such that all of the sidewalk is within right-
of-way. Unless the utility providers object, all utilities along Boardwalk will then also be within
right-of-way, and no 8 foot utility easement will be needed behind the R.O.W. OK
Number: 12 Created: 6/28/2006
16/28/06] Label proposed R.O.W. on the Site Plan and provide dimension from centerline of
Boardwalk. Done.
Number: 13 Created: 6/28/2006
[6/28/06] All intersections and drive approaches must me A.D.A. access requirements.
Show ramps where needed. All new walks will meet these requirements and all existing
walks already meet them.
Peec
Topic: Grading & Drainage Plan
Number: 22 Created: 6/28/2006
[6/28/061 Show and label the limits of grading including within the R.O.W. and on Post
Office site. Done
Number: 23 Created: 6/28/2006
[6/28/063 All proposed retaining walls need to be shown on the Grading Plan. Any walls
over 30 inches in height must be labeled — Under Separate Permit By Building Department.
Please provide adequate number of wall elevations, top and bottom. Show drainage behind
the walls. Done
Number: 24 Created: 6/28/2006
16/28/06] Proposed connection to the existing 5 foot Type R curb inlet on the Post Office
site will need a drainage easement dedication. Please show this drainage easement on the
plat. This easement will be by separate instrument
Number: 25 Created: 6/28/2006
[6/28/06] Street grading and drainage for the right turn lane on Boardwalk will not be
approved as shown. All drainage shall be conveyed to the curb & gutter at a 2 percent cross
slope to match the existing road section. No outfall gutter or concrete pan shall be used to
convey the street drainage east past the access. Street drainage will need to directed to an
inlet near the access. See redline comments. No street drainage shall be directed into the
access of the site. A high point elevation must be shown at the ingress/egress on
Boardwalk. Done
Number: 26 Created: 6/28/2006
[6/28/061 Please show the water and sanitary sewer service connections on the Grading
Plan for reference. Done
Number: 27 Created: 6/28/2006
[6/28/06] Show all attached sidewalk as 8 feet wide. Transition from 8 to 6 feet wide on
JFK. Done
Topic: Plat
Number: 18 Created: 6/28/2006
[6/28/061 Please make sure all text fits within the border on the cover sheet. Done
Number: 19 Created: 6/28/2006
[6/28/061 Dedication of R.O.W. along Boardwalk should extend to back of sidewalk. Unless
utilities object, no additional utility easement will be required behind the new R.O.W.. Please
show dimension of new R.O.W. from centerline on Boardwalk. Done
Number: 20 Created: 6/28/2006
[6/28106] A reciprocal, shared access easement will be needed on the Post Office property.
Please dedicate this easement on the plat. OK
Pagc 4
a car or cars stopped to read the menu board could block cars wanting to exit the lane on
the north side of the building. The menu board was moved back one car to alleviate this
problem.
Number: 43 Created: 6/30/2006
[6/30/061 Based on the Site Plan layout, service access to the businesses, especially in the
larger Office/Retail/Restaurant building, could be difficult. This is a tight site and will have
to be serviced off hours from the main drive.
Number: 44 Created: 6/30/2006
[6/30/061 Is the crosswalk from the small, drive -up building to the larger building going to be
an enhanced pedestrian crossing, or could it be? It is in an awkward location relative to the
potential vehicular movement and crossovers. This is a raised walk so the cars have to
cross slowly. There will also be signage to warn of pedestrian crossing.
Department: Engineering Issue Contact: Randy Maizland
Topic: Cover Sheet
Number: 5 Created: 6/28/2006
[6/28/06] Provide month and year under title, correct spelling/grammar in title. Label Vicinity
Map, Vicinity Map should be at a larger scale to show location with respect to larger City
arterial streets adjacent. Done
Number: 6 Created: 6/28/2006
[6/28/061 Bench mark data and basis of bearings shall be shown on the cover sheet. Done
Number: 7 Created: 6/28/2006
[6/28/06] Revise the Index and City signature block per the redline comments. Provide a
reference to the Geotechnical Engineer and report submitted. Provide standard engineers
statement attached to redlines on cover sheet. Done
Number: 8 Created: 6/28/2006
[6/28/061 No standard General Notes sheet was provided with this submittal. Please include
the general notes (Sheet 2) with your next submittal for review. Done
Topic: General Comments
Number: 34 Created: 6/28/2006
(6/28/061 Please complete the attached Development Agreement Information Sheet with
your next submittal. A Draft Development Agreement will be prepared with your next round
of review. Did not find this sheet.
Number: 35
none
Created: 6/28/2006
Topic: General Notes
Number: 9 Created: 6/28/2006
[6/28/06] No City General Notes were provided with this plan set submittal. Please include
with your next round of review. Done
Page
Number: 45 Created: 6/30/2006
[6/30/06] There should be a detail of the trash enclosure on the plans, possibly on the Site
Plan or Building Elevations Plan. Site Landscape Details Sheet #3
Number: 46 Created: 6/30/2006
[6/30/06] The existing & proposed utilities should be on the Landscape Plan but do not have
to be and could be eliminated from the Site Plan, which would "clean it up" a bit. Fixed.
Topic: General Notes
Number: 36 Created: 6/30/2006
[6/30106] The General Notes as shown on Sheet 1 of 2 of the Landscape Plan must be on
the Site Plan. Done.
Topic: Landscape Plan
Number: 48 Created: 6/30/2006
[6/30/06] There are several discrepancies between the Landscape Plan and the Site Plan.
Fixed.
Number: 50 Created: 7/3/2006
[7/3/06] There are several areas on the Landscape Plan that need additional shrub
plantings to satisfy the requirement to screen parking & vehicular use areas, per Section
3.2.1(E)(4) of the Land Use Code. Please see the red -lined plan. Added as requested.
Number: 52 Created: 7/3/2006
[7/3/06] Two more Linden trees are needed as street trees along both JFK Parkway and
Boardwalk Drive. Please see red -lined Landscape Plan for locations. Added one on JFK.
Boardwalk tree is not on adjacent to our property.
Topic: Lighting Plan
Number: 51 Created: 7/3/2006
[7/3106] There are a couple of spots on the Lighting/Photometric Plan that are right on or
just over the allowable level of 10 foot-candles. Why would the 'Type B" light over the entry
to the larger building create that much light? Is it the fluorescent source that makes it that
high and could another type fixture be used? Just to reiterate, Section 3.2.4(D)(3) states that
"Light sources shall be concealed and full shielded and shall feature sharp cut-off capability
so as to minimize up -light, spill -light, glare and unnecessary diffusion on adjacent property".
Also, Section 3.2.4(D)(7) states that "Maximum on -site lighting levels shall not exceed ten
(10) foot-candles, except for loading and unloading platforms where the maximum fighting
level shall be twenty (20) foot-candles". Fixed.
Topic: Site Plan
Number: 37 Created: 6/30/2006
[6/30/06] The Site Plan must identify all proposed uses in the buildings. The "Drive -Up
Building Area" must be identified as Drive-Thru Coffee, as shown on the Landscape Plan.
The Site Plan must also identify the larger building as containing a restaurant (if truly
intended), as shown on the Landscape Plan. Done.
Number: 42 Created: 6/30/2006
[6/30/061 There will be awkward vehicular movement and crossover between the 2 drive-
thru lanes for the coffee shop. At the west end of the building there is also the possibility that
Page 2
STAFF PROJECT REVIEW
C i tv of Fort Collin,
EDWARD G ZDENEK Date: 07/07/2006
ZTI GROUP/ARCHITECTURE
631 W. MULBERRY
FORT COLLINS, CO 80521
Staff has reviewed your submittal for FOX POINTE PLAZA PDP - TYPE II, and we offer the
following comments:
ISSUES:
Department: Current Planning Issue Contact: Steve Olt
Topic: Building Elevations
Number: 47 Created: 6/30/2006
[6/30/06] The drive-thru coffee building is very nice looking. However, the elevations are
quite small and some of the information is very difficult to read. Could these elevations be
enlarged somewhat? What do the numbers in the squares refer to on all 4 elevations? There
is no legend on the Building Elevations Plan. Done
Number: 49 Created: 6/30/2006
[6/30/061 The larger, 2-story Office/Retail/Restaurant (maybe) building is very nice looking.
However, the west elevation does not appear to satisfy the standard set forth in Section
3.5.3(C)(1) of the Land Use Code. This section states that the horizontal mass shall not
exceed a height -width ratio of 1:3 without substantial variation in massing that includes a
change in height and a projecting or recessed element. This elevation is 120' long and is
28.5' high, for a ratio of approximately 1:4. Therefore, there should be some element of
height change on this elevation. This elevation features a curved face that projects from
the rest of the building approx. 10' which we feel meets this standard.
Topic: General Comments
Number: 38 Created: 6/30/2006
16/30/06] The proposed building sizes are inconsistent between the Site Plan and the
Landscape Plan. The Site Plan shows the small building to be 325 square feet and the
Landscape Plan shows the same building to be 400 square feet. The Site Plan shows the
larger building to be 11,744 square feet and the Landscape Plan shows the same building to
be 11,500 square feet. Please reconcile this discrepancy. Fixed.
Number: 39 Created. 6/30/2006
[6/30/061 It is very difficult to follow the existing and proposed sidewalk locations on both the
Site and Landscape Plans. Added hatch to new sidewalks.
Number: 40
16/30/06] There is overlapping information on
labels difficult to read or totally illegible. Fixed
Created: 6/30/2006
some of the plans that make some notes and
Number: 41 Created: 6/30/2006
[6/30/06] The proposed amount of parking for this development plan (a convenience
shopping center) is 39 spaces, which is within the allowable 5 spaces per 1,000 square feet
of total leasable floor area, being somewhere between 11,825 square feet & 12,144 square
feet (depending on reconciling the square footages on the Site & Landscape Plans). OK