6a COMMENT SHEET
City of Fort Collins
Current Planning
DATE: August 23, 2006 R E C E I V E D
SEP 15 2006
TO: Park Planning CURRENT PLANNING
PROJECT PLANNER: Ted Shepard
#5-05B ARCADIA PDP — TYPE II AND FINAL PLANS
Please return all comments to the project planner no later than the staff
review meeting:
September 20, 2006
Note - Please identify your redlines for future reference
No Problems
Problems or Concerns (see below, attached, or DMS)
///1¢ //%J �//. w L� ✓IC�ecL1 Gc feGT/�� �4UG-d (0sf sX&,,�s ,,es� m
yG ya rn O�nrC /.� r
�eGei„,¢ pYlir;c� s7�uym�ue,�=er and 2.a.te�e,�,�/
V
%/!6
Name (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
X Plat X Site _Drainage Report _Other
XUtility _Redline Utility _Landscape
Ted Shepard
Planning Department, City of Ft. Collins
P.O. Box 580
Ft. Collins, Co. 80522
December 30, 2005
Below is the U.S. Postal Service's referral response for project: #5-05A Arcadia PDP,
Modification of Standard
d
Referral Response
Mail Service: Centralized delivery using of a minimum of 4 centralized box units
(3 industry type III and 1 type II ) is required. Revise plan to show the required CBU
locations as approved by the U.S. Postal Service. In all cases the CBUs must be
located in the public right of way or a designated easement. Be advised the
responsibility of purchase and maintaining the CBUs with the concrete pads is that of
the owner/developer/builder/HOA. Prior to occupancy within the development
approved mail receptacles will be in place. Delivery Agreement will be in place prior
to any delivery of mail. Contact Bonnie Ham Growth Coordinator, U.S. Postal
Service 301 E. Boardwalk, Ft. Collins, Co., phone # 970-225-4130, cell 4 970-214-
3668, fax # 970-225-4139.
Thank you,
Bonnie Ham
USPS Ft. Collins
FINAL PLAN
COMMENT SHEET
Citv of Fort Collins
Current Planning
DATE: August 23, 2006
RECE11lED
TO: Post Office AUG 3 t;
2006
PROJECT PLANNER: Ted Shepard 61111RENT P(,g1Y1y1NG
#5-05B ARCADIA PDP — TYPE II AND FINAL PLANS
Please return all comments to the project planner no later than the staff
review meeting:
September 20, 2006
Note - Please identify your redlines for future reference
❑ No Problems
Problems or concerns (see below, attached, or DMS)
of e
.Qreoil8 Cobrdlnotor•8ennlo Xnm;
Y8F8 $91 a. foordwolk
ni .. , n 1/w ._'In Fort Comes CO 88814.9/90
Name (please print)
C CK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Site _Drainage Report _Other
_Utility _Redline Utility _Landscape City of Fort Collins
Ted
I have drawn a proposed tree planting for the open space pasture. The applicant's species choices
and locations were not appropriate for this type of area. I suggest the applicant incorporate my
ideas or call me to discuss this area.
Tim
FINAL PLAN
COMMENT SHEET
Current Planning
DATE: August 23, 2006
TO: Forestry
PROJECT PLANNER: Ted Shepard
#5-05B ARCADIA PDP — TYPE II AND FINAL PLANS
Please return all comments to the project planner no later than the staff
review meeting:
September 20, 2006
Note - Please identify your redlines for future reference
❑ No Problems
[Problems or Concerns (see below, attached, or DMS)
See
Name (please print)
C `(,4-,f q
co 4 Q,L'C a. -I
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat Site Drain e ort Other
_Utility _Redline Utility Lan e
Department: Stormwater-Water-Wastewater Issue Contact: Roger Buffington
Topic: WaterlWatewater
Number: 106 Created: 9/21/2006
[9/21/06] Swivel tees are required at fire hydrant locations.
Number: 107 Created: 9/21/2006
[9/21/06] Substitute a temporary fire hydrant for the blow -off at the west end of the 12-inch
water main.
Number: 108 Created: 9/21/2006
[9/21/06] Revise the valving on the water mains as noted on the redlined plans.
Number: 109 Created: 9/21/2006
[9/21/06] Add steel casing pipe on the water main and sanitary sewer crossings under the 2'
x 3' RBC.
Number: 110 Created: 9/21/2006
[9/21/06] At point of connection with existing 12-inch sewer, match crowns or 3/4 points on
the existing and proposed sewers.
Number: 111 Created: 9/21/2006
[9/21/06) Due to the shallow san sewer depth, we will allow a 0.1 ft drop for straight through
MH's.
Number: 112 Created: 9/21/2006
[9/21/06] Add the shallow sanitary sewer manhole standard detail.
Department: Zoning Issue Contact: Gary Lopez
Topic: Zoning
Number: 80 Created: 9/7/2006
[917/06] No issues
Please return all of your redlined plans when you re -submit.
Should you have any questions regarding these issues or any other issues related to this
project, please feel free to call me at (970) 221-6750.
Sincerely, c �—
Ted Shepard
Chief Planner
Page 7
[9/19/06] The boring of the water line under the railroad track will necessitate a license
agreement with the railroad company.
The agreement that was submitted had the private owners as the licensee, but since the
City will own maintain and operate that line, the license should have the City as the
beneficiary of that license agreement.
The crossing of that water line with the existing sanitary line should be potholed now during
the design phase.
Topic: Water Line Lowering
Number: 102 Created: 9/19/2006
[9/19/06] Please fill out the table specifying all the water line lowerings proposed.
Topic: Water Plans
Number: 101 Created: 9/19/2006
[9/19/06] Please identify clearly City of Fort Collins lines and Northen Colorado Water district
line on the plans. The district line may have some conflict with the proposed trees in the
Willox Lane right of way.
Topic: Water Quality Outlet Detail
Number: 104 Created: 9/20/2006
[9/20/06] Please use the City of Fort Collins outlet detail for your water quality pond. I can
email you that detail, if you don't have an electronic version. That detail should be modified
to reflect the fact that this pond is a wet pond.
Topic: Water/Wastewater- Off -site Easement
Number: 31 Created: 1 /17/2006
[9/19/06] No easement dedication has been submitted.
[5/2/06] Easement should be dedicated to the City.
[1/17/06] A letter of intent for the proposed off -site easement for the sewer line is required
prior to hearing. At final that easment needs to be dedicated to the City. Please also
delineate the existing sanitary line easement on the mobile home property.
Topic: Water/Watewater
Number: 66 Created: 5/2/2006
[9/19/06]
[5/2/06] City standards call for water lines to be ductile. iron with polywrap. Please adjust
Several areas do not show crossings of water lines and storm lines across sewer lines.
Sanitary line a t times shallower than 3.5 feet from top of pipe, please provide insulation in
these instances. Maybe able to gain some depth by using only .1 feet of drop across
manholes on straight sections of pipe.
Stub out sewer service for existing house out of the street.
Note all locations of water lowerings, call them out on plan and profiles.
Provide better detail for 12" water crossing under the railroad tracks. Show steel casing on
plan view.
Page 6
The residents to the south apparently own water rights that come off the lateral that is now
being piped. How will these owners be able to get their water delivered ?
Topic: Landscape Plan
Number: 94 Created: 9/19/2006
[9/19/06] Please provide special plantings or wetland grasses for the open area where
swales from this subdivision drain onto.
The area where the trickle pans transition to natural swale should be reinforced with a
geotextile material.
Please show water and sanitary sewer lines on landscape plans in order for us to be able to
check for any potential conflicts.
Topic: Maintenance
Number: 95 Created: 9/19/2006
[9/19/06] Has there been an agreement with the Parks department regarding the
maintenance of the pond ?
Topic: Sewer crossings
Number: 99 Created: 9/19/2006
[9/19/06] Line 4 B crosses the storm line with only 0.67 feet of clearance. Does that
account for encasing and pipe wall thickness ? We may need to work on a special detail for
that crossing.
Topic: Sewer Line on Tract B
Number: 98 Created: 9/19/2006
[9/19/06] Please remove the manhole shown in the open space, and revise pipe lengths to
minimize length of run between the streets, even if that length exceeds 400 feet.
Topic: Stormwater- Erosion Control
Number: 81 Created: 9/18/2006
[9/18/06]
Your plan should have a note (which is also reflected in the schedule) that the ponds will be
excavated as the first step in ov6dot grading. That way they can be utilized as sediment
traps (which is what the report calls for) immediately. The plan should also indicate the
ponds as sediment traps, which it currently does not.
The first sentence in the last paragraph of section 6.1 on page 11 of the report doesn't make
sense. Please correct. Also in the same paragraph, the sediment traps must remain until
completion of the development.
I did not find any PS, EFF, or surety calculations.
Topic: Trail Crossing
Number: 96 Created: 9/19/2006
[9/19/06] Please provide a low flow crossing for the area where the swale drains across the
trail. Pipe only needs to carry two year flow.
Topic: Water Line Boring
Number: 100 Created: 9/19/2006
Page 5
3. Plat is missing a lot of dimensional info.
4. Based upon configuration, the plat will need 5 street names.
Department: Light & Power Issue Contact: Monica Moore
Topic: General
Number: 8 Created: 1 /10/2006
[8/30/06] Streetlight layout is still NOT shown on landscape plans. Street tress WILL need
to be adjusted to accommodate streetlighting.
[5/1/06]
[1/10/06] Street trees must maintain clearances from streetlights. 40-feet separation from
shade trees and 15-feet separation from ornamental trees. Contact Light and Power
Engineering to initiate design of the streetlight layout
Topic: Landscape Plan
Number: 47 Created: 5/1 /2006
[8/30/06]
[5/1/06] Landscape plan needs to show proposed streetlight placement and vault placement
in relationship to the planned placement of street trees.
Department: Natural Resources Issue Contact: Doug Moore
Topic: General
Number: 79 Created: 9/4/2006
[9/4/06] No remaining issues.
Department: PFA Issue Contact: Carle Dann
Topic: fire
Number: 103 Created: 9/20/2006
[9/20/06] No additional comments or concerns at -this time.
Department: Stormwater-Water-Wastewater Issue Contact: Basil Harridan
Topic: Detention on City Parks property.
Number: 93 Created: 9/19/2006
[9/19/06) Agreement with the Parks Department should be provided regarding the proposed
work on the parks property.
Topic: Grading Plan
Number: 97 Created: 9/19/2006
[9/19/06] Please provide FF elevation and detailed spot elevations on the grading plans.
How will the proposed retaining wall be built along the property line ? If construction would
affect neighboring property to the north and east, then a construction easement may be
needed.
Please add notes that no grading shall be done on neighboring properties.
Topic: Irrigation Line
Number: 77 Created: 5/5/2006
[9/19/06]
[5/5/06] Please show irrigation line that will serve the park property on the plans.
Page 4
[5/2/06] Since the easment has been dedicated already, no letter of intent is necessary, but
we will need the easement to come through the city dedication process. TDRF fees and
filing fees will apply.
[1/16/06] Provide a letter of intent indicating the willingness of the mobile home park to
grant the off -site utility easement shown. .
Topic: Streets
Number: 54 Created: 5/2/2006
[9/19/06] Please clearly indicate the approx. limits of street cuts for the two water service
connections on Willox. Add the standard street cut note provided with the redlines.
[5/2/06] The street cut limits shown on Willox may not be realistic. Cuts for service
connections are not shown, and with the milling indicated, it may just be required to cut the
street to the existing edge of pavement.
Number: 62 Created: 5/2/2006
[9/19/061 Cross sections for ultimate design only have been submitted. Please include
interim cross sections with the next submittal. The cross section provided do not show
adequate information relating to cross slope, gutter flow line elevations and how proposed
grades will tie back into existing ground. See redline comments for clarification.
[5/2/06] At final compliance, we will require cross sections to be shown at 50' (min) intervals
along Willox Ln. including both interim and ultimate improvements, as well as existing
conditions.
Number: 63 Created: 5/2/2006
[9/19/06] Additional information is still needed on the plans to indicate interim dimensions
and existing versus proposed pavement limits. Please see the redline comments for
clarification.
[5/2/06] (Public Hearing Comment) Please provide additional detail on the Willox design.
Label existing and proposed ROW limits on the plan view, provide interim and ultimate
dimensions on the standard cross-section. Please note that any interim improvements are
not eligible for reimbursement unless they are able to be used as part of the final cross-
section of the street. Please indicate existing limits of pavement, and how much you are
widening out each side.
Number: 72 Created: 5/3/2006
[9/19/06] Existing and proposed grades on the ultimate Willox design are different at the
R&R crossing, mainly at the flowlines. Please address how the railroad crossing will be
accomodated for with these proposed grade changes.
[5/3/06] It appears that you are regrading Willox Ln. at the railroad crossing. Please
indicate the tracks on your profile sheet, and indicate if you plan on raising the tracks.
Topic: Technical Services
Number: 42 Created: 1 /18/2006
[9/19/06] Boundary and legal close but do not match. Acerage in legal is incorrect. Note 1
on Plat cover sheet describes private access. There are only public access easements
being shown on the Plat. Where is the private access ? Why is an outlot A being created
rather than a tract lot ? Please show how Willox Lane was dedicated. See redlines for
additional comments and clarification.
[1/18/06] Technical Services Comments:
1. Boundary Closes, Legal doesn't match the plat.
2. Title & Dedication do not match.
Page 3
[9/19/06] The stormwater surface drainage is being conveyed over the pedestrian access
path leading to Soft Gold Park. This may create a hazardous condition. during heavy flows or
freezing. Please provide a pipe under the path for water to cross. Clearly indicate this on the
plan with a detail if necessary.
Number: 86 Created: 9/19/2006
[9119/06] Clearly label the limits of concrete paving on Sweet Corn Drive as ECR to BC and
provide an expansion joint layout detail. You may use the CDOT m-412-1 or equivelant.
Revise construction notes accordingly to reference the detail.
Number: 87 Created: 9/19/2006
[9/19/06] Make sure that all plan sheets showing street layouts have the street names
shown as well as any intersecting street names TYP. See redline comments for clarification.
Number: 88 Created: 9/19/2006
[9/19/06] Show the approx. limits of street cuts for the 12 inch water line installation and
service connections on sheet 23. Add the City standard street cut note.
Number: 89 Created: 9/19/2006
[9/19/06] Please dimension all streets with ROW, sidewalk, parkway and FL to FL widths.
Also label any utility easements behind the ROW. See redlines for clarification.
Number: 90 Created: 9/19/2006
[9/19/06] Refer to Willox Lane interim design. Show all dimensions for proposed interim
paving and label the ROW. Clearly label on the plans the existing and proposed edge of
pavement. Show dimensions on the interim pavement asphalt cross section. See redlines
for additional comments and clarification.
Number: 91 Created: 9/19/2006
[9/19/06] No interim cross section have been provided. Please add standard cross sections
for every 50 feet with the next submittal.
Number: 92 Created: 9/19/2006
[9/19/06] Refer to Willox Lane ultimate design. A low point is proposed with a vertical curve
at STA 4+62. Please address how the drainage will be collected and conveyed from the
street at this location. Same condition at STA 25+96, how will the drainage work ?
Department: Engineering Issue Contact: Dan DeLaughter
Topic: Grading Plan
Number: 19 Created: 1 /16/2006
[9/19/06] Please show the retaining wall foundation with respect to the property line in the
trickle pan/ret. Wall section detail provided.
[1/16/061 For the 2 retaining walls shown on the eastern part of the site, label the heights
and provide spot elevations for top and bottom. Provide construction details if walls are
higher than 2'. The structures, including footings may not cross onto adjacent property
(without obtaining an offsite easement) or into utility easements.
Topic: Plat
Number: 13 Created: 1 /16/2006
[9/19/06] No easement has been submitted to date.
Page 2
STAFF PROJECT REVIEW
City of Fort Collins
MICHAEL CHALONA Date: 09/27/2006
LAND IMAGES, INC
1136 E. STUART #2040
FORT COLLINS, CO 80525
Staff has reviewed your submittal for ARCADIA PDP - TYPE II AND FINAL PLANS, and we
offer the following comments:
ISSUES:
Department: Engineering Issue Contact: Dan DeLaughter
Topic: Details
Number: 50 Created: 5/2/2006
[9/19/06] Need to show proposed retaining wall foundation with respect to the property line
in the trickle pan/ret. Wall section -detail
[5/2/06] Please provide structural details for the retaining walls along the property lines. We
need to be sure they can be built without obtaining offsite easements.
Topic: General
Number: 38 Created: 1 /18/2006
[9/19/06]
[1/18/06] Transportation Development Review Fees will apply for all future submittals,
including Final Compliance, Minor or Major Amendments, and ROW and easement
vacations and dedications not done with the plat. Please contact the Engineering
Development Review Office for a copy of the fee structure.
Number:57 Created:5/2/2006 ,
[9/19/06] Please submit evidence of permision to bore within the railroad ROW.
[5/2/06] 1 have received a copy of the permit to be on railroad ROW for survey work, but will
an additional permit be required in order to complete the boring work? Please coordinate
with Union Pacific.
Department: Engineering Issue Contact: Randy Maizland
Topic: General - Utility Plans
Number: 82 Created: 9/19/2006
[9/19/06] Please add the geotechnical engineer name and contact information to the cover
sheet with a reference to the latest soils report.
Number: 83 Created: 9/19/2006
[9/19/06] Refer to sheet 2, general note 48 D. Please provide a letter from Park Planning
granting approval to drain the Arcadia site into the existing pond located in the park. The
letter from Parks should also grant permission to regrade the existing pond as shown on the
plans. Clearly indicate on the plans who will be grading within the park site.
Number: 84 Created: 9/19/2006
[9/19/06] Clearly label the public access easement on the Plat. See redlines for clarification.
Number: 85
Created: 9/19/2006