HomeMy WebLinkAboutODELL BREWING CO. EXPANSION - MAJOR AMEND./REPLAT - 21-08 - CORRESPONDENCE - TRAFFIC STUDY (5)Action:- Following are actions which seem appropriate at this point:
Northern Engineering develop accurate base plan for these two
residences and update the base map to be accurate so alignments of driveways
can be evaluated
BHA lay out the access drive and forwards to Northern.
City and Odells meet to review implications and hammer out
specifics.
Prepare easements These can be identified and dedicated on the
plat, unless they are off -site.
Prepare Development Agreement. This will be started after the
project goes to hearing.
Thoughts?
If you are interested in pursuing a road classificationchange, I suggest
that you thoroughly pursue that before finalizing the layout and taking this
project to hearing, since that could impact the need for the improvements
along the frontage of the neighboring properties.
Bruce A. Hendee
BHA Design, Inc.
1603 Oakridge Drive
Fort Collins, CO. 80525
P- 970. 223. 7577
F- 970. 223. 1827
C- 970. 227. 0834
www.bhadesion.com <hftp://www.bhadesion.com/>
From: David Kasprzak(mailto:dkasprzak(Dbhadesign.coml
Sent: Friday, September 12, 2008 9:59 AM
To: bhendee(cDbhadesign.com
Subject: Approved access drive option
6. The right-of-way is of adequate width along Odells and the 2
properties to the west to accommodate the north half of the 4 lane roadway
section and have approximately 22 feet to spare. So provided that the design
accommodates the sidewalk and the shared driveway within the right-of-way
there should be little to no impact on the adjacent properties other than
now needing to use the shared driveway to access the property.
7. There are still unanswered questions regarding how cutting off
direct access on to Lincoln Avenue may affect the neighbors. There are two
property owners between the Odell site and 3rd Street; Arne Sargenfri and
Alfred Baca. The property closest to Odells is owned by Alfred Baca. Once
access is cut off, he will have to use the Odell access drive to enter and
exit his property or drive over his neighbors property to get to third
street. Odells can grant an easement as part of the plat.
8. Correct.
9. How are impacts conveyed to the property owners?
10. A letter needs to be sent to the adjacent property owners by Odells
identifying what is proposed and what the changes mean. A copy of the
letter(s) being sent need to be provided to the City. I would recommend
that these letters are sent to the neighbors prior to the hearing, so that
they would have a chance to express any concerns prior to or at the public
hearing.
11. What is the timing of sidewalk installation? Does it need to be
constructed now or sometime in the future in which case Odells pay
cash -in -lieu to the city for future construction?
12. The sidewalk, curb and shared driveway need to be built at the time
that the western access to Odells is constructed. A condition Iof having
this access point was that with this access point that the accesses in this
area would be consolidated, so this needs to be done when the access point
is taken.
13. If Matt Delich completes a study of the classification of Lincoln
Avenue and finds a 3 lane alternative suitable, will this affect location of
sidewalk? Would it be best to conduct this study and then decide on the
final location of sidewalk?
14. A reclassification of this roadway to a minor arterial (3 lane) could
affect the sidewalk location. It would allow for the sidewalk to be moved
further south, or the sidewalk could remain in the same location and a
bigger parkway provided. It would be best to conduct this study and if the
road classification can be changed to get this change processed thru City
Council and amend the Master Street Plan prior to designing the frontage
improvements, since the location of the curb and gutter will change if the
road is reclassified. That way a redesign of the frontage improvements will
not need to be provided before approval. It is also my understanding that
if the road classification change would be accepted and the Master Street
Plan amended than the western access could be provided without having to
consolidate the accesses.
Sheri
>>> "Bruce Hendee" <bhendee(cDbhadesign.com> 9/12/2008 1:04 PM >>>
Sheri, Jeff,
I wanted to get back with your regarding our discussions on the Odell
property access on to Lincoln Avenue.
In Concept the Odells have agreed with the solution proposed on the attached
drawing. Our understanding is that you have agreed conceptually to this
alternative as well. There are issues to be addressed that need
clarification before Odell's feel they can finalize their full commitment.
To reaffirm this to both parties I wanted to review the specifics below
1. Odell Brewing Company will design and construct a stubbed out
driveway access for adjoining residential properties to the west from their
proposed new access drive on the west side of the brewery expansion. The
access drive will provide an alternative access for the adjoining
neighborhood property to Lincoln Avenue.
2. Correct
3. Odell Brewing Company will design and pay for an extension of
sidewalk. Sheri asked for some landscaping associated with this sidewalk.
There are questions to be resolved with the landscape related to
responsibility for irrigation and maintenance. There are issues associated
with the timing of installation and responsibility for construction. These
issues need to be clarified prior to making a commitment.
4. In addition to the sidewalk a curb will need to be installed to
control the traffic movements, without the curb the neighbors might still
drive across the sidewalk to access the lots. As to whether there is
landscaping, there needs to be something to separate the driveway from the
sidewalk. Landscaping is certainly an option that would work. There may
also be other options that can provide for a distinction between the
sidewalk and the driveway. The party installing the improvements, including
the landscaping, is responsible for providing 2 years of maintenance upon
completion and acceptance of the improvements. In accordance with the City
Code the maintenance of the sidewalk is the adjacent property owners
responsibility, and the City is responsible for trimming and replacement of
any trees within the row after the 2 year maintenance period. And typically
it is the adjacent property owner that maintains any parkway landscaping and
grass. As for the timing of the construction, the improvements will need to
be installed at such time as the west driveway for Odells is installed.
5. The design solution must fit within the existing ROW which with our
current knowledge is wide enough to accommodate a 4 lane arterial but is
unclear whether there will be impacts on adjoining properties.
Sheri is out until October 13 so I have not been able to coordinate this
through her.
Thanks for your help.
Bruce A. Hendee
BHA Design, Inc.
1603 Oakridge Drive
Fort Collins, CO. 80525
P- 970. 223. 7577
F- 970. 223. 1827
C- 970. 227. 0834
www.bhadesi-n.com
From: Sheri Langenberger fmailto:slangenberger(..fcgov.coml
Sent: Friday, September 19, 2008 9:56 AM
To: Bruce Hendee; Jeff Scheick
Cc: David Kasprzak; Denise Weston; Helen Migchelbrink; Joe Olson; Kathleen
Bracke; Susan Joy; Ted Shepard; Matt Delich (Matt Delich); Nick Haws;
Brendan McGivney
Subject: Re: FW:Access Drive on Lincln Avenue for Odell Brewing Company
Bruce,
I have provided input, conformation and additional information on the items
and questions you had sent. Sorry for the few day delay, I wanted to run
the response by the rest of the staff to verify I was correct in the
responses before replying. Please see the fuchsia text below.
From: Denise Weston
4 1 o�L Z `s
To: Bruce Hendee; Kathleen Bracke
Date: 10/3/2008 1:56:36 PM
Subject: Re: FW: FW:Access Drive on Lincoln Avenue for Odell Brewing Company- Master
Street Plan Amendment
Bruce,
In order to provide some clarification for all, I have provided an outline of the process to modify the Master
Street Plan. This process could be expected to take at least 6-8 weeks. This is dependent on the
modeling analysis required and the coordination with the Transportation Board and the City Council.
Process Outline:
Receipt and review of a traffic study analyzing the proposed modification submitted by the developer.
Traffic modeling of the two arterial alternatives (in addition to the traffic study above).
Coordination with land owners along Lincoln Avenue.
Propose to and request support by the Transportation Board (monthly meeting).
Propose modification to the City Council.
I hope this helps. If there is anything else we can do to help coordinate your proposal prior to the
finalization of the MSP amendment, please let us know.
Thanks,
Denise Weston
Denise Weston
Senior Transportation Planner
City of Fort Collins
250 North Mason
PO Box 580
Fort Collins, CO 80522
(970)416-2643
>>> "Bruce Hendee" <bhendee@bhadesign.com> 9/29/2008 10:34 AM >>>
Kathleen, Denise,
I am continuing to try and resolve the discussion regarding the
classification of Lincoln Avenue. As you no doubt recall the classification
between 3 and 4 lanes has been a point of discussion which impacts future
plans for Odell Brewing Company and their proposed access. We currently have
Matt Delich conducting an analysis of the area to assist in making the
determination about the final configuration. He should be complete with the
analysis in about a week.
According to Sheri the next step after Matt's work is to amend the Master
Street Plan if appropriate. Making the assumption that 3 lanes would work,
I'd like to understand how long and the order of magnitude for this to
occur. If Matt's study finds this to be appropriate would this be initiated
by the City or would the developer be required to make this application?
What are the steps we need to pursue and how long will it take? Can we
expedite the process?