HomeMy WebLinkAboutODELL BREWING CO. EXPANSION - MAJOR AMEND./REPLAT - 21-08 - CORRESPONDENCE - (10)Department: Stormwater-Water-Wastewater Issue Contact: Wes Lamarque
Topic: Stormwater
Number: 16 Created: 8/15/2008
RESPONSE: VOLUME CALCULATIONS HAVE BEEN PROVIDED FOR POND B, BOTH
WITH AND WITHOUT THE INFILTRATION CONSIDERED. A STAGE -STORAGE TABLE
HAS ALSO BEEN PROVIDED.
[11/18/08] The pond sizing calculation still includes the infiltration as part of the release
rate. Please show how much volume is required with just the .23 cfs release rate. We can
than compare this required amount of volume with how much volume is being provided to
determine if the provided amount is adequate. Also please provide a stage -storage table to
show how much volume is being proposed.
[8/15/081 The release rate for the detention pond in basin B-1 includes the infiltration rate as
well as the orifice release rate for the sizing of the volume required. Discussions are
needed to determine if this will be allowed or if just the .29 cfs release rate from the outlet
structure can be used to size the volume required in the pond.
Number: 17 Created: 8/15/2008
RESPONSE: PER A TELEPHONE DISCUSSION WITH STORMWATER STAFF ON
4/07/09, THE EXTENSION OF AN UNDERDRAIN PIPE IS NOT NECESSARY.
111/18/08] Stormwater staff is still concerned with the western edge drainage. Please
provide an under -drain from the dry well to the bedding of the permeable pavers.
[8/15/08] Please clarify how the western edge of the property is to drain. A positive outfall
is needed, unless other approved mitigation techniques are used like the dry well.
Number: 30 Created: 11/18/2008
RESPONSE: THE TEXT AND CALCULATIONS ARE NOW CONSISTENT.
[11/18/08] The release rate stated in the text is not consistent with the calculations in the
report.
Number: 31 Created: 11/18/2008
RESPONSE: POND SIDE SLOPES DO NOT EXCEED 4:1 IN ANY LOCATION.
[11/18/08] The side slopes for the detention pond must be 4 to 1, not 3 to 1.
Number: 32 Created: 11 /19/2008
RESPONSE: THE DRAINAGE EASEMENT IS DESIGNATED TO BE DEDICATED TO
THE CITY OF FORT COLLINS.
[11/19/08] The drainage easement for the detention pond and the pervious pavement
needs to be dedicated to the City of Fort Collins.
Be sure and return all of your redlined plans when you re -submit.
If you have any questions regarding these issues or any other issues related to this project,
please feel free to call me at (970) 221-6750.
Sincerely:
Ted Shepard
Chief Planner
Pa�,,c 4
Number: 27 Created: 11/18/2008
RESPONSE: LINCOLN AVENUE IMPROVEMENTS CAN BE FOUND ON SHEETS R1-
R10. THE GOLF COURSE DRIVEWAY REALIGNMENT IS INCLUDED THEREIN.
[11/18/08] This project is ready to go to hearing provided that the ultimate design for Lincoln
improvements is submitted with Final Compliance and that Odell's brewery acknowledges
that the additional driveway cut is contingent upon the agreement of the golf course.
Number: 28 Created: 11/18/2008
RESPONSE: ACKNOWLEDGED. THE PREFERENCE IS THAT ANY COMMENTS CAN
BE RESOLVED WITHOUT A FULL-BLOWN PAPER RE -SUBMITTAL. IF POSSIBLE,
PDFs AND FOLLOW-UP CORRESPONDENCE CAN ADDRESS LINGERING
CONCERNS AND ALLOW THE NEXT SUBMITTAL TO GO TO MYLAR.
[11/18/08] Detailed comments to follow in Final Compliance.
Department: Light & Power Issue Contact: Alan Rutz
Topic: Light & Power
RESPONSE: ACKNOWLEDGED.
Number: 8 Created: 8/12/2008
(11/18/08]
(8/12/081 Normal site and development charges will apply to new development.
Department: Transportation Planning Issue Contact: Matt Wempe
Topic: General
RESPONSE: THE 4-LANE ARTERIAL SECTION WITH A CONTINUOUS 12' CENTER
TURN LANE IS SHOWN ON THE FINAL PLANS.
Number: 25 Created: 11/17/2008
[11/17/08] Per the memo dated November 11, 2008, Lincoln Avenue will remain a four -lane
arterial. Based on the traffic volumes, a 12-foot two-way left turn lane will be acceptable in
place of a median.
Number: 26 Created: 11 /17/2008
RESPONSE: THE REALIGNMENT OF THE LINK-N-GREENS DRIVEWAY IS INCLUDED
WITH THE LINCOLN AVENUE ROADWAY DRAWINGS.
[11/17/08] Per the letter from the City Traffic Engineer, Transportation staff will conditionally
support the variance request for a second access point on Lincoln Avenue. This support is
contingent upon the realignment of the golf course driveway to match the proposed western
access point.
Department: Stormwater-Water-Wastewater Issue Contact: Roger Buffington
Topic: Landscape plan
Number: 29 Created: 11/18/2008
RESPONSE: STREET TREES HAVE BEEN SHIFTED TO MAINTAIN 6-FEET OF
SEPARATION
[11/18/08] Provide a minimum of 6 feet of separation between water and sewer service
lines and trees on north side of Lincoln.
Paee 3
L
With that said, Traffic was not inclined to grant an additional access point to this project.
However, we discussed a few options that your clients may wish to explore.
The first option is to take all access off the existing drive and construct a drive around the
north side of the building within the proposed access easement that will connect to the new
parking lot.
The second is to close the existing driveway and take all access off the new driveway.
Traffic Engineering would consider this option provided that the new driveway does not
conflict with the existing driveway on the south side of Lincoln. If you choose to pursue this
option, please show the existing driveway on the south side of Lincoln and update the
variance request evaluating the separation distance and safety concerns between them in
addition to the separation distance between the new driveway and Third St. Traffic will
evaluate the new request and make a determination based on the new information.
The third option is to take access off Buckingham to the north. This would not trigger any
improvements to Buckingham itself and would only require an access easement through the
northern Odell property. While none of the options discussed here are listed in any
preferential order, this last option may be the better one for your clients in the long term.
With all access restricted to right in, right out along Lincoln, having a second point of access
to the north may be a good thing for Odell's overall circulation. It may also solve any
emergency access requirements PFA might have.
Speaking of PFA, please be sure to discuss emergency access requirements directly with
them. I do not know what those might be and can not speak for that department. PFA has
stated that they are fine with the access that is provided now and the new access on the
west is sufficient for accessing the new addition.
Number: 12 Created: 8/12/2008
RESPONSE: AN UPDATED CHECKLIST IS INCLUDED WITH THIS FINAL PLAN
SUBMITTAL.
[11/18/08] Please resubmit with the first round of Final Compliance. Thank you.
[8/12/08] Please see Appendix E4 for all design requirements for the plan sets. It's not an
all inclusive list of LCUASS but it's pretty close anyway. Please complete and submit E4
with the next submittal. Any items left off the plan set will become a new comment to be
addressed prior to plan approval.
Number: 13 Created: 8/12/2008
RESPONSE: ACKNOWLEDGED. WE POLITELY REQUEST AN IN PERSON MEETING
WITH THE PARTY RESPONSIBLE FOR SCANNING CITY DOCUMENTS TO ENSURE
THERE ARE NO DIFFICULTIES WITH THE FINAL MYLARS.
[11/18/08] Just carrying this comment into Final with a note that scanning requirements
must be met prior to the final mylar approval.
[8/12/08] Please see Appendix E6 for all scanning requirements.
Page 2
T
STAFF PROJECT REVIEW
Citvof Fort Collins
DAVID KASPKZAK/BRUCE HENDEE Date: 11/24/2008
BHA DESIGN INCORPORATED
1603 OAKRIDGE DRIVE
FORT COLLINS, CO 80525
Staff has reviewed your submittal for ODELL BREWING COMPANY EXPANSION -MAJOR
AMENDMENT/REPLAT-TYPE I, and we offer the following comments:
ISSUES:
Department: Engineering Issue Contact: Susan Joy
Topic: General
Number: 9 Created: 8/12/2008
RESPONSE: THE ULTIMATE ROADWAY IMPROVEMENTS HAVE BEEN DESIGNED
USING THE MODIFIED 4-LANE ARTERIAL SECTION DESRIBED BELOW. LIMITS,
PAYMENT AND TIMING OF CONSTRUCTION WILL BE ADDRESSED IN THE
DEVELOPEMNT AGREEMENT.
[i 1/18/08] Transportation Planning has received and reviewed the updated TIS that looked
at downgrading Lincoln Avenue and has determined that Lincoln needs to remain a 4 lane
arterial to adequately serve the area. However, a modified street section is both appropriate
and justified from Riverside to Lemay. It is agreed then, that a 4 lane arterial is required
minus the median and a center 12' continuous lane in its place. Please design the ultimate
improvements to this configuration and see the previous comment below as to the actual
construction.
[8/12/08] This development is responsible for the design and construction of Lincoln
Avenue to a 4 lane arterial as identified on the Master Street Plan plus an additional 1000' of
preliminary design on either side of the property. The city would consider taking cash in lieu
of actually constructing the road improvements depending on the timing of the Fort Collins
Brewery development on the northwest corner of Lincoln and Lemay. It all depends on the
timing of the two projects and what makes the most sense.
Number: 10 Created: 8/12/2008
RESPONSE: THE LINK-N-GREENS DRIVEWAY REALIGNMENT IS INCLUDED WITH
THE LINCOLN AVENUE CONSTRUCTION DRAWINGS.
[11/18/08] The variance request for the driveway spacing has been approved by Traffic with
the condition that the additional drivecut align with the golf Course driveway to the south. A
letter of intent from the golf course agreeing to the realignment of their driveway will be
required prior to the hearing.
[8/12/08] The variance request for driveway spacing was denied for the following reasons...
Lincoln Avenue is called out as a 4 lane arterial on the Master Street Plan and as
development occurs, each property owner is responsible for the design and construction of
their frontage to bring it up to standard. The ultimate cross section includes a median to
restrict the left turn movements along the street making the current driveways right in, right
out only in the future. In addition, we will be consolidating as many of the existing accesses
as possible and will not be allowing additional drive cuts to the properties fronting Lincoln.
This particular area is going through some major changes in the near future and the new
developments coming in will bring more and more traffic. More traffic, bigger streets and
higher traveling speeds mean a greater potential for accidents.