HomeMy WebLinkAboutAMENDED CSURF CENTRE FOR ADVANCED TECHNOLOGY - ODP - MJA110001 - CORRESPONDENCE - MINUTES/NOTES22. Question: (Resident) You also will rent to non -students, is that correct?
Answer: (Developer) We market and lease to students 99% of the time
because that is our target market; however, we cannot
discriminate without violating Fair Housing regulations.
23. Question: (Resident) Have the bike routes to campus been thought
about thoroughly studied? This is the City's responsibility.
Answer: (Developer's Consultant) The most likely route is Rolland
Moore Drive to Centre Avenue to West Prospect Road at the
stop light. There will be bike lanes on Rolland Moore Drive
and the Public Commercial Street. There will be an 8' wide
sidewalk along the Public Local Street for bikes and
pedestrians. The City provides bike lanes and pedestrian
signals. The West Prospect Road & Centre Avenue
intersection has signals for bikes and pedestrians as a
constrained intersection.
C
17. Question: (Resident) Are you saying that you are definitely using solar
energy?
Answer: (Developer) We have planned for it, but it depends on the
City's adoption of the split tariff concept explained to us by
the City's Economic Development Director.
18. Question: (Resident) Who is paying for the canal move? How did it
come about? Why is the move not shown on the ODP?
Answer: (Developer's Consultant) Campus Crest is working with the
ditch company on the possible ditch realignment. Campus
Crest would pay for the realignment.
(City Planner) The possible ditch realignment is a separate
process from the City's development review process for the
Amended CSURF Centre for Advanced Technology ODP.
19. Question: (Resident) Is The Grove at Fort Collins PDP dependent on the
ditch realignment?
Answer: (Developer's Consultant) Campus Crest, CSURF and the
ditch company all want the ditch to move but, no, the PDP is
not directly dependent on a realignment.
20. Question: (Resident) If you move the ditch how do you know whether or
not there will be flooding into neighboring properties?
Answer: (Developer's Consultant) The ditch realignment has nothing
to do with storm water.
21. Question: (Resident) We have a concern about 600 students living here.
What is your management philosophy?
Answer: (Developer) The project manager lives on the site and there
will be numerous student managers. Our rules are not much
different that those used by CSU. We have shared our rules
and regulations with CSU and they have said our rules are
very similar and may be a little more strict than theirs. We
will have highly trained R.A.'s. We believe in active, hands-on
management.
5
13. Question: (Resident) SEC filings — substantial losses.
Answer: (Developer) Campus Crest has a heavy amount of
depreciation. We have a fortress balance sheet. We have
turned a profit and our cash flow is positive. Campus Crest
files its financials on a quarterly basis with the SEC. These
are available to all persons through the SEC. In our most
recent quarter we showed Funds From Operations (FFO) of
approximately $48mm. We have one of the lowest leverages
REITs in our industry and a fortress balance sheet. This may
be from a pre -public filing, but certainly does not reflect our
first quarter filing from this year, which is more relevant.
14. Question: (Resident) If you are so financially solvent why can't you
down -scale the project?
Answer: (Developer) We are experiencing substantial investments
(costs) in the sustainability and green build components of
the project. The proposed density for the Grove is similar to
or in some cases less than comparable student housing
projects in Fort Collins.
15. Question: (Resident) What is the projected electricity use for this
project?
Answer: (Developer) The use for this project is significantly reduced
from that for the Greeley project.
16. Question: (Resident) How many kilowatt hours are being used? You are
over -estimating and over -selling. 40% is not true. You are
way off on your photo -voltaic use.
Answer: (Developer) Architectural Energy Corporation is in the
process of developing an energy model to estimate the
electric use for the project. Our estimates for the energy
offset are based on the 600-900kW system that we are
currently sizing for our Greeley property.
n
7. Comment: (Resident) Pulling Rolland Moore Drive to the south and
protecting the wetlands and neighborhood is a better plan
than one that would have the curved alignment to the north.
Response: No response required and none was given.
8. Comment: (Resident) A resident at the Worthington Independent Living
Facility would like a traffic light somewhere along Centre
Avenue to provide traffic control and pedestrian movement
along that street.
Response: No response required and none was given.
9. Question: (Resident) Who did the traffic counts on Centre Avenue in
February, 2011?
Answer: (City Traffic Engineer) The City is not aware of and did not
conduct that study. Private companies are allowed to take
traffic counts on City streets without notifying City Traffic
Operations.
10. Question: (Resident) What happens if Campus Crest abandons the
project?
Answer: (Developer) We do not envision trouble with our financing
capital and, therefore, we do not foresee abandoning The
Grove project. We are owners and operators.
11. Question: (Resident) What requirements does the City have to ensure
development of the project, if approved?
Answer: (City Engineer) Actual implementation of a project is done
through the City's Development Construction Permit process
that includes requiring the developer to pay construction
permit fees for the necessary public improvements and to
bond their full value.
12. Question: (Resident) Have you considered downsizing the project to 300
- 400 students?
Answer: (Developer) No, the economics dictate the size and viability of
the project.
3
r
many of our residents come to live with us after their first
year in school and so typically bring their friends with them
as their roommates. Students can swap or move into other
rooms, if necessary.
3. Question: (Resident) Have students been involved in the design of these
units?
Answer: (Developer) Yes, they have, primarily through the cooperative
Campus Crest and Institute for the Built Environment
design process. Also, Campus Crest's site manager lives at
the project.
4. Question: (Resident) Are the individual apartments gender specific?
Answer: (Developer) For the most part, yes, they are. If not, parents
are notified.
5. Comment: (Resident) With this development bringing 612 transient
students into the area Rolland Moore Drive will become a
speedway, which will have an adverse effect on the
neighborhood.
Response: (Developer's Consultant) First, the City requires that Rolland
Moore Drive be constructed between South Shields Street
and Centre Avenue. It has always been master planned for
the connection. Second, Rolland Moore Drive is being
designed to provide traffic calming and speed mitigation
measures through the project
6. Question: (Resident) Could a gate possibly be placed in the Rolland
Moore Drive in the middle of the project to divide the traffic
into 2 sections? The gate would then provide emergency
access only between the 2 sides.
Answer: (City Engineer) The City does want neighborhoods to
connect, not just here but City-wide. More connection
options would actually be better. Also, there is a City
ordinance against gated developments.
2
NEIGHBORHOOD INFORMATION MEETING
PROJECT: The Grove at Fort Collins
DATE: May 23, 2011
APPLICANT: Campus Crest Development
CITY PLANNER: Steve Olt
Current Planning
This potential project, known as The Grove at Fort Collins, would be located
at the southwest corner of Centre Avenue and Rolland Moore Drive directly
south of the Gardens on Spring Creek in the Centre for Advanced Technology.
The applicant proposes to develop a multi -family residential, student housing
project containing 218 dwelling units (with a mix of 2-bedroon, 3-bedroom and
4-bedroom units) in 12 buildings. There would be 499 parking spaces on -site
and on the public local street to satisfy the parking requirements. Additional
on -street parking would be available on Rolland Moore Drive and the Public
Commercial Street. The property is 27.5 acres in size. It is located in the MMN -
Medium Density Mixed -Use Neighborhood and E - Employment Zoning
Districts.
A Project Development Plan was submitted to the City of Fort Collins on
December 8, 2010 for review.
................. QUESTIONS, CONCERNS, COMMENTS, RESPONSES .................
1. Question: (Resident) Can you mail us the questions and answers when
they are ready?
Answer: (City Planner) Yes, we can and that will be done.
2. Question: (Resident) Apparently you will be renting each bedroom
individually. I know a student that says that this is a
nightmare. How will the students be involved in the
matching process.
Answer: (Developer) We have a limited liability leasing policy. We do a
high level of roommate matching. A lot of this is done by
word of mouth or through Facebook. Keep in mind that
1