HomeMy WebLinkAboutISLAMIC CENTER OF FORT COLLINS - PDP - PDP110011 - CORRESPONDENCE -Department: Environmental Planning
Contact: Lindsay Ex, 970-224-6143, lex@fcgov.com
Topic: General
Number: 1 Created: 05/09/2011
05/09/2011: No comments.
Department: Light And Power
Contact: Doug Martine, 970-224-6152, dmartine@fcgov.com
Topic: General
Number: 1 Created: 04/28/2011
04/28/2011: No Comments.
Department: PFA
Contact: Carle Dann, 970-219-5337, CDANN@poudre-fire.org
Topic: General
Number: 1 Created: 04/22/2011
04/22/2011: SPRINKLER REQUIREMENTS
This proposed building shall be fire sprinklered. 2006 International Fire Code Section 903
Number: 2 Created: 04/22/2011
04/22/2011: FIRE DEPARTMENT CONNECTION
Fire department connections shall be installed remote from the buildings or in an approved
location, and located on the street or fire lane side of buildings, fully visible and
recognizable from the street or nearest point of fire department vehicle access or as
otherwise approved by the fire code official. 2006 International Fire Code 912.2 and PFA
Fire Prevention Bureau Policy
Number: 3 Created: 04/22/2011
04/22/2011: KEY BOXES REQUIRED
Poudre Fire Authority requires a key box ("Knox Box") to be mounted in approved
location(s) on every new building equipped with a required fire -sprinkler system or
fire -alarm system. Knox Boxes are required to be installed approximately 60 inches above
grade and no higher than 72 inches above grade. PLEASE NOTE: PFA sells Knox Boxes
at cost at our headquarters, 102 Remington St., Fort Collins
2006 International Fire Code 506.1
Number: 4
Created: 04/22/2011
04/22/2011: FIRE LINE REQUIREMENT
Buildings that are required to be fire sprinklered shall have a minimum 6-inch fire line
unless hydraulic calculations can support a smaller fire line. NFPA 13 (2007) 23.1.3
Page 5
Department: Engineering Development Review
Contact: Susan Joy, 970-221-6581, sjoy@fcgov.com
Topic: General
Number: 6 Created: 05/06/2011
05/06/2011: Please widen the Emergency Access Easement to include the curbs
otherwise PFA can not enforce the "no parking" law or the painting and signage .
requirements. The site and landscape plans have done this but the utility plans have not. I
will need to see the updated plan sets prior to hearing to make sure that this has been
done.
Number: 7 Created: 05/06/2011
05/06/2011: The operable gate has not been placed where previously agreed. All previous
meetings have had the gate placed east -west across the north drive aisle just north of the
ramps to allow cars to turnaround off Summer Street. This arrangement provided the
same benefits of the 100' culdesac on which the variance request was based and
ultimately granted. Please relocate the gate to the agreed upon location and place it so
that it doesn't block the ped ramps, sidewalks or parking spaces when open or closed.
Number: 14 Created: 05/06/2011
05/06/2011: Please label tow, bow for all retaining walls on the site, landscape and utility
plans. The retaining wall along Lake Street may require a handrail depending on the height
of the wall.
Number: 16 Created: 05/06/2011
05/06/2011: Please show, label, dimension all easements and row.
Number: 17 Created: 05/06/2011
05106/2011: Please show and label all utilities, existing and proposed.
Number: 18 Created: 05/16/2011
05/16/2011: From Erika Keeton, Special Projects Manager: Soil stabilization will be
required in drive aisle/road areas for swelling soils.
Number: 19 Created: 05/16/2011
05/16/2011: Please send over pdfs of the updated plan sets showing that the easements
have been corrected, the location of the gate has been corrected to an approved location,
the curb returns at Summer and the drive entrance have been corrected, and that
sidewalk chases have been added to handle the flows (if choosing not to change the high
point to reduce the area of drainage to 750sf or less).
Topic: Landscape Plans
Number: 15
05/06/2011: Please remove all contours.
Topic: Site Plan
Created: 05/06/2011
Number: 13 Created: 05/06/2011
05/06/2011: Please remove the "possible connection for shared parking" and only show
existing and proposed improvements. You can always come through with revisions at a
later date should you obtain your agreements with the neighboring property after these
plans are approved and filed.
Page 4
Department: Engineering Development Review
Contact: Susan Joy, 970-221-6581, sjoy@fcgov.com
Topic: Construction Drawings
Number: 11 Created: 05/06/2011
05/06/2011: Please show and dimension all street cuts and include the street cut note:
Limits of street cut are approximate. Final limits are to be determined in the field by the
City Engineering Inspector. All repairs to be in accordance with City street repair
standards.
Number: 12
Created: 05/06/2011
05/06/2011: Grading Sheet - The temporary asphalt sidewalk to Prospect does not appear
to meet ADA's maximum slope requirements. Please label the existing (or proposed?)
channel and culvert shown at the north end of the asphalt sidewalk. There appears to be
some grading being done to accommodate the sidewalk and we will want details of that in
Final Compliance.
Topic: General
Number: 1 Created: 05/06/2011
05/06/2011: The City Engineer has approved your request not to terminate Summer
Street in a 100' diameter culdesac and will accept the drive aisle with the Emergency
Access and Access Easement provided that the sidewalks to Lake, Summer and
Prospect are also placed in access easement and that the "hammerhead turnaround"
remains free and clear to the public. I will need to see the updated plan sets prior to
hearing to make sure that this has been done.
Number: 2 Created: 05/06/2011
05/06/2011: Summer Street must be terminated using the radius style curb return (see
Illinois Street in Rigden Farm) as discussed in previous meetings. The method currently
shown is what we use to narrow down a public street midblock, not what is used at
intersections. The radius style curb also has the benefit of not effecting the driveway
configuration for the property owner immediately to the west of this project nor does it
eliminate as many on street parking spaces. Flowline and centerline profiles will be
required in Final Compliance.
Number: 3
Created: 05/06/2011
05/06/2011: Summer Street sidewalk connection - Sidewalks can not be widened in
increments of less than 4' so the area of taper must be completely removed and then
reconstructed to the wider width. I suspect that the curb and gutter is attached to the
existing sidewalk as well so you will need to remove and replace all sidewalk as far as you
are removing the curb and gutter. All removed or newly constructed sidewalks must be
put back detached to the current standard of 4.5' wide.
Number: 4 Created: 05/06/2011
05/06/2011: Driveways must be constructed in concrete to the right of way line. See
detail 707.
Number: 5
Created; 05/06/2011
05/06/2011: The pedestrian crossings in the drive aisles at the Summer intersection plus
the temporary asphalt sidewalk, plus the permanent concrete sidewalk north to Lake
Street and the sidewalks coming off Summer Street must be dedicated with a public
access easement (2' either side).
Page 3
Department: Advance Planning
Contact: Ted Shepard, 970-221-6343, tshepard@fcgov.com
Topic: General
Number: 8 Created: 05/17/2011
05/17/2011: On the two architectural elevation sheets, please indicate the where the
building achieves the height of 40 feet above grade.
Number: 9 Created: 05/17/2011
05/17/2011: On sheet A3.2, on the right side of the East (southeast) elevation, there is a
large two-story wall that except for the windows, is undifferentiated. Staff is concerned
that this elevation is lacking a distinctive base as required in Section 3.5.3(D)(6).
Number: 10 Created: 05/17/2011
05/17/2011: On sheet A3.2, please indicate the color of the small, lower domes, and the
color of the steel frame colonade with metal roof.
Number: 11 Created: 05/17/2011
05/17/2011: On the Lighting Plan, please indicate in heavier line, the west property line. It
appears that there are foot candles beyond the west property lien that exceed 0.1 but it is
difficult to determine where these levels occur in relationship to the property line. Section
3.2.4(D)(8) requires that foot candles not exceed 0.1 as measured 20 feet off property line.
Number: 12 Created: 05/17/2011
05/17/2011: The P.D.P. is ready for the Administrative Hearing. These comments can be
addressed at the time of the Final Plan submittal. And, at your option, these comments
can be addressed on a revised set of plans that may be forwarded to the Hearing Officer
in advance of Final Plan submittal.
Department: Engineering Development Review
Contact: Susan Joy, 970-221-6581, sjoy@fcgov.com
Topic: Construction Drawings
Number: 8 Created: 05/06/2011
05106/2011: Only the highlighted items on the checklist have been reviewed.
Number: 9 Created: 05/06/2011
05/06/2011: No more than 750sf of drainage may flow from the driveways and across the
sidewalk. Please adjust your highpoint accordingly or divert the flows from the driveway,
through the parkway and install sidewalk chases to properly deal with the flows (Check
both driveways on Lake and the driveway off Summer).
Number: 10 Created: 05/06/2011
05/06/2011: Please renumber the sheets so that the horizontal control sheet is before the
grading and utility sheet. Please label tow, bow for all retaining walls. Please label and
dimension all easements and row and whether or not they are existing or proposed. Once
this information is shown on the horizontal control sheet, you can minimize what you have
to label and dimension on all other sheets (lineweights will usually suffice).
Page 2
F�ort Collins
May 17, 2011
Dana Lockwood
Lockwood Architects, Inc.
1027 W. Horsetooth Rd., Ste 200B
Fort Collins, CO 80526
STAFF PROJECT REVIEW
City staff and outside reviewing agencies have reviewed your submittal for Islamic Center of Fort
Collins, and we offer the following comments:
Department: Advance Planning
Contact: Ted Shepard, 970-221-6343, tshepard@fcgov.com
Topic: General
Number: 1
Created: 05/11/2011
05/11/2011: The location of the control gate, or bollards, in the parking lot needs to be
established so that it meets the needs of the Poudre Fire Authority for fire access,
Engineering for the lost -driver turn -around, and the neighborhood, to discourage
cut -through traffic. A follow-up neighborhood meeting with the homeowners on Summer
Street prior to the pubic hearing is recommended so that the design and operational
characteristics of the control gate can be fully explained.
Number: 2 Created: 05/17/2011
05/17/2011: On the site plan, please add a note number 11 that describes general purpose
and function of the gate/bollards in the parking lot.
Number: 3 Created: 05/17/2011
05/17/2011: On the site plan, please add the Legal Description.
Number: 4 Created: 05/17/2011
05/17/2011: On the site and landscape plan, please indicate the approximate height of the
vertical wall and guardrail that form the north edge of the detention pond.
Number: 5 Created: 05/17/2011
05/17/2011: On the site plan, under Land Use Statistics, Building Intensity, please indicate
that the use is a 'Place of Worship" as this would be consistent with the permitted use in
the H-M-N zone.
Number: 6 Created: 05/17/2011
05/17/2011: On the site plan, either delete or describe the significance of "Qiblah."
Number: 7 Created: 05/17/2011
05/17/2011: On the landscape plan, along the west edge of the west parking and the east
edge of the east parking it appears that there are an insufficient number of shrubs to
comply with Parking Lot Perimeter Landscaping - Section 3.2.1(E)(4)(b). There appear to
be gaps which would not comply with the standard.
Project: Islamic Center of Fort Collins
Project Description: This is a request for a new mosque (praying area), children playing area,
gymnasium and elementary school for the Islamic Center of Fort Collins on 3.26
acres. The project will be constructed in phases, with the mosque being Phase
One, the school being Phase Two, and the gymnasium being Phase Three.
Phase one will consist of a two story, 11,600 sq ft building with an approximate
6,900 sq ft unfinished basement. The main prayer hall will have a capacity of 340
persons and the mezzanine will have a capacity of 130 persons. Parking will be
provided onsite and also in the existing parking lot of the Plymouth
Congregational Church per a shared parking agreement, as the two
congregations worship on different days (Fridays and Sundays). The building will
not only represent Islamic architecture by including a dome and a minaret, but will
also include an exterior in the Northern Colorado vernacular. In this respect, this
building will be unique in its architecture and will add to the diverse cultural identity
of Fort Collins.
Date: 05/1012011 Issue ID: 1 Topic: Site Plan Round: 1 Status: Active
Issue: 05/10/2011: Please add a legal description for the property.
Date: 05/10/2011 Issue ID: 2 Topic: Site Plan Round: 1 Status: Active
Issue: 05/1012011: There are many line over text issues.
Date: 05/10/2011 Issue ID: 3 Topic: Landscape Plans Round: 1 Status: Active
Issue: 05/1012011: There are many line over text & text over text issues.
Page 1 of 1
Be sure and return all of your redlined plans when you re -submit.
If you have any questions regarding these issues or any other issues related to this project, please
feel free to contact me at 970-221-6343.
Sincerely,
/�
Ted Shepard
Chief Planner
Page 9
Department: Water -Wastewater Engineering
Contact: Roger Buffington, 970-221-6854, rbuffington@fcgov.com
Topic: Construction Drawings
Number: 1 Created: 05/05/2011
05/05/2011: Show all water services that haved been stubbed onto the site from Lake
Street. (There are 3 existing 3/4" stubs.) All water service stubs must be used or
abandoned at the main. Add appropriate notes to coordinate abandonment with Water
Utilities (970-416-2165).
Number: 2 Created: 05/05/2011
05/05/2011: Label sizes of all proposed water and sewer services.
Number: 3 Created: 05/05/2011
05/05/2011: Is the sewer service connecting to an existing service stub?
Number: 4 Created: 05/05/2011
05/05/2011: Show curb stop and meter pit on domestic water service.
Number: 5 Created: 05/05/2011
05/05/2011: The water main shown in the north half of Lake is an old 4" main that has
been abandoned.
Number: 6 Created: 05/05/2011
05/05/2011: Add profiles of water service, fire line and sewer service to insure that there is
adequate cover through the detention pond.
Number: 7 Created: 05/05/2011
05/05/2011: Is an irrigation tap planned for the project? If yes, add to the plans. (Fees
have previously been paid for a 1-inch domestic water service and a 1-inch irrigation
service.)
Number: 8 Created: 05/05/2011
05/05/2011: Add note shown on the redlined plans for the fire line wet tap connection.
Number: 10
05/05/2011: See redlined plans for other comments.
Created: 05/05/2011
Number: 11 Created: 05/12/2011
05/12/2011: The depth of the sanitary sewer MH in Lake Street at approximately the
east/west center of the site is approximately 14 feet. Invert and rim elevations are shown
on the overall utility plan.
Topic: General
Number: 9
Created: 05/05/2011
05/05/2011: Will the future phases all be part of the same building or separate buildings?
If separate buildings, each building must have separate water and sewer services in which
case you may want to give some thaought to stubbing services now.
Page 8
Department: PFA
Contact: Carle Dann, 970-219-5337, CDANN@poudre-fire.org
Topic: General
Number: 9 Created: 04/22/2011
04/22/2011: DEVELOPMENT REVIEW APPLICATION AND FEE
You are required to complete a PFA Development Review Application and pay the review
fee. Cost for a project of this scope is $250. You can do this in person at the Fire
Prevention Bureau at 102 Remington St. or apply/pay online at www.pfafiireprevention.org.
Under Quick Links, click on Development Review Application.
Department: Stormwater Engineering
Contact: Wes Lamarque, 970-416-2418, wlamarque@fcgov.com
Topic: General
Number: 1 Created: 05/1012011
05/10/2011: The Water Quality volume was not calculated correctly. The required volume
is .065 ac-ft.
Number: 2 Created: 05/10/2011
05/10/2011: There is no maintenance access into the detention pond. There is also
detention pond landscape standards that have criteria for the landscape/retaining walls.
The standard describes maintenance requirements and aesthetic requirements.
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: Landscape Plans
Number: 3 Created: 05/10/2011
05/1012011: There are many line over text & text over text issues.
Topic: Site Plan
Number: 1 Created: 05/10/2011
05/10/2011: Please add a legal description for the property.
Number: 2 Created: 05/10/2011
05/10/2011: There are many line over text issues.
Department: Transportation Planning
Contact: Matt Wempe, 970-416-2040, mwempe@fcgov.com
Topic: Site Plan
Number: 1 Created: 05/10/2011
05/10/2011: The asphalt walk from Prospect Road and the concrete walk adjacent to the
driveway on the west side of the street should be included in an access easement. This
can be accomplished by either expanding the 24' access and emergency easement
shown on the plan, or by creating a separate easement.
Department: Water -Wastewater Engineering
Contact: Roger Buffington, 970-221-6864, rbuffington@fcgov.com
Page 7
Department: PFA
Contact: Carle Dann, 970-219-5337, CDANN@poudre-fire.org
Topic: General
Number: 5 Created: 04/22/2011
04/22/2011: REQUIRED ACCESS
Fire access roads (fire lanes) shall be provided for every facility, building or portion of a
building hereafter constructed or moved into or within the PFA's jurisdiction when any
portion of the facility or any portion of an exterior wall of the first story of the building is
located more than 150 feet from fire apparatus access as measured by an approved route
around the exterior of the building or facility. This fire lane shall be visible by painting and
signage, and maintained unobstructed at all times. A fire lane plan shall be submitted for
approval prior to installation. In addition to the design criteria already contained in relevant
standards and policies, any new fire lane must meet the following general requirements:
L Be designed as a flat, hard, all-weather driving surface (asphalt or concrete) capable
of supporting fire apparatus weights. Compacted road base shall be used only for
temporary fire lanes or at construction sites.
6 Have appropriate maintenance agreements that are legally binding and enforceable.
4 Be designated on the plat as an Emergency Access Easement.
4 Maintain the required minimum width of 20 feet throughout the length of the fire lane
(26 feet on at least one long side of the building when the structure is three or more stories
in height).
If the building is equipped throughout with an approved automatic fire -sprinkler system, the
fire code official is authorized to increase the dimension of 150 feet.
PLEASE NOTE: Make sure the EAE is either shown on the plat or if not platting, then it
needs to be dedicated by separate document. Also, if you're fairly certain of the location of
the east parking lot and drive aisle, you might want to dedicate it as an EAE at this time, so
you won't have to do that at the time you develop Phase(s) 2and 3.
2006 International Fire Code 503.1.1, 503.2.3. 503.3, 503.4 and Appendix D
Number: 6 Created: 04/22/2011
04/22/2011: TURNING RADII
The required turning radii of a fire apparatus access road shall be a minimum of 25 feet
inside and 50 feet outside 2006 International Fire Code 503.2.4 and Appendix D103.3
Number: 7 Created: 04/22/2011
04/22/2011: GATE OPERATION
PFA will require that gate operation be approved in advance.
Number: 8 Created: 04/22/2011
04/22/2011: ADDRESS NUMERALS
Address numerals shall be visible from the street fronting the property, and posted with a
minimum six-inch high numerals on a contrasting background. (Bronze numerals on
brown brick are not acceptable). If the numerals are mounted on a side of the building
other than the side off of which it is addressed, the street name is required to be posted
along with the numerals.
2006 International Fire Code 505.1