Subway at 651 SE Frontage Road, PDP 120016, Round Number 1 Comment Response
Page 9 of 9
Comment Number: 15 Comment Originated: 06/06/2012
06/06/2012: LUC 3.2.2(C)(5)(a) Walkways shall connect street sidewalks with building entries with
Directness and continuity.
The proposed sidewalk connection does not meet the standard, more connections along the north
and east sided of the property to the public right of way are needed.
The route selected is the only route that will meet ADA. The site sits in a substantial hole and 3:1
slopes exist along the entire east frontage. We explored another connection along the northerly
Frontage Road, but that route did not meet ADA either. Stairs are not acceptable due to liability
issues.
Mr. Jason Holland
Subway at 651 SE Frontage Road, PDP120016, Round Number 1 Comment Response
Page 8 of 9
Canopies/porticos, overhangs, recesses or projections of at least 3% of the wall length,
Arcades, Distinctive roof forms, Arches, Outdoor patios, Display windows, Planter or wing walls
the incorporate landscaped areas and/or places for sitting.
Comment Number: 11 Comment Originated: 06/01/2012
06101/2012: 3.5.3(B)(2) Requires a commercial building to meet build -to -lines, meaning the
building should not sit back any further from the property then 15ft.
Since the original plat established building envelopes and setbacks the proposed building
should be brought to the north and east building envelope line.
The building is currently placed at the 25' setback on the east side. Since detention and water
quality are required for this site, there is insufficient room to move the building to the north setback
line. We feel the pedestrian patio on the north is a greater amenity than moving the building north.
Comment Number: 12 Comment Originated: 06/01/2012
06/01/2012: LUC 3,5.3(C) Horizontal masses shall not exceed a height:width ratio of 1:3 without
substantial variation in massing that includes a change in height and projecting or recessed
elements
The proposed elevations on the east side of the building is divided by hardie board trim, but
this does not adequitly meet this standard.
Comment Number: 13 Comment Originated: 06/04/2012
06/04/2012: LUC 3.5.3 (D)(6)(b)2. A recognizable "top" a sloping roofs with overhangs and
brackets.
Department: Zoning
Contact: Noah Beals, 970.416.2313, nbeals(&fcgov.com
Topic: General
Comment Number: 14 Comment Originated: 06/04/2012
06/0412012: LUC 3.2.2(J) Parking Lot Setbacks from property line along a non -arterial street is
10 ft.
Our reading of the code is that the parking lot setback is 5' minimum and 10' average. We have
set the setback at 10' at the midpoint of the stall which should meet the 10' average requirement.
LUC 3.2.1(E) 6% of the interior parking lot is required to be landscaped.
We have added a landscape island in the parking row along the west property line. This only brings
the interior landscape to about 2.6%. We are providing 46% total landscape area on the site.
Subway cannot lose any more parking spaces and remain a viable project.
Mr. Jason Holland
Subway at 651 SE Frontage Road, PDP120016, Round Number I Comment Response
Page 7 of 9
05/31/2012: No signs or their locations are approved by the PDP and FDP. Sign and locations
are approved through a separate sign permit.
Comment Number: 4 Comment Originated: 05/31/2012
05/31/2012: Need elevations for all structures (trash/recycling enclosures and freezers...).
Comment Number: 5 Comment Originated: 05/31/2012
05/31/2012: Mechanical/utility equipment (vent, conduits, meters, RTU... ) locations need to be
identified on the plans (site, landscaping, and elevations) with a note on how they will be
screened/painted.
Comment Number: 6 Comment Originated: 05/31/2012
05/31/2012: Trash Enclosure needs to be designed with a walk-in access without having to
open the main service gate.
Department: Zoning
Contact: Noah Beals, 970-416.2313, nbeals(&fcaov.com
Topic: General
Comment Number: 7 Comment Originated: 05/31/2012
05/31/2012: Land Use Code (LUC) 4.21(F) Development located within one -quarter mile of the
centerline of 1-25 shall be subject to Division 3.9 of LUC.
Comment Number: 8 Comment Originated: 06/01/2012
06/0112012: 3.9.4(A) Parking lot Perimeter Landscaping 75% of all parking lot areas shall be
screened from nearby streets, public right or ways, public open spaces by at least one of the
following three methods: 1) a berm 3 feet tall with maximum slope of 3:1 in combination of
evergreen shrubs and trees 2) hedge at lest 3 ft tall consisting of a double row of shrubs
capable of growing into hedge within 3 years of installation 3) decorative fence or wall between
3 to 4 ft in height in combination with trees and shrubs.
Comment Number: 9 Comment Originated: 06/01/2012
06/01/2012: 3.9.5(B) Buildings that face public street adjionding developments or connecting
pedestrian frontage shall be articulated, fenestrated and proportioned to human scale along at
least 60% of the facade using features such as windows, entrances, arcades, arbors or
awnings.
The proposed elevations on the south and east side of the building is divided by hardie board
trim, but this does not adequitly meet this standard.
Comment Number: 10 Comment Originated: 06/01/2012
06/01/2012: 3.9.5(B)(2) Building Facades facing a primary access street shall have clearly
defined, highly visible customer entrances that feature at least two of the following:
Mr. Jason Holland
Subway at 651 SE Frontage Road, PDP120016, Round Number 1 Comment Response
Page 6 of 9
4.500 cf and 3,000 cfs for a .25 cfs release. Please revise.
Comment Number: 5 Comment Originated: 06/07/2012
06/07/2012: RCP is required within the City ROW. Please revise the detention pond's outlet
pipes.
Comment Number: 6 Comment Originated: 06/07/2012
06/07/2012: Please use the City's standard water quality outlet structure.
Department: Technical Services
Contact: Jeff County, 970-221.6588, jcountycDfcgov.com
Topic: Construction Drawings
Comment Number: 5 Comment Originated: 06/11/2012
06/11/2012: There are line over text issues on sheets C4 & C5.
Department: Traffic Operation
Contact: Ward Stanford, 970.221.6820, wstanford()fcgov.com
Topic: Construction Drawings
Comment Number: 1 Comment Originated: 06/18/2012
06/18/2012: Construction Notes, sheet C2: Please revise each location where "Local Entity
Engineer" is used under the Traffic Signing and Pavement Marking Construction Notes, to state
"Local Entity Traffic Engineer".
Department: Zoning
Contact: Noah Beals, 970-416.2313, nbeals()fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 05/31/2012
05/31/2012: An access easement with the lot to the west (OUTLOT B of INTER CHANGE
BUSINESS PARK) will need to be recorded.
Comment Number: 2 Comment Originated: 05/31/2012
05/31/2012: Any work on the lot to the west (OUTLOT B of INTER CHANGE BUSINESS PARK)
does not receive approval from this PDP and FDP. The lot to the west is located in the county
and any work on this lot will need county approval.
Comment Number: 3 Comment Originated: 05/31/2012
Mr. Jason Holland
Subway at 651 SE Frontage Road, PDP120016, Round Number I Comment Response
Page 5 of 9
Department: Light And Power
Contact: Doug Martine, 970.224.6152, dmartine(o)fcuov.com
Topic: General
Comment Number: 1 Comment Originated: 05/31/2012
05131/2012: Power requirements, a location for an electric transformer, and electric
development charges will need to be coordinated with Light & Power Engineering
(970)221-6700.
Comment Number: 2 Comment Originated: 05/31/2012
05/31/2012: Relocation of the existing electric equipment will be at the expense of the
developer.
Comment Number: 3 Comment Originated: 05/31/2012
05/31/2012: Light & Power will need a copy (paper or pdf) of the recorded plat.
Comment Number: 4 Comment Originated: 05/31/2012
05131/2012: An AutoCad (v.2008) drawing of the final site plan will need to be sent to Terry Cox
at TCOX@FCGOV.COM.
Department: Stormwater Engineering
Contact: Wes Lamarque, 970-416.2418, wlamaroueojcoov.com
Topic: General
Comment Number: 1 Comment Originated: 06/07/2012
06/07/2012: A drainage easement is required for the limits of the detention pond.
Comment Number: 2 Comment Originated: 06/07/2012
06107/2012: Please document in the text of the drainage report the outfall to the west of the site
since this was not the originally designed path for this site. Explain the route all the way to
Boxelder Creek. Drainage easements must exist down to Boxelder Creek to use the west
outfall.
Comment Number: 3 Comment Originated: 06/07/2012
06/07/2012: A release rate of .03 cfs is not practical and clogging would most likely occur with
an orifice this small. This site can use .25 cfs as a release (.50 cfs/acre). The City of Fort
Collins does not use Urban Drainage's hydrology criteria.
Comment Number: 4 Comment Originated: 06/07/2012
06/07/2012: The detention pond is undersized. The required detention with a .03 cfs release is
Mr. Jason Holland
Subway at 651 SE Frontage Road, PDP120016, Round Number 1 Comment Response
Page 4 of 9
Comment Number: 10 Comment Originated: 06/15/2012
06/13/2012: Reinforced Concrete Pipe (RCP) is required for drainage facilities in the right of
way. Please revise the plans.
Comment Number: 11 Comment Originated: 06/15/2012
06/13/2012: A meeting with CDOT has been rescheduled for Friday, June 22nd to discuss
concerns and requirements related to the development. Revised comments that address their
concerns will be provided shortly after the scheduled meeting.
We have not heard the results of this meeting. Were there any issues?
Department: Forestry
Contact: Tim Buchanan, 970-221-6361, tbuchanan(a.fcaov.com
Topic: Landscape Plans
Comment Number: 1 Comment Originated: 06/12/2012
06/12/2012:
Not all of the trees are clearly labeled. The tree and shrub list should include size, method of
transplant and number used. Standard transplant method is Balled and Budapped. Minimum
sizes for trees are:
Shade Trees 2.0 inch caliper
Ornamental Trees 1.5 inch Caliper
Evergreen Trees 8 feet height.
Comment Number: 2 Comment Originated: 06/12/2012
06112/2012: Please add these landscape notes:
-The soil in all landscape areas, including parkways and medians, shall be thoroughly
loosened to a depth of not less than eight (8) inches and soil amendment shall be thoroughly
incorporated into the soil of all landscape areas to a depth of at least six (6) inches by tilling,
discing or other suitable method, at a rate of at least three (3) cubic yards of soil amendment
per one thousand (1,000) square feet of landscape area.
•A permit must be obtained from the City forester before any trees or shrubs as noted on
this plan are planted, pruned or removed on the public right-of-way. This includes zones
between the sidewalk and curb, medians and other city property. This permit shall approve the
location and species to be planted. Failure to obtain this permit may result in replacing or
relocating trees and a hold on certificate of occupancy.
Mr. Jason Holland
Subway at 651 SE Frontage Road, PDP 120016, Round Number 1 Comment Response
Page 3 of 9
State Highway 14 Frontage Road
Comment Number: 4 Comment Originated: 06/13/2012
06/13/2012: An access easement/agreement from the adjacent property owner to the west will
be required for the west point of access
Comment Number: 5 Comment Originated: 06/13/2012
06/13/2012: A letter of intent for a construction easement will be required from the adjacent
property owner for the improvements proposed on the west property line. An additional letter
of intent from the adjacent property owner will also be required for the access easement for the
west point of access to the development. These letters will need to be provided prior hearing.
Comment Number: 6 Comment Originated: 06/13/2012
06/13/2012: An access easement will need to be dedicated where the sidewalk in the public
right of way routes around existing utility boxes.
Comment Number: 7 Comment Originated: 06/13/2012
06/13/2012: The lot to the west is currently located in county limits, any work proposed on this
lot will need county approval.
Department: Engineering Development Review
Contact: Tyler Siegmund, 970-416.2779, tiegmund cDfcgov.com
Topic: General
Comment Number: 6 Comment Originated: 06/15/2012
06/13/2012: An access easement or right of way will need to be dedicated where the sidewalk
along the SE Frontage Rd routes around the existing utility boxes. Without a replat, this
process will need to be done by separate document using the City's Transportation
Development Review Fee form (TDRF). For additional information on these fees, please see:
http://www.fcgov.com/engineering/dev-review.php
Since you are not planning on replating the property, all easement vacations (if needed) and
referenced dedication above will need to be done by separate document.
a.Each easement dedication request has a TDRF of $250 for the processing and review of
the dedication. The recording fees will also need to be provided once we know how many
documents and pages there are. Please contact me if you need more information about this
process.
Comment Number: 9 Comment Originated: 06/15/2012
06/13/2012: To achieve pedestrian connectivity level of service, a sidewalk and handicap
ramps will need to be installed along the west side of the SE Frontage Rd up to the traffic light
to accommodate pedestrians accessing the development.
Mr. Jason Holland
Subway at 651 SE Frontage Road, PDP 120016, Round Number 1 Comment Response
Page 2 of 9
06/08/2012: Related to to comment three: 3.2.1(E)(2)(d) requires at least five feet of
landscaping in front of 50% of the building. An effort to put more landscaping at the building
entrance and building face should be investigated. Perhaps the eastern 25' building setback
along the frontage road could be reduced. The LUC code may allow a 15' - 25' building
setback range. At a minimum, a shade tree should be placed in a cut-out or tree grate directly
south of the HC parking space. A proposed tree south of the building can be relocated to
meet this requirement. Refer to redline plan.
Again, the narrow site is the constraining factor. We have added a tree grate as suggested above.
Department: Current Planning
Contact: Jason Holland, 970.556.3176, iholland&fcoov.com
Topic: Landscape Plans
Comment Number: 5 Comment Originated: 06/08/2012
06/08/2012: The parking median to the west needs landscape shrubs or perennial material and
an additional shade tree. Please show some options for this.
Comment Number: 6 Comment Originated: 06/08/2012
06/08/2012: Please add the standard City landscape notes to the plans and show tabulations
for tree species diversity.
Comment Number: 7 Comment Originated: 06/08/2012
06/08/2012: The plant list needs to show the common/scientific name, quantity, size/caliper,
and water use for each plant.
Comment Number: 8 Comment Originated: 06/08/2012
06/08/2012: Please note that irrigation plans are required prior to issuance of builing permit.
Department: Engineering Development Review
Contact: Tyler Siegmund, 970-416-2779, tsiegmundojcaov.com
Topic: General
Comment Number: 1 Comment Originated: 06/13/2012
06/13/2012: Update general note #19 on the cover sheet to reference current project drainage
and erosion control study
Comment Number: 2 Comment Originated: 06/13/2012
06/13/2012: Update Geotech report reference to current project geotech report
Comment Number: 3 Comment Originated: 06/13/2012
06/13/2012: Label the radius on the horizontal control plan for new the drive approach off of
s
ll
Y'lPerception
ij design group,, inc.
P�
6901 South Pierce Street. Suite 350 Littleton, Colorado 80128 Voice 303-232.8089 Fue 303-232.5255
June 29, 2012
Mr. Jason Holland
City of Fort Collins Community Development
281 North College Avenue
Fort Collins, CO 80522
Re:Subway at 651 SE Frontage Road, PDP120016, Round Number 1 Comment Response
Dear Mr. Holland,
Attached is a pdf drawing of the above referenced site. The purpose of this letter is to outline issues that
we will not be able to address, and provide explanation why. We would like to resolve these differences
prior to making the full re -submittal in an effort to avoid future reviews. I have added text in red below to
discuss said issues. Issues which we feel we can address are left blank below for now. A complete
response letter will be provided with the submittal. Note also, I have erased "No Comment" responses to
shorten this document.
Comment Summary:
Department: Current Planning
Contact: Jason Holland, 970-556-3176, ihollandna.fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 06/08/2012
06/08/2012: Recycling will be required within the trash enclosure. Refer to section 3.2.5 and the
standard details that were sent to the design team via email.
Comment Number: 2 Comment Originated: 06/08/2012
06/08/2012: Please verify that the HC ramp to the south meets standard clearance
requirements at top of ramp. It appears that the ramp may be too close to the corner of the
building, verify with engineering staff that this is acceptable.
Comment Number: 3 Comment Originated: 06/08/2012
06/0812012: The 4.5' sidewalk dimension in front of the building is tight. A minimum of five to
six feet is preferred to the face of curb.
Due to the narrow nature of the site and 25' required setback to the east, we have provided the
maximum sidewalk possible. Note that the required sidewalk for ADA is 3' which we exceed.
Topic: Landscape Plans
Comment Number: 4 Comment Originated: 06/08/2012