Loading...
HomeMy WebLinkAboutMASON ST. NORTH, MAJOR AMEND. - FDP - 4-97C - SUBMITTAL DOCUMENTS - ROUND 1 - (5)What is the elevation of the abandoned 36-inch storm sewer in Cherry Street at the point of crossing with the 8-inch water main? If there is a conflict, remove abandoned storm sewer 5 feet each side of water main and plug ends of storm sewer with concrete. Number: 162 Created: 12/6/2001 The thrust block on the fire hydrant on Mason Court will not have undistributed earth behind it; therefore, restrain all joints between hydrant and the 12x12x8 tee on the east side of Mason Court. Can hydrant be placed on east side of Mason Court? Number: 163 Created: 12/6/2001 Maintain 5 foot separation between raised planter boxes and water service/meter pits. Number: 164 Created: 12/6/2001 See additional comments on plans. Be sure and return all of your redlined plans when you re -submit. If you have any questions regarding these issues or any other issues related to this project, please feel free to call me at (970) 221-6750. Yours Truly, Steve Olt City Planner Page 5 Please revise Q100 values in the plans and report. Incorrect intensity was used for all Q100 calculations. Incorrect intensities were also used to calculate the Q2 but the error was on the conservative side. Topic: Drainage Number: 165 Created: 12/10/2001 The proposed 48-inch storm sewer near Building C is within a few feet of the building. Please investigate whether or not the waterline could be relocated farther south, thus allowing for the storm sewer to be moved at least 10-feet from the building. See Sheet 6. This may require an easement within the railroad easement. If this is not possible, an alternative would be to use water tight pipe like DIP, for the area in front of Building C. Number: 166 Created: 12/10/2001 Please provide calculation & cross-section for area just west of Building C to verify 100-year flows will turn corner and not inundate the underground parking. See drainage plan. Number: 167 Created: 12/10/2001 Please provide an outfall for the sub -basin south of the railroad tracks. The parking lot drains to the east along the south side of the railroad tracks to a low lying area. With some regrading to the south of the railroad tracks and the inlet in sub -basin 1d enlarged, flows from the south parking lot may be able to dump into the box culvert at this inlet. Department: Water Wastewater Topic: General Issue Contact: Jeff Hill Number: 146 Created: 11 /30/2001 Place all water and sewer mains in roadways/drives when possible. Number: 147 Created: 11 /30/2001 Provide elevation views for buildings "A" and "B" for our review. All individual buildings must provide their own services. Number: 148 Created: 11 /30/2001 Eliminate all unnecessary water line fittings when possible. Number: 149 Created: 11 /30/2001 Show all proposed water and sewer services on the overall utility plans ( including proposed irrigation taps). Number: 150 Created: 11 /30/2001 Lower storm sewer in order to allow water main to cross above storm sewer and to prevent a lowering of water main. Number: 151 Provide appropriate scales for all plan and profile views. Department: Water Wastewater Created: 11 /30/2001 Issue Contact: Roger Buffington Topic: utility plans Number: 157 Created: 12/6/2001 Plan sheet 13 includes details which appear to be for a subdrain. Is there a subdrain on the project? What is this detail to be used for? Number: 158 Created: 12/6/2001 Plan sheet 13 includes a manhole base detail that is not a City standard detail. What is this detail to be used for? Number: 159 Created: 12/6/2001 Re -align the water main at the SE corner of the building. Number: 160 Created: 12/6/2001 Move 6-inch water line on NW side of building into the drive as noted on the plans. Number: 161 Created: 12/6/2001 Page 4 Topic: sheet 6 Number: 138 Created: 11 /23/2001 Please show the street cut to be made on Cherry. Topic: Site Plan Number:123 Created:11/23/2001 There are still areas where the 6' minimum sidewalk width is not being met where cars overhang the sidewalk. Number: 124 Created: 11 /23/2001 There is inadequate backing distance behind the westernmost garage south of the railroad tracks. Number: 126 Created: 11 /23/2001 Where is the public access easement(s) for the area south of the RR tracks? Number: 127 Created: 11 /23/2001 The utility easement along the south side of Mason Court should be 9 feet per LCUASS figure 7-9F. Please provide this width. —r Number: 128 Created: 11 /23/2001 Please note that for the certain portion of building A that crosses over the electric easement, that the easement has been vacated above a certain elevation and that portion of the building is permissible there. Number: 156 Created: 12/5/2001 Please use phantom lines for existing features so that a differentiation can be made between what is existing and what is proposed. (This applies to all sheets) Number: 168 Created: 12/12/2001 Please note that under the variance for parking setbacks along Mason Court, a minimum of 20' must be maintained. Please configure parking to meet this requirement. Topic: utility plans Number: 144 Created: 11 /29/2001 The design and construction of the median in Cherry needs to be completed with this project. Please re -include the median in this plan set. Construction of the median will most likely be required by the time of Certificate of Occupancy for the buildings. Department: Stormwater Utility Issue Contact: Wes Lamarque Number: 112 Created: 11 /20/2001 Please provide swale cross -sections and calculations for all swales. (repeat comment) Number: 113 Created: 11 /20/2001 Please provide identifier for benchmarks. (repeat comment) Number: 114 Created: 11 /20/2001 Please provide a P.E. signature and stamp for next submitted reports. Number: 115 Created: 11 /20/2001 Erosion Control Comments: Please provide calculations. The BMP's noted in the report are not translated to the plan well or are not shown on the plan -- please correct. Number: 116 Created: 11 /20/2001 Page 3 3. What is the potential source of the groundwater? 4. Are there any existing wells in the area? 5. Address ground water quality. 6. Address water flow calculations, how was pipe sized, what are recommendations for construction of subdrain? 7. Identify the cone of influence as a result of the dewatering. 8. Where will subdrain(s) terminate? 9. Where is the log of the second boring number 6? Topic: Grading Number: 139 Created: 11 /23/2001 Please provide a detail of the retaining wall. Number: 140 Created: 11 /23/2001 What is the elevation of the basement floor? (repeat) Number: 154 Created: 12/5/2001 Presently, new grading is shown under the railroad tracks. Shouldn't that be adjusted so that the tracks are not affected? Topic: Landscape Plan Number: 122 Created: 11 /23/2001 The building outlines/footprints don't seem to match from the Site plan to the landscape plan. Topic: Plat Number: 117 Created: 11/23/2001� o Please dedicate a 9' utility easement along Mason Court as shown in LCUASS Figure 7-9F. Number: 118 Created: 11 /23/2001 Please add a note to the cover sheet referring to the vacation of old easements if they are not shown on this plat (repeat). Number: 119 Created: 11 /23/2001 Please include a legal description of the height limitation on the Light and Power easement as it passes underneath the building. Number: 120 Created: 11 /23/2001 Please verify that the gas company and light and power are amenable to the areas where their exclusive easements are infringed upon. Number: 121 Please provide a line for the Railroad to sign on. Topic: Sheet 3 Number: 134 Where are the sight distance easements? Number: 135 Please show striping on Cherry Street. (repeat) Created: 11 /23/2001 Created: 11 /23/2001 Created: 11 /23/2001 Number: 136 Created: 11 /23/2001 It appears that an offsite easement is needed for work to be done to the west of the property just north of Cherry. Topic: Sheet 5 Number: 137 Created: 11 /23/2001 Where is MH A-1 shown on the plan view of the sanitary sewer? Page 2 STAFF PROJECT REVIEW Citvof Port Collins Wolff -Lyon Architects Date: 02/25/2004 777 Pearl St., Ste. 210 Boulder, CO 80302 Staff has reviewed your submittal for MASON STREET NORTH (MAJOR AMEND. TO MARTINEZ PUD), #4-97B, and we offer the following comments: ISSUES: Department: Engineering Topic: Cover sheet Number: 130 Please list the Developer and Owner of this project. (repeat) Number: 131 Please lighten the vicinity map so that it is legible/reproducible. Issue Contact: Katie Moore Created: 11/23/2001 Created: 11 /23/2001 Number: 132 Created: 11 /23/2001 Please show the indemnification statement separately from the signature block and include only on the cover sheet. Number: 133 Please provide a signature line for the railroad. Created: 11 /23/2001 Topic: Drainage Number: 155 Created: 12/5/2001 Please provide a legal description and sketch of the required drainage area on Parks' land. These will be used to file a Notice of Facility Location in lieu of an Easement. Topic: General Number: 141 Created: 11 /23/2001 Please provide the under -walk drain detail from LCUASS. Number: 142 Created: 11 /23/2001 No design has been shown for the subdrains needed for building C per the soils report. Please show how subdrains will tie into an approved discharge facility. Number: 143 Created: 11 /29/2001 ,y, The driveway between buildings A and B may be 18' in width; the driveway between t/buildings B and C may be 22' in width, and the driveway access off of Cherry must be a minimum of 24' in width per the Variance Request approvals and denials. Number: 145 Created: 11 /29/2001 The comments numbered lower than 117 are repeat comments. Number: 152 Created: 11 /30/2001 Please refer to the redlined utility plan checklist for further comments. Topic: Geotechnical Report Number: 153 Created: 11 /30/2001 Subsurface report does not address issues as outlined in LCUASS 5.6: 1. Site location map does not address irrigation ditches, wet lands or other features. 2. Where are flow rates addressed, potential high water levels? Page 1