HomeMy WebLinkAboutRICHARDS LAKE TO WAVERLY TRANSMISSION LINE - SPAR - 12-08 - SUBMITTAL DOCUMENTS - ROUND 1 - PLANNING OBJECTIVESTri-State Richard Lake to Waverly 115-kV Transmission Line Project
Site Plan Advisory Review Application
Activity
Date
Receive materials
May 2009
Construction
June -October 2009
In-service
November 2009
4.3 Site Plan Drawings
As required, 31 large -format copies of the site plan drawings (labeled RI-101) have been
provided with this submittal.
4.4 Architectural Elevations and Visual Simulations
Eight large -format copies of the architectural elevations schematic (labeled RI-102) have
been provided with this submittal. The architectural elevations are accompanied by submittal
of schematics of the transmission line deadend structures (labeled G20-001) and the
transmission line tangent structures (labeled G20-002). Figure 5 provides a graphical
representation of typical wood and steel transmission structures. Figure 6 provides a visual
simulation of the transmission line.
4.5 Letters of Intent and Easements
The proposed project has been discussed with Anheuser-Busch and the company is aware of
Tri-State's needs and requirements for an easement across their property. Tri-State will
continue to coordinate with Anheuser-Busch personnel regarding timing and requirements to
conduct necessary surveys and will commence easement negotiations as soon as the
surveys and design are complete.
Every effort will be made to acquire the rights by negotiation with each landowner. However,
if the necessary rights cannot be acquired by a negotiated agreement, Tri-State, as a public
utility, may institute eminent domain proceedings to obtain these rights under Colorado
Revised Statute §38-1-121. This process provides for an impartial commission or jury of fee
holders in the city or county, as appropriate, to establish the value of the land being acquired
and the amount of damages, if any, awarded to the owners.
28 May 2008
Tri-State Richard Lake to Waverly 115-kV Transmission Line Project
Site Plan Advisory Review Application
Comment 5: Bruce Vogel of the Light & Power Department indicated that if there are to
be any modifications to city of Fort Collins electric facilities, then Bob Hover should be
contacted.
Response: Tri-State will coordinate with Bob Hover should there be any modifications to city
of Fort Collins electric facilities.
Comment 6: Doug Moore of the Natural Resources Department indicated that he is
unaware of any regional open space in this area.
Response: Tri-State agrees and has confirmed that there is no open space, wetlands,
floodplains, or other natural areas within the city of Fort Collins that would be impacted by this
project.
Comment 7: All of the proposed transmission line construction appears to be outside
of the city of Fort Collins limits, in Larimer County.
Response: A portion of the transmission line (approximately 0.4 miles) and the existing
Richard Lake Substation are located within the city limits.
4.2.8 Legal Description of the Site
Richard Lake Substation:
SE Y<, NW '/<, Sec 33, T8N, R68W, 6th P.M.
Approximate Transmission Line Alignment:
Eastern side of the NW'/4, Sec 33, T8N, R68W, 6th P.M.
4.2.9 Tri-State Ownership Information
Tri-State ownership information is listed in Attachment 4.
4.2.10 Estimated Project Schedule
Construction activities will begin after all permits and land rights have been acquired. An
estimated schedule of project activities is shown in Table 4.
Table 4:
Estimated Project Schedule
Activity .
Date
Permit approvals
June -July 2008
Survey
July -October 2008
Complete design/coordination
October -November 2008
Easement acquisition
November 2008-May 2009
May 2008 27
Tri-State Richard Lake to Waverly 115-kV Transmission Line Project
Site Plan Advisory Review Application
Comment 2: Glen Schlueter of the Stormwater Utility Department indicated that this
proposal does not seem to have any impacts on any of the proposed city of Fort
Collins improvements shown in the Stormwater Master Plans north of the city. The
transmission line appears to be north of city regional facilities. There are
improvements planned south of the Anheuser-Busch plant and possibly future
improvements east of Interstate 25 that have not yet been determined.
Response: Tri-State will work with the Stormwater Utility. Department to ensure that the
project complies with stormwater requirements and does not interfere with any stormwater
utility or other utility easements.
Comment 3: Roger Buffington of the Water/Wastewater Department offered the
following comments:
a. There is an existing 12-inch water main around the Richard Lake Substation and
north to County Road 52.
b. Locate the existing 12-inch water main in the area of the Richard Lake Substation
and north to County Road 52 to avoid conflicts during design and construction of
the transmission line.
Response: Tri-State has obtained a utility map identifying the location of the existing 12-inch
water line and other buried utilities. Tri-State will locate the transmission line with a 10-foot
minimum separation from other utilities. Tri-State's contractor will locate all underground
utilities to ensure proper separation prior to construction.
Comment 4: Mike Herzig of the Engineering Department offered the following
comments:
a. The towers must be kept out of the 115-foot-wide right-of-way for County Road 52
and the associated 15-foot-wide utility easements.
b. Please notify the city of Fort Collins Engineering Department before starting work
on the transmission line project.
Response: Tri-State will place the transmission structures outside the 115-foot right-of-way
for County Road 52 and the associated 15-foot-wide utility easements. Tri-State will
coordinate with the Fort Collins Engineering Department during the final design process and
will notify the Department before construction begins.
26 May 2008
Tri-State Richard Lake to Waverly 115-kV Transmission Line Project
Site Plan Advisory Review Application
Topic No.:`
Description
WQ-5
Waste waters from construction operations shall not enter streams, water courses or other surface waters
without use of such turbidity control methods as settling ponds, gravel -filter entrapment dikes, approved
flocculating processes that are not harmful to fish, recirculation systems for washing of aggregates or other
approved methods. Any such waste waters discharged into surface waters shall be essentially free of
settleable material. Settleable material is defined as that material that will settle from the water by gravity
during a 1-hour quiescent period.
WO-6
Erosion control measures will be implemented on disturbed areas, including areas that must be used for
maintenance operations (access ways and areas around structures).
WQ-7
Drainages within the project area (list) will be spanned by the transmission line and no structures will be
placed within the 100-year floodplain..
4.2.6 Neighborhood Meeting
Tri-State set up a project web site (htti)://www.tristateot.orci/Transmission/ovrea/index.cfm)
where interested parties could access and learn more about Tri-State and the purpose and
need for the project. Tri-State developed a questions and answers and project overview
handout and distributed them to interested landowners.
Tri-State held a neighborhood meeting on January 8, 2008, at the PVREA offices. Thirty-five
people attended the meeting. A copy of the meeting sign -in sheet is presented in
Attachment 3.
The meeting was held in an open house format where information stations were established
and equipped with technical experts to address areas of interest including purpose and need,
land and siting, engineering, environment, and electric and magnetic fields (EMF). A formal
presentation was made during the meeting to provide a summary of the project, the routing
process, and to answer questions.
No issues, comments, or concerns were raised at the neighborhood meeting pertaining to the
portion of the proposed project route located within the city of Fort Collins.
4.2.7 Review and Response to City Comments
Tri-State participated in a meeting with the city of Fort Collins Conceptual Review Team on
October 27, 2003, to discuss the proposed Richard Lake to Waverly 115-kV Transmission
Line Project. Tri-State's response to each of the city's comments is listed below. A copy of
the staff comment letter from November 14, 2003, is provided in Attachment 1.
Comment 1: Jenny Nuckols of the Zoning Department indicated that all construction
identification signs may be up to 64 square feet in size, per the city of Fort Collins Sign
Code.
Response: Tri-State will comply with all construction signage notification requirements per
the city of Fort Collins sign code.
May 2008 25
Tri-State Richard Lake to Waverly 115-kV Transmission Line Project
Site Plan Advisory Review Application
Topic No.
Description
LU-4
The contractor shall eliminate, at the earliest opportunity, all construction ruts that are detrimental to
agricultural operations and/or hazardous to movement of vehicles and equipment. Such ruts shall be
leveled, filled and graded, or otherwise eliminated in an approved manner. Damage to ditches, tile drains,
culverts, terraces, local roads and other similar land use features shall be corrected as necessary by the
contractor. The land and facilities shall be restored as nearly as practicable to their original condition.
LU-5
If new access roads are needed, the width of such access roads will require 12 to 14 foot -wide driving
surfaces, with additional width as required for drainage features and cut and fill slopes. Tri-State will
consult with the City should new roads be identified.
Public Health and Safety
HS-1
Tri-State shall comply with applicable regulatory compliance standards for public health and safety.
HS-2
The contractor will apply necessary mitigation to eliminate problems of induced currents and voltages on to
conductive objects sharing a right-of-way, to the mutual satisfaction of the parties involved. The contractor
will install fence grounds, where required, on fences that cross or are parallel to the proposed line.
HS-3
Structure foundation holes will not be left open overnight and will be covered. Covers will be secured in
place and will be strong enough to prevent livestock, wildlife, or the public from falling through and into a
hole.
Noise
N-1
Construction vehicles and equipment shall be maintained in proper operating condition and shall be
equipped with manufacturers' standard noise control devices or better (e.g. mufflers, engine enclosures).
Soils and Geology
S-1
All soils compacted by movement of construction vehicles and equipment, shall be loosened and leveled
harrowing or disking to approximate pre -construction contours and reseeded with certified weed -free
grasses and mulched (except in cultivated fields).
S-2
Movement of construction vehicles and equipment shall be limited to the right-of-way and approved access
routes.
S-3
Excavated material not used in the backfilling of poles shall be spread around each pole or transported off -
site to a Tri-State approved disposal location. Disturbed areas shall then be regraded to approximate pre -
construction contours and reseeded as specified in S-1.
S-4
Topsoil will be removed, stockpiled, and re -spread at temporarily disturbed areas not needed for
maintenance access.
Traffic
T-1
The contractor shall make all necessary provisions for conformance with federal, state and local traffic
safety standards and shall conduct construction operations so as to offer the least possible obstruction and
inconvenience to public traffic.
Water Quality and Erosion
WQ-1
A NPDES Stormwater permit will be obtained and a stormwater pollution prevention plan (SWP3) will be
developed (if the project meets the appropriate criteria).
WQ-2
Construction activities shall be performed by methods that prevent entrance or accidental spillage of solid
matter, contaminants debris, and other objectionable pollutants and wastes into flowing streams or dry
water courses, lakes and underground water sources. Such pollutants and wastes include, but are not
restricted to, refuse, garbage, cement, concrete, sanitary waste, industrial waste, radioactive substances,
oil and other petroleum products, aggregate processing tailings, mineral salts and thermal pollution. All fuel
and fluid spills within this area will be handled in accordance with appropriate stale and federal spill
reporting and response requirements.
WQ-3
Dewatering work for structure foundations or earthwork operations adjacent to, or encroaching on, streams
or water courses shall not be performed without prior approval by Tri-State and appropriate state agencies.
Water and eroded materials will be prevented from entering the streams or watercourses by constructing
intercepting ditches, bypass channels, barriers, settling ponds or other approved methods.
WQ-4
Excavated material or other construction materials shall not be stockpiled or deposited near or on stream
banks, lake shorelines or other water course perimeters where they can be washed away by high water or
storm runoff or can in any way encroach upon the actual water source itself.
24 May 2008
Tri-State Richard Lake to Waverly 115-kV Transmission Line Project
Site Plan Advisory Review Application
Topic No.
Description
WL-2
High biodiversity within designated Neighborhood Species Richness Areas will be maintained to the extent
possible to minimize impacts to plant and wildlife species in the vicinity of the project. Pedestrian surveys
for important habitat or species occurrences will be completed prior to construction, and environmental
protection measures will be specified accordingly to further ensure protection of the natural resources
along proposed transmission line routes.
WL-3
Construction and routine line maintenance will comply with all applicable seasonal restrictions and
protection buffers established by the Colorado Division of Wildlife for migratory birds.
Wetlands
W-1
Welland and riparian areas (of or relating to, or located on, the banks of a river or stream) will be crossed
only in designated and approved locations. Existing access routes shall be used to access the right-of-way
on either side of such areas. All crossing impacts to the wetland will be minimized and mitigated if
necessary. Crossings will not change the overall wetland hydrology, diminish the flood storage capacity of
the wetland, or negatively impact wildlife where possible. Where such avoidance is not possible, the
applicants will hire a qualified biological consultant to conduct a site specific assessment to determine the
level of potential impacts and identify appropriate mitigation measures, and secure the necessary Corps of
Engineers permit if applicable.
W-2
Applicable wetland development standards will be complied with and the project will observe applicable
buffer areas and widths from the boundary of wetlands whenever possible.
W-3
If wetlands are impacted by the project, appropriate mitigation measures will be implemented in
consultation with the Corps of Engineers and a mitigation plan will be developed according to Larimer
County guidelines.
Cultural Resources
CR-1
A Class I file search will be conducted to determine the need for Class III resource inventory of cultural
sites. If needed, a Class III survey shall be conducted along applicable access routes identified for the
project and within the proposed impact footprint of the project prior to the initiation of project construction.
These survey results will be submitted to the Colorado State Historic Preservation Office for review and
concurrence and specific mitigation measures necessary for each site or resource will be determined.
CR-2
Sites identified during the cultural resources survey as eligible for listing on the National Register of
Historic Places will be flagged and/or monitored for avoidance during construction, operation, and
maintenance activities.
CR-3
Prior to construction, all supervisory construction personnel will be instructed on the protection of cultural
resources with reference to relevant laws and penalties, and the need to cease work in the location if
cultural resource items are discovered.
CR-4
Should any previously unknown historic/prehistoric sites or artifacts be encountered during construction, all
land altering activities at that location will be immediately suspended and the discovery left intact until such
time that Tri-State is notified and appropriate measures taken to assure compliance the National Historic
Preservation Act and enabling legislation.
Fire Prevention/Control
FP-1
Construction vehicles shall be equipped with government approved spark arresters.
FP-2
The contractor shall maintain in all construction vehicles a current list of local emergency response
providers and methods of contact/communication.
Land Use
LU-1
The contractor shall limit movement of crews, vehicles, and equipment on the right-of-way and approved
access routes to minimize damage to property and disruption of normal land use activity. Construction
trails not required for maintenance access shall be restored to the original contour and made impassable to
vehicular traffic. Access to the right-of-way is restricted in order to respect the property rights of the
affected land owners.
LU-2
The contractor shall maintain all fences and gates during the construction period. Any fence or gate
damaged during construction will be repaired immediately by the contractor.
LU-3
The contractor shall coordinate with the landowners to avoid impacting the normal function of irrigation
devices during project construction and operation.
May 2008 23
Tri-State Richard Lake to Waverly 115-kV Transmission Line Project
Site Plan Advisory Review Application
Topic No. Description
Aesthetics
A-1
The contractor shall exercise care to preserve the natural landscape and shall conduct his construction
operations so as to prevent any unnecessary destruction, scarring or defacing of the natural surroundings
in the vicinity of the work. Except where clearing is required for permanent works, approved temporary or
permanent construction roads, staging areas or excavation operations, vegetation shall be preserved and
shall be protected from damage by the contractor's construction operations and equipment.
A-2
Any scarring, defacing, damage or destruction of the natural landscape resulting from construction
operations shall be repaired by the contractor to the satisfaction of Tri-State and the affected landowner(s).
A-3
All construction materials, waste and debris shall be removed from the project area in a timely manner.
Burning or burying of waste materials on the right-of-way or at the construction site will not be allowed. All
materials resulting from the contractor's clearing operations shall be removed from the right-of-way.
A-4
To lessen the visual impact of the transmission line the wood structures will be dark and the self-supporting
steel structures will be Corten.
Air Quality
AQ-1
The contractor shall utilize such practicable methods and devices as are reasonably available to control,
prevent and otherwise minimize atmospheric emissions or discharges of air contaminants.
AQ-2
Possible construction related fugitive dust shall be controlled by the periodic application of water to all
disturbed areas along the right-of-way and access roads.
AQ-3
Vehicles and equipment showing excessive emission of exhaust gases due to poor engine adjustments or
other inefficient operating conditions shall not be operated until corrective adjustments or repairs are made.
AQ-4
Tri-State will adhere to the control measures prescribed in the Air Quality Control Commission's
Regulation 1, Article III.C.2.b.iv, which may include, but are not necessarily limited to, planting vegetation
cover, providing synthetic cover, watering, chemical stabilization, furrows, compacting, minimizing
disturbed areas in the winter, wind breaks and other methods or techniques approved by the Air Pollution
Control Division of the Colorado Department of Public Health and Environment.
Vegetation Resources
V-1
Vegetation shall be preserved and protected from damage by construction operations to the maximum
extent practicable. Removal of brush and trees will be limited to those necessary for access, construction
and maintenance of the line and/or pose a threat to safe and reliable operation of the line, or as otherwise
determined by Tri-State and the affected landowner(s). There will be no clear cutting within the right-of-way
unless specifically approved in writing by Tri-State.
V-2
Temporarily disturbed areas will be seeded using a prescription recommended by the Natural Resources
Conservation Service, Ag Extension Office and/or the County Weed Control Officer. All seed will be
certified weed -free.
V-3
Water tum-off bars or small terraces shall be installed across all temporary construction access roads and
trails on hillsides to prevent erosion and facilitate natural revegetation of the trails.
V-4
On completion of the work, all work areas, except any permanent access roads/trails, shall be regraded, as
required, so that all surfaces drain naturally, blend with the natural terrain, and are left in a condition that
will facilitate natural revegetation, provide for proper drainage and prevent erosion.
V-5
To minimize the spread of noxious weeds, construction crews will limit transport of seeds to agricultural
lands or rangelands by cleaning construction equipment and vehicles before entering the construction
area.
V-6
Further research and consultation with CNHP will be conducted regarding the identified Rare Vegetation
Types areas on the Larimer County Environmental Map. Specific mitigation will be developed as
appropriate for the species of concern within these areas.
Wildlife Resources
WL-1
In order to preclude avian electrocutions and minimize collision risk, Tri-State will incorporate state-of-the-
art design practices, as outlined by Avian Power Line Interaction Committee (APLIC). Swan Flight
Diverters will be installed on portions of the near identified habitat areas of concern.
22 May 2008
Tri-State Richard Lake to Waverly 115-kV Transmission Line Project
Site Plan Advisory Review Application
The operation and maintenance phase of the transmission line will involve two Tri-State
personnel to patrol and inspect the transmission line twice a year. Any repair may involve
more personnel depending on the nature of the work. Day-to-day operation of the
transmission line will be directed by system dispatchers from Tri-State's operation center.
4.2.4 Description of Rationale Behind the Assumptions and Choices Made
by the Applicant
PVREA approached Tri-State, the co-op's power supplier, about construction of the new
transmission line due to increased electric loads in the area and because of reliability
concerns of the existing radial 115-kV line. Use and dependence on the current line is
reaching a critical level. To maintain acceptable voltage levels and increased reliability, a
redundant source is required.
The transmission line has been routed along the BNSF railroad in an industrial district. The
project location meets project objectives while minimizing environmental impacts. There are
no known sensitive environmental resources within the city limits that would be affected by
the proposed project.
4.Z5 Description of How Conflicts Between Land Uses or Disturbances to
Wetlands, Natural Habitats and Features and/or Wildlife Will Be
Avoided to the Maximum Extent Feasible
Tri-State implements environmental protection measures (EPMs) for every construction
project as standard operating procedure. EPMs are measures taken during the construction
and maintenance phases of the project to avoid or minimize environmental impacts. Tri-State
uses construction inspectors and environmental monitors during construction to ensure that
the EPMs are strictly followed.
Table 3 lists the EPMs for the project. The EPMs are designed to reflect all applicable local,
state and federal legislative environmental compliance requirements and laws. They will be
refined to include any project -specific conditions that may be suggested by the city.
Table 3:
Tri-State Richard Lake to Waverly 115-kV Transmission Line Project Environmental Protection Measures
Topic No. Description
General
G-1
The contractor shall comply with all federal, state and local environmental laws, orders and regulations.
Prior to construction, all supervisory construction personnel will be instructed on the protection of cultural
and ecological resources. To assist in this effort the construction contract will address: a) Federal and state
laws regarding antiquities, plants and wildlife, including collection and removal; and b) the importance of
these resources and the purpose and necessity of protecting them.
G-2
Prior to construction of the project, qualified independent contractor(s) shall be retained by Tri-State to
meet with project engineers and agency representatives to review design plans, discuss areas of
environmental sensitivity within the project area, and, in particular, those areas where a monitor must be
present during construction. Where needed, the contractor(s) will meet with the engineer(s) and agency
representatives in the field to determine methods to avoid or minimize impacts to sensitive resources to the
greatest extent possible.
May 2008 21
Tri-State Richard Lake to Waverly 115-kV Transmission Line Project
Site Plan Advisory Review Application
4.Z3 Estimate of Number of Employees for Business, Commercial and
Industrial Uses
Construction of the transmission line will include the following activities performed in
sequence by crews progressing along the length of the transmission line:
• Soil exploration
• Permission to survey
• Surveying
• Land rights acquisition
• Structure site work
• Materials hauling
• Foundation construction
• Forming/placing foundation concrete
• Structure assembly and erection
• Ground wire and conductor stringing
• Cleanup
• Revegetation
Qualified, licensed electrical contractors will be selected to construct the project. The
approximate number of personnel and equipment required for construction of the
transmission line is shown on Table 2.
Table 2:
Anticipated Construction Equipment and Personnel Required
Activity
Personnel
(number)
Equipment
Soil exploration
3-4
1 truck with 4° auger, 2 pickup trucks
Permission to survey
1
1 vehicle
Surveying
8
24 pickup trucks
Land rights acquisition
1
1 vehicle
Structure site work
34
1 bucket truck, 1 pickup truck
Materials hauling
8-12
2 tractor trailers, 2 hydrocranes, 3 pickup trucks, 2 Flatbed trucks
Foundation construction
1 truck w/ auger, crane digger, 2 pickup trucks, 1 Bobcat
Forming/placing of foundation concrete
8
1 concrete truck, 2 pickup trucks, 1 hydrocrane
Structure assembly and erection
6
1 hydrocrane, 2 pickup trucks, 1 Flatbed truck, 1 crane
Ground wire and conductor stringing
15-25
1 reel trailer, tensioner, puller, 3-5 pickup trucks, 1 winch truck,
1 digger, 1 flatbed truck, 2 tractor trailers, 2 bucket trucks
Cleanup
3
1 tractor,1 flatbed truck, 1 Bobcat
Revegetation
3
1 tractor, disc, 1 pickup truck, 1 flatbed truck, 1 drill seeder
20 May 2008
Tri-State Richard Lake to Waverly 115-kV Transmission Line Project
Site Plan Advisory Review Application
Land Use
Goal A3: Mountain Vista will have an Employment and Industrial District with a variety of
business types and sizes and will be designed in a manner that is compatible with
surrounding land uses.
The proposed project is an appropriate use within the industrial district and is compatible with
surrounding land uses.
4.2.1.5 Community Appearance and Design
Goal Cl: Important view corridors and vistas in Mountain Vista will be protected and
enhanced.
The proposed project is located in an industrial district within a setting dominated by the
existing Richard Lake Substation, the exiting Anheuser-Busch complex, and existing
transmission facilities located to the south of Richard Lake Substation. The Mountain Vista
Subarea Plan (Section 2.5) seeks to protect views of the foothills and mountains and
specifically identifies views to the southwest that are outside of the industrial district and
project area. The proposed project is not anticipated to significantly alter or negatively impact
the existing view corridor within this industrial district.
4.2.2 Description of Proposed Open Space, Wetlands, Natural Habitats
and Features, Landscaping, Circulation, Transition Areas, and
Associated Buffering On Site and In the General Vicinity of the
Project
The project is located within an industrial district and is bounded on the west by agricultural
land and on the east by the Burlington Northern Santa Fe (BNSF) railroad tracks. There are
no known areas of designated open space, wetlands, natural habitats and features,
circulation, transition areas, and associated buffering on site in the vicinity of the project. A
review of the Fort Collins Natural Habitats and Features Inventory Map indicated that the
project site is not within 500 feet of an area or feature identified as a natural habitat or feature
and does not possess characteristics of wetlands, riparian areas or foothills forest. The
existing PRPA-owned Richard Lake Substation is landscaped with trees around the existing
fenceline. The project will maintain the integrity of current landscaping with minimal impacts.
Tri-State will replace any disturbed landscaping after construction.
May 2008 19
Tri-State Richard Lake to Waverly 115-kV Transmission Line Project
Site Plan Advisory Review Application
Tri-State has coordinated closely with Platte River Power Authority (PRPA) regarding the
necessary expansion at Richard Lake Substation. Fort Collins Utilities has reviewed and
approved Tri-State's substation expansion plan. PRPA will be installing two new 115-kV
circuit breakers to expand the ring bus and maintain the reliability of service to Anheuser-
Busch.
4.2.1.2 Industrial Districts
PRINCIPLE ID-1: Industrial Districts will provide places for a wide range of industrial
and commercial uses that do not need or are not suited to high public visibility.
Policy ID-1.1 Land Uses. Industrial land uses such as manufacturing, assembly plants,
primary metal and related industries, vehicle -related commercial uses such as auto repair,
maintenance and storage, other types of commercial operations, warehouses, outdoor
storage yards, and distribution facilities, are appropriate for an Industrial District. Industrial
Districts should include a variety of flexible sites for small, local, and startup business and
industry, as well as large national or regional enterprises.
The proposed project is an allowable and appropriate use within the industrial district
(Figure 4).
4.2.1.3 Rural Lands
PRINCIPLE RUL-2: Rural lands and agricultural land uses should remain a valuable
component of Fort Collins' economy, culture, and heritage.
Agricultural land is located to the west of the proposed route and will be unaffected. The
project is located within an industrial district.
4.2.1.4 Mountain Vista Subarea Plan
The proposed project is also located within the area covered by the Mountain Vista Subarea
Plan, which has established additional guidelines related to the City Plan. No constraints
identified within the Mountain Vista Subarea Plan are present within or adjacent to the
proposed route. The proposed project is consistent with the visions, goals, principles, and
policies of the Mountain Vista Subarea Plan as described below.
The proposed project is consistent with the Subarea Plan principals and policies related to
economic sustainability and development, environment, and growth management as
described in Section 4.2.1.1, which details conformance with the City Plan.
16 May 2008
Tri-State Richard Lake to Waverly 115-kV Transmission Line Project
Site Plan Advisory Review Application
Growth Management
PRINCIPLE GM-4: Investment in capital facilities and services will be reviewed
comprehensively and made within a framework that balances and evaluates the costs
and the relative importance of competing needs.
Policy GM-4.1 City Commitment to Providing Capital Facilities. Recognizing the limits of
the City's financial resources, the City commits to deriving the greatest value possible from its
investments in infrastructure.
Policy GM-4.1A City Commitment to Providing Capital Facilities. The City will seek to
prioritize existing deficiencies, ensure maintenance of existing capital facilities, and remedy
existing insufficiencies in facility provision over time as resources allow.
Richard Lake Substation must be expanded with the addition of two 115-kV circuit breakers
for the dual purpose of providing adequate transmission line protection for the new 115-kV
transmission line proposed for construction to Waverly and to maintain the reliability of
service to Fort Collins Utility customers served from the substation, including Anheuser-
Busch.
PRINCIPLE GM-9: The City's ongoing involvement in related planning processes in the
region is another important way to achieve Fort Collins' vision.
Policy GM-9.1 Area -Wide Collaboration. The City will be an active participant in county-,
regional-, and state-wide decision -making and policy -setting for major land use, utilities,
transportation, housing, environmental management, and telecommunication issues that
cross jurisdictional boundaries. The protection of the interests of all segments of the city's
population and economy and the quality of life in urban areas, will guide the City's activities
as a regional cooperator.
Policy GM-9.3 Collaboration of Service Providers. Service providers should coordinate
closely with each other in needs assessment, facility siting and other matters to ensure
continuing delivery of effective and efficient urban services. Where feasible, service providers
will explore the possibility of consolidating agencies and/or jurisdictions to minimize the
duplication of services.
The proposed project addresses Poudre Valley Rural Electric Association's (PVREA) request
to administer reliable electric service to its consumers in the vicinity of the project. Tri-State
has worked closely with PVREA from the inception of the proposed project and has
coordinated field evaluation and power system planning efforts as applicable. Tri-State has
coordinated with Larimer County and received their approval to proceed with the project in
Larimer County.
May 2008 15
Tri-State Richard Lake to Waverly 115-kV Transmission Line Project
Site Plan Advisory Review Application
Noise pollution associated with the proposed project is anticipated to be minimal. Typical
noise from construction operations and equipment is expected. Noise from heavy machine
during construction of the transmission line may create a short-term nuisance to nearby
residents. Tri-State will mitigate this nuisance by ensuring that construction vehicles and
equipment are maintained in proper operating condition and equipped with manufacturers'
standard noise control devices or better (e.g., mufflers, engine enclosures).
PRINCIPLE ENV-8: The City will minimize potentially hazardous conditions associated
with flooding, recognize and manage for the preservation of floodplain values, adhere
to all City mandated codes, policies, and goals, and comply with all State and Federally
mandated laws and regulations related to the management of activities in flood prone
areas.
The proposed project is not located within the boundaries of a 100-year floodplain.
Policy ENV-8.6 Watershed Approach to Stormwater Management Policy. In addition to
flood control and drainage functions, stormwater systems will be designed to minimize the
introduction of human caused pollutants. Educational programs and demonstration projects
will be pursued to enhance public understanding of pollution prevention efforts. Tributary
systems will be designed for water quality control, with appropriate use of buffer areas, grass
swales, detention ponds, etc. Receiving water habitat restoration and protection will be
included in stormwater master plans, in conjunction with habitat mapping efforts.
Tri-State will comply with county, city, state and federal stormwater management permitting
and plan requirements. Best management practices (BMPs) for soil sedimentation and
erosion control will be implemented on any disturbed areas. Water quality protection
measures are further discussed in Table 3 in Section 4.2.5.
PRINCIPLE ENV-10: The City will apply cost-effective pollution prevention and zero -
waste strategies that will help protect all environmental resources, including air, soil,
and water and accelerate the community's ability to meet the City's adopted goal of
diverting 50% of the waste stream from disposal in landfills by 2010.
Policy ENV-10.1. Hazardous Materials and Waste. The City will assertively apply pollution
prevention -based management in its operations and be committed to acting as a resource to
assist the community in preventing pollution and eliminating hazardous chemical usage, and
for enforcing environmental regulations.
Hazardous materials are not anticipated to be generated during the proposed project. Other
waste, including construction materials and debris, shall be removed from the project area in
an orderly and timely manner. Any fuel and fluid spills from construction equipment will be
reported and handled in accordance with applicable regulatory spill reporting and response
requirements (see Table 3 in Section 4.2.5).
14 May 2008
Tri-State Richard Lake to Waverly 115-kV Transmission Line Project
Site Plan Advisory Review Application
Policy ENV 1.2. City-wide Approach. The City's primary approach to improving air pollution is
to reduce total city-wide emissions over the long term. The City's secondary approach is to
assure that localized air pollution exposures conform to adopted health standards.
The operation of the proposed project will not adversely affect air quality. There will be minor
temporary impacts on air quality during project construction from fugitive dust generation and
vehicle emissions, but these impacts are expected to be temporary and insignificant.
Tri-State will comply with state requirements for controlling fugitive dust emissions during the
construction of the project. Tri-State's Standard Environmental Protections Measures (EPMs)
(Table 3 in Section 4.2.5) address air quality preservation and mitigation.
Vehicles and equipment shall operate so as to avoid excessive emission of exhaust gases
and shall be operated in accordance with mitigation measure AQ-3 in Table 3, Section 4.2.5.
PRINCIPLE ENV-6: Natural habitat/ecosystems (wildlife, wetlands, and riparian areas)
will be protected and enhanced within the developed landscape of Fort Collins.
Policy ENV-6.1 Protection and Enhancement. The City's regulatory powers will be used to
preserve, protect, and enhance the resources and values of natural areas by directing
development away from sensitive natural features —such as wetlands, riparian areas and
wildlife habitat. When it is not possible to direct development away from natural areas, these
areas will be protected in the developed landscape.
Policy ENV-6.2 Floodplains. The City will preserve and protect natural areas in the 100-year
floodplain of the Poudre River, Spring Creek, Fossil Creek, Boxelder Creek and other
waterways.
The portion of the proposed project within the city will be developed within an existing
industrial area and will not impact any sensitive natural features, natural areas, or floodplains
within the city limits. There is no Federal Emergency Management Agency or city -designated
floodplain that will be crossed by the proposed project within the city.
Tri-State has initiated consultation with the U.S Fish and Wildlife Service (USFWS) and the
Colorado Division of Wildlife (CDOW) on this project (see Attachment 2). Additional
consultation with both agencies will take place to obtain feedback on specific mitigation
measures for the project and to ensure that their input is reflected in the project's design and
construction plans.
PRINCIPLE ENV-7: Community noise standards will be enforceable, measurable, and
realistic.
Policy ENV-7.1 New Policy Development. Comprehensive policies will be developed to
guide the implementation of programs and regulations to prevent noise pollution.
May 2008 13
Tri-State Richard Lake to Waverly 115-kV Transmission Line Project
Site Plan Advisory Review Application
4.2.1.1 Policies and Principles: Community -wide
Land Use
PRINCIPLE LU-4: More specific subarea planning efforts will follow the adoption of
these City Plan Principles and Policies which tailor City Plan's city-wide perspective to
individual neighborhoods, districts, corridors, and edges.
Policy LU-4.1 Planning within the Context of City Plan. City Plan establishes citywide policies.
Subarea plans are needed to help implement City Plan by applying its general, city-wide
policies to a specific subarea.
The proposed project is located within the area covered by the Mountain Vista Subarea Plan,
which provides land use, design, environmental and transportation recommendations for
vacant lands to the northeast. Conformance of the proposed project to the Mountain Vista
Subarea Plan is discussed in detail in Section 4.2.1.4 of this document. The proposed project
is consistent with the principles and policies of the Mountain Vista Subarea Plan.
Economic Sustainability and Development
PRINCIPLE ECON-1: The City will pursue a balanced and sustainable economic
development program.
Policy ECON-1.2 Economic Development Policy. The City will work with the business
community and various business organizations to develop specific plans, goals and
objectives in order to continue to encourage and support economic development and
economic opportunities which provide primary employment, increase private investment
within the community, and improve the quality of life for Fort Collins' residents.
Policy ECON-1.2g Economic Development Policy Goals. Focusing on planning and the
provision of municipal services and facilities such as streets and utilities as the City's role in
dealing with prospective expansions or relocations.
The proposed project will support future economic development in the area by improving
electric service and providing power delivery infrastructure to increase electric reliability and
capacity.
Environment
PRINCIPLE ENV-1: Continually improve Fort Collins' air quality as the City grows.
Policy ENV-1.1 Air Quality Plan. The City will adopt and implement a comprehensive Air
Quality Plan that addresses the following issues:
a. Emissions from vehicles
b. Emissions from commerce and industry
c. Wood burning
d. Visual air quality
e. Certain indoor air pollutants and greenhouse gases
12 May 2008
Tri-State Richard Lake to Waverly 115-kV Transmission Line Project
Site Plan Advisory Review Application
4.0 Submittal Requirements
This section provides information required for submittal by the city of Fort Collins, including
the list of affected landowners and a statement of planning objectives in conformance with
city criteria.
4.1 Names and Addresses of Landowners within 800 Feet
The Richard Lake Substation site is located on property owned by:
CITY OF FORT COLLINS
P.O. BOX 580
FORT COLLINS, CO 80521
The property crossed by the transmission line is owned by:
JOHN MARTZ
ANHEUSER-BUSCH, INC.
8000 MARYLAND AVENUE, SUITE 350
CLAYTON, MO 63105
The only other property owner within 800 feet of either the transmission line or the
substation is:
CHARLES KELLER
LORI KELLER
C/O CARL KELLER
2316 N COUNTY ROAD 9
FORT COLLINS, CO 80524
4.2 Statement of Planning Objectives
4.2.1 Statement of Appropriate City Plan Principles and Policies Achieved
by the Proposed Project
An update to the Fort Collins City Plan was adopted in May 2004 (Fort Collins 2004). The
City Plan contains a comprehensive set of principles and policies intended to guide land use
within the city limits. Many of these principles and policies are directed at residential
development, transportation or other areas that are not directly related to the proposed
project. The specific principles and policies that relate most directly to the proposed project
are presented below. In general, the project is consistent with relevant adopted city plans,
including the City Plan and the Mountain Vista Subarea Plan (Fort Collins 1999).
May 2008 11