HomeMy WebLinkAboutNORTH COLLEGE MARKETPLACE, WETLANDS - FDP - 39-08/A - CORRESPONDENCE - (5)North College Marketplace Project
Punch list items per email dated 4.16.10 from URA
Stormwater Items
Issue:
Solution:
1.
The wetland will have 5 to 6 inches of standing water in the pond
contractor to lower storm line A out fall to elevation 4971 which .
because of the reverse grade in the outfall pipe.
will drain south wetlands as originally engineered for. Lowering
will occur 4.27.10-4.30.10.
2.
There is standing water in more than 15%of the wetland even with
item in correct. Mitigation report requires 80%vegetation
the pond being pumped.
established by the end of year 3.
3.
The erosion control fabric on the slopes of the pond and the water
project engineer revised construction plan set for alternative
quality berm have not been installed as shown on sheet C-141.
erosion control method to be implements 4.27.10-4.30.10
4.
Scourstop has not been installed at the outlet of all the pipes into
1 remaining scourstop at south end of filtration pond to be
the water quality pond.
installed by 4.30.10
S.
The pans in the water quality pond are holding water.
pans were constructed per plans.
6.
There is seepage from the irrigation ditch in the northwester corner
comment noted - no action required by developer.
of the wetland.
7.
Manhole A2 in Willox needs to have steps for access.
steps to be installed by 4.30.10
8.
Orifice plate and trash collector installed at outfall point in south wetlands
plate and collector to be installed by 4.30.10
9.
Orifice plates installed on all head walls at end of concrete pans in filtrate
plates to be installed by 4.30.10
pond
Wetlands Items
Issue:
Solution:
1. Planting of all willow stakes at the bottom of the berm with wetlands
boundary wetland.
completed by contractor.
2. Relocation of Limit -of -Development fencing (orange construction
fence) along area as defined in the final plans.
completed by contractor.
3. Cut green outfall drain pipes to match slope from forebay into wetlands.
completed by contractor.
4. Remove all survey and grade stakes from the wetlands property
completed by contractor.
5 Finish grading and restore the area at the southeast storm drain outlet in
the south.
completed by contractor.
6. Remove all trash from the wetlands property
completed by contractor.
7 Irrigation system has to be running
completed by contractor.
King Soopers Property (Filtration Area) Items:
Issue:
Solution:
1.
Fore bay: the bottom is scarified
completed by contractor
2
The scouring fabric has to be installed
completed by contractor
3
Wetlands/uplands plantings installed
completed by contractor
4.
Wetlands seeding to be completed
completed by contractor
5
Irrigation system has to be running
completed by contractor
4/27/2010 File:URA Punchlist Matrix for NCMP
Page 1 of 1
Steve Olt - North College Marketplace Wetlands Acceptance Punchlist Matrix
From: Blaine Rappe <brappe@lovelandcommercial.com>
To: <gschlueter@fcgov.com>, <esaunders@fcgov.com>
Date: 4/27/2010 1:39 PM
Subject: North College Marketplace Wetlands Acceptance Punchlist Matrix
CC: <mfreeman@fcgov.com>, Christina Vincent <cvincent@fcgov.com>, <solt@fcgov.com>,
Eric Holsapple <eholsapple@lovelandcommercial.com>, Nathan Klein
<nklein@lovelandcommercial.com>, <jlaugel@connellresources.com>, John Warren
<jwarren@connellresources. com>
Glen & Erica,
Attached please find the punchlist for the North College Marketplace Wetlands Acceptance as originally drafted
by the URA. Per our meeting last Tuesday afternoon I compiled the punchlist into matrix so all parties are aware
of the solution and completion date. As you will see final completion date is 4.30.10. Please contact me for any
questions, thank you.
Blaine Rappe, CCIM & CPM
Loveland Commercial, LLC
1043 Eagle Drive
Loveland, CO 80537
Phone 970-667-7000 ext. 101
Fax 970-635-2514
Email: brappeOlovelandcommercial.com
www.lovelandcommercial.com "
file://C:\Documents and Settings\solt\Local Settings\Temp\GW}0000l.HTM 4/27/2010