From: Randy Maizland
To: Eckman, Paul; Olt, Steve
Date: 3/11/2008 9:07:53 AM
Subject: Re: ROW - license agreement - King Soopers Fueling Station
Hi Paul,
Steve Olt is back in now so I want to revisit this idea with you. There has been a development review
application submitted for the King Soopers Fueling Station at Taft & Elizabeth. Standard PDP review
process and we'll have a DA and issue a DCP for construction so there definitely will be an opportunity to
place conditions on the project.
They have agreed to dedicate the requested ROW but street widening will not take place at this time.
What would be the best way to allow the applicant to use the ROW in the interim condition until the City
widens the road (i.e. revockable permit, license agreement, DA language etc....)? The ROW would only
be used for concrete pavingto provide additional room to pass on the outside edge of the fuel pumps.
There will be no structures placed in the ROW and the pumping stations will still be fully operational in the
ultimate condition when the ROW is used for street widening.
Thanks, Randy
>>> Paul Eckman 3/4/2008 2:33 PM >>>
Would this require a development application? Would we be able to impose a development condition on
our approval?
>>> Randy Maizland 3/4/2008 1:15 PM >>>
Hello Paul,
The King Soopers on Taft Hill & Elizabeth purchased the old gas station at this intersection. They want to
rebuild with a new King Soopers fueling station but their "cookie cutter" fueling station layout doesn't fit
entirely within the site after they dedicate the new ROW the City needs for future widening. They want
permission to use the ROW in the interim condition until the street is eventually widened out. There would
not be any structures in the ROW, only concrete pavement and landscaping. Once the street widening
occurs they would essentially lose a lane for passing around the outer most pump station which they are
OK with. What I need help with is figuring out what is the best way to grant permission to use this ROW in
the interim condition ? Revockable encroachment permit, license agreement etc...
Please give me a call at 2292 at your earliest convenience so we can discuss this
Thanks, Randy