Loading...
HomeMy WebLinkAboutKING SOOPERS FUELING STATION (CEDARWOOD PLAZA) - PDP - 40-07 - CORRESPONDENCE - (36)ground sign has to be at least 15' from an interior side lot line. If the facility is addressed off Elizabeth, then the south lot line is the rear lot line and the Taft Hill sign meets this requirement, but the Elizabeth sign is then closer than 15' to the west lot line, which becomes the side lot line. If the address is off Taft Hill, then the opposite is true (the Elizabeth sign is ok, but the Taft sign isn't. Response: Because of the new dedicated right-of-way and the small landscaping buffers at the interior side lot lines a monument sign is proposed in the proposed dedicated right of way area at the northeast comer of the site. Please see the previous comments that address the monument signage. Sincerely, Matthew F. Duhaime P.E., P.L.S Project Manager Galloway, Romero & Associates File No. ksl12-Comment Respons letter2.doc CC: File Galloway & Company, Inc. • Phone 303.770.8884 • Fax 303.770.3636 • 5350 DTC Parkway, Greenwood Village, CO 80111 • www.gallowayUS.com Number' 89 Created: 4/1/2008 [4/1/08] See red -line comments on the Site & Landscape Plan. Be sure that any revisions to the Utility Plan sheets are also reflected on the Site and Landscape Plan sheets Response: Site and Landscape plan changes are reflected on the utility plan set. Department: Stormwater-Water-Wastewater Issue Contact: Roger Buffington Topic: Water/Wastewater Number: 70 Created: 4/1/2008 [4/1/08] It appears that the existing sewer service connects to the manhole in Elizabeth; therefore, to abandon the service, excavate and cap/grout service on site AND install a water- tight plug in the manhole. Response: Utility plan note # directs the contractor to plug the service at the main. Number: 71 Created: 4/1/2008 [4/1/08] Frost free yard hydrants not allowed unless proper backflow prevention is provided. Contact John Nelson (221-6677) for information regarding notes and details to be included on utility plans. Response: Note has been added directing the contractor to install a back flow preventer between the meter and the yard hydrant. Number: 72 Created' 4/1/2008 [4/1/08] Provide a complete set of utility plans with the re -submittal. Response: See submittal set. Number: 73 Created: 4/1/2008 [4/1/08] Add note to coordinate with Water Utilities (416-2165) on re-routing of the water service and re -location of the meter pit. Response: Note has been added. Department: Zoning Topic: Zoning Number: 52 Created: 3/25/2008 Issue Contact: Peter Barnes [3/25/08] Per Section 3.8.7(E)(13), only 2 signs are allowed on the canopy, one on the east fascia and one on the north fascia. The plan shows 4 such signs, one on each fascia. The south and west signs need to be removed. Per Section 3.8.7(E)(8), the maximum allowed height of logo and cabinet signs is 30", the plan indicates that the logos on the canopy are 33" tall. Also, the maximum size allowed for the one canopy sign on the north fascia is 12 square feet (Sec. 3.8.7(E)(13), but the logo and letters combined is more than 18 square feet (the logo can't be considered as one sign and the letters as another, because then there would be two signs when only one is allowed. So as one sign, it can't exceed 12 square feet) Response: Signage on the canopy fascia has been revised. Number: 53 Created: 3/25/2008 (3/25/08] Both of the monument signs appear to be in the ROW once the additional ROW is dedicated. They have to be on private property. Additionally, Sec. 3.8.7(G)(2) requires that a Galloway & Company, Inc. • Phone 303.770.8884 • Fax 303.770.3636 • 5350 DTC Parkway, Greenwood Village, CO 80111 • www.gallowayUS.com Q interim walk and the construction of a new 6 foot ultimate walk for review. This payment will be provided in the development agreement and will be due at the time of building permit. If you do not wish to escrow money for an ULTIMATE sidewalk you must construct it in the ultimate location with this project (at the new ROW line). Response: An engineers cost estimate for the removal and construction of a new walk are included inn this submittal. Number: 82 Created: 4/1/2008 [4/1/08] Please place a note on the Utility Plan that states that all interim improvements within the ROW are subject to the terms and conditions of the development agreement. The temporary use of the ROW for the fuel station will be outlined in the development agreement language. Response: Note has been added at two locations on the utility plan. Number: 83 Created: 4/1/2008 [4/1/08] Please call out the pedestrian ramps on the Utility Plan sheet with the LCUASS standard detail. Including detail for truncated domes. Response: Pedestrian ramps are referred to LCUASS standard detail Number. 84 Created: 4/1/2008 [4/1/08] All LCUASS typical construction details must be provided at Final Compliance submittal. All detail sheets shall include all applicable LCUASS details for ROW construction and should be located at the end of the plan set with signature blocks. Be sure to use the latest 2001 adopted LCUASS details. Response: All LCUASS construction details are included in the planning and utility sets. Number: 85 Created: 4/1/2008 [4/1/08] Please clearly show/label and dimension the existing and new proposed ROW on the Utility Plan sheet. Response: Dimensions have been added Number: 86 Created: 4/1/2008 [4/1/08] Please label the sidewalks - Tie back into existing walk - at both ends and call out the radius for the transitions. Response: Dimensions have been added Number. 87 Created: 4/1/2008 [4/1/08] Some of the text is too small to read on the Utility Plan sheet. Please enlarge. Response: Text has been enlarged Number. 88 Created: 4/1/2008 [4/1/08] Clearly show and label existing or proposed water and sewer service connections on the Utility Plan sheet. Response: Existing and proposed water and sewer services are labeled. Galloway & Company, Inc. • Phone 303.770.8884 • Fax 303.770.3636 a 5350 DTC Parkway, Greenwood Village, CO 80111 a www.gallowayUS.com Number:38 Created:12/31/2007 [4/1108] Same [12/31/07] Please add a standard signature block to sheet 5. Response: Standard signature block has been added to sheet 5-(grading and drainage plan) Number. 75 Created: 4/1/2008 [4/1/08] Only Sheet 4 of the Utility Plan set was re -submitted for review. This was discussed by telephone with Galloway. My review of sheet 4 only has been completed; however, all other comments on the remaining sheets will be carried forward. Please re -submit a complete revised set of Utility Plans with your next submittal. All comments clouded in green are carry- over repeat comments. All comments clouded in red are new comments. Response: Understood Number: 77 Created: 4/1/2008 [4/1/08] A ROW dedication legal description was e-mailed to me for review. A review fee of $250 must be submitted as well. The bearings and distances on the legal description do not match those shown on the Utility Plan set. Please revise to match and resubmit the revised legal description with completed and signed deed of dedication. I can provide you with the dedication template in a Word document by email on request. Send request to rmaizland(a'fcgov.com. Response: A revised legal description and exhibit are included in this resubmittal. The review fee is included in this submittal, the utility and site plans both show the corrected bearings and distances. Number: 78 Created: 4/1/2008 [4/1/08] Please submit a signed letter from Cedarwood Plaza (prior to scheduling a hearing) indicating that they are OK with the cross lot access arrangement proposed on the plans on the NW corner of the parcel. Response: King Soopers is in the process of obtaining a cross access agreement from the owners of the Cedarwood Plaza. A copy of the agreement will be made available before final approval. Number: 79 Created: 4/1/2008 [4/1/08] Monument signs may not encroach into the new ROW area. Please pull these signs out of the ROW limits. Response: The monument signs in the right of way have been removed. One monument sign is in the right of way at the northeast corner and is part of the variance request. Number: 80 Created: 4/1/2008 [4/1/08] Please label and call out both of the new driveway cuts per LCUASS DWG 707. Call out the radius at the driveway. Response: The new driveway cuts are labeled with the radius and LCUASS 707 reference. Number: 81 Created: 4/1/2008 [4/1/08] The sidewalk being shown on the plans will be considered and INTERIM sidewalk since i, will need to be removed and replaced when the street is widened in the future. If you wish to construct this sidewalk in the INTERIM location you will also be required to escrow funds for the future ULTIMATE sidewalk. Please provide an engineers cost estimate for the removal of the Galloway & Company, Inc. 9 Phone 303.770.8884 • Fax 303.770.3636 • 5350 DTC Parkway, Greenwood Village, CO 80111 • www.gallowayLlS.com Number: 29 Created: 12/31/2007 [4/1/08] Same - Only sheet 4 was re -submitted. Incomplete plan submittal. [12/31/07) Two City of Fort Collins bench marks are required on the plans. Please provide this information on the cover sheet. Response: Two Fort Collins bench marks are identified on the cover sheet. Number: 30 Created: 12/31/2007 [4/1/08] Same - Incomplete re -submittal package. [12/31/07] Please use the standard General Notes (1-48) from L.C.II.A.S.S. Appendix E. Available online. List all variance requests under note 48 (i.e. driveway - intersection separation etc...). Response: General Notes 1-48 are included on both the planning and utility cover sheets. Variance request under note 48 are included. Number. 32 Created: 12/31/2007 [4/1/08] Same - only sheet 4 was re -submitted. [12/31/07] Please provide the standard indemnification statements on the cover sheet (provided with redlines). Please add all consultant info on the cover sheet (i.e. Traffic Eng, Geotech, Architect etc...). Response: Standard indemnification statements are included on both the planning and utility cover sheets. At this time there are no other consultants. Number: 33 Created: 12/31/2007 [4/1/08] Same [12/31/07] Please label in bold print FOR REFERENCE ONLY on the bottom right corner of sheet 2. Response: Note added to sheet 2 (Alta Survey) Number: 34 Created: 12/31/2007 [4/1/08] Same [12/31/07] Please see the.red-lines, Sheet 4, regarding ROW & Easement dedications and sidewalk location and width requirements. Response: ROW bearing and distances have been added. Number: 37 Created: 12/31/2007 [4/1/08] 1 will defer to Stormwater regarding detention or water quality requirements. [12/31/07] No storm water detention/water quality being shown. From previous meetings and the conceptual review meeting I was under the impression that at a minimum, some water quality detention would be required, maybe in the parkway strip, if not on -site. It appears all drainage is surfaced drained directly to the street through the access driveways?? I will defer to Stormwater for comments regarding drainage detention requirements on this site. Response: Water Quality will be provided by the landscaping strips between the curbs and sidewalks. Galloway & Company, Inc. • Phone 303.770.8884 • Fax 303.770.3636 • 5350 DTC Parkway, Greenwood village, CO 80111 • www.gallowayUS.com Number: 59 Created: 3/26/2008 [3/26/08] The 2 proposed monument signs (items #31) cannot be in the street rights -of - way. Response: Both monument signs have been removed. A proposed monument sign is shown at the Taft Hill and Elizabeth St. comer, the location is witf in the new dedicated right of way. King Soopers would like to include this monument sign as part of the interim agreement with the sidewalks and handicap ramps. Placing a monument sign behind the new dedicated right of way would place them out of sight from the traffic along the adjoining streets. Number. 60 Created: 3/26/2008 [3/26/08] To ensure full legibility of the Site Plan, please avoid overlapping of text with line work and shading. Response: Overlapping text has been removed. Number: 61 Created: 3/26/2008 [3/26108] Is Sheet 3 of 7, Site Details included in the Utility Plan set where it really Response: Site details are included in both the planning and utility sets. Department: Engineering Issue Contact: Randy Maizland Number: 25 Created: 12/31/2007 [4/1/08] Legal description for ROW dedication was submitted by email however the review fees and deed of dedication have not been provided. Legal does not match Utility Plan regarding bearings and distances shown. Please revise the legal (or plans) to match and submit the revised legal, deed of dedication and $250 review fee with your next submittal. [12/31/07] At the June 18 Conceptual Review meeting, it was stated that new additional ROW dedications would be needed for both South Taft Hill Road and West Elizabeth Street, 57.5 feet from centerline and 42 feet from centerline respectively. Based on the scale 1=20 shown on the plan, it does not appear that enough ROW exists and no new ROW is being proposed??? A 15 foot utility easement must also be dedicated behind the new ROW. Please see the redline comments. Response: A new legal description and exhibit is included for review. Site and Utility Plans have been revised; the $250 review fee is included in this resubmittal. Number: 28 Created: 12/31 /2007 [4/1/08] Same - Incomplete submittal. Only Sheet 4 was re -submitted. [12131/07] The Landscape, Lighting and Elevation plans should be separated from the Utility Plan set. They are filed separately. Please revise the index on the cover sheet. A detail sheet will be required at the final compliance review stage. Response: See revised sheet set Galloway & Company, Inc. • Phone 303.770.8884 • Fax 303.770.3636 • 5350 DTC Parkway, Greenwood Village, CO 80111 9 www.gallowayUS.com i (generally) from 11.2 to 25.4. These are all acceptable numbers if they represent the initial installation of the under -canopy lights. , Response: See revised Photometric plan, under canopy lighting has been revised to minimize light levels outside the canopy area. Number: 65 Created: 3/27/2008 (3/27/08] Section 3.2.4(D)(7) of the LUC states that maximum on -site lighting levels shall not exceed 10 foot-candles, except for loading and unloading platforms where the maximum lighting level shall be 20 foot-candles (excepting under -canopy lighting). The Lighting Plan as submitted shows levels of 15 to 24 foot-candles distances of 7' to 15' outside the edges of the canopy. This is unacceptable, what is driving it? Response: Maximum foot-candle levels 10' from the edge of the canopy are now at 6.0 fc. Number: 66 Created: 3/28/2008 [3/28/08] Is it necessary to have pole heights of 30' for the lighting at the 4 corners of the site? Also, the proposed 750 Metal Halide light source may be too high. Response: Light poles are shielded from the rear and are reduced to 20' with 450 watt fixtures Number: 67 Created: 3/28/2008 [3/28/08] The Encore Flat Lens 20OW Metal Halide fixtures under the canopy appear to be completely flush mounted with the ceiling deck of the canopy. Is this a reasonable assumption? Could the 20OW Metal Halide light source (being very white) be contributing to the high foot- candle levels outside of the canopy? Maybe a High Pressure Sodium source would be better? Response: The 30' site lights with 750 watt fixtures were contributing to the high foot-candle levels both pole height and fixture specifications have changed see revised site photometric plan. Number: 68 Created: 3/28/2008 [3/28/08] There may be concern about the Encore Focus - Double or Single Deck 100W Metal Halide fixtures. They obviously are directional lights that extend down below the actual ceiling deck of the canopy. Being directional, rather than wholly down -directional, they can be directed to areas outside of the canopy, which could be problematic. Response: Focus lights have been removed. Tooic: Site Plan Number: 16 Created: 12/27/2007 [3/26/08] On the Site Plan, there is a divided square under the canopy in the middle of the site. What does it represent? [12/27/07] There are several symbols on the Site Plan that are not labeled. They should be removed. Please see the red -lined Site Plan. Response: The site plan has been revised Number. 58 Created: 3/26/2008 [3/26/08] On the Site Plan, there is a divided square under the canopy in the middle of the site. What does it represent? Response: The square is a proposed window washing & trash container Galloway & Company, Inc. • Phone 303.770.8884 • Fax 303.770.3636 • 5350 DTC Parkway, Greenwood Village, CO 80111 • www.gallowayUS.com Number:57 Created:3/26/2008 [3/26/08] Please add a Note #5 under LANDSCAPE GUARANTEE AND MAINTENANCE stating: The property owner will be responsible for the on -going upkeep and maintenance of all plant material in the public street rights -of -way. Response: Note #5 has been added Topic: Lighting Plan Number: 62 Created: 3/27/2008 [3/27/08] Section 32.4(B) of the City's Land Use Code (LUC) states, in part, that all development shall submit a proposed lighting plan that meets the functional security needs of the proposed land use without adversely affecting adjacent properties or the community. Section 3.2.4(D)(3) states, in part, that light sources shall be concealed and fully shielded and shall feature sharp cut-off capacity so as to minimize up -light, spill -light, glare and unnecessary diffusion on adjacent property. Under -canopy fueling areas shall feature flush -mount, flat lens light fixtures as part of any newly constructed canopy or remodeled canopy. Response: All lights are flush mounted flat lenses Number: 63 Created: 3/27/2008 [3/27/08] Section 3.2.4(D)(8) of the LUC states that light levels measured 20' beyond the property line of the development site (adjacent to residential uses and public rights -of -way) shall not exceed 0.1 foot-candle as a direct result of the on -site lighting. Based on the Lighting Plan as submitted, lighting levels 20' outside of this property along South Taft Hill Road range from 4 foot- candles to 6 foot-candles; and, lighting levels outside of this property along West Elizabeth Street range from 3 foot candles to 5 foot-candles. Are these high numbers a result of the street lighting? Response: The lowest wattage light fixtures available for a canopy fixture are 200 watt and 175 watt, both lights were analyzed, the site pole lights have been changed to 20' high 450 watt fixtures. The following is a summary of the lighting levels 20' from the property lines: 1) Maximum lighting levels at 20' from the existing Taft Hill right of way are 0.4 foot-candles, 1.0 foot-candles from the proposed dedicated right of way. 2) Maximum lighting levels at 20' from the existing Elizabeth right of way are 0.1 foot- candles, 0.2 foot-candles from the proposed dedicated right of way. 3) Maximum lighting levels at 20' from the West property line into the grocery parking lot are 0.3 foot-candles. 4) Maximum lighting levels at 20' from the south property line into the grocery parking lot are 0.1 foot-candles. The canopy light fixtures are located as far from the edge of the canopy to provide adequate light to the user at the east and west fuel pump islands. The small site with fixtures close to the property lines makes meeting the Fort Collins lighting code for this small and constricted site impractical. We are requesting a vvaniance. �• t C,bo�� Number: 64 Created: 3/27/2008 v/• [3/27/08] The table in Section 3.2.4(C) of the LUC allows for the average maintained maximum foot-candle level of 20.0 for under -canopy areas. Also, this table allows for initial installation maximum foot-candle levels of 26.0 for under -canopy areas. Based on the Lighting Plan as submitted, the under -canopy foot-candle levels range Galloway & Company, Inc. 9 Phone 303.770.8884 • Fax 303.770.3636 • 5350 DTC Parkway, Greenwood Village, CO 80111 9 www.gallowayUS.com fixtures, including under -canopy lighting, will feature down directional and full cutoff luminaries. The word 'cutoff is inappropriately shown twice in this note. Response: See the attached Cover Sheet for the Planning Set, General Site Note 9. Number: 5 Created: 12/27/2007 [3/26/08] Did not receive revised Cover Sheet. [12/27/07] In General Note 11 on the Cover Sheet, please add: Maximum building height is 24'. Minimum building height is 20'. V Response: See the attached Cover Sheet for the Planning Set +, General Site Note 3. 00 Number: 50 Created: 1 /4/2008 [3/26/08] Repeat. See Zoning comments #52 & #53. [1/4/08] All project signage is subject to the City's Sign Code that is administered by the Zoning Department. Please contact Zoning for information on the sign allowance and locations for this development proposal. They can be reached at 970-416-2745. Response: See the attached Elevation Sheet for the Planning Set. The proposed canopy elevations comply with City Signage Code 3.8. 7 (E), (3), (13) -+ O,9.., �A&+ V fkCVAe-, phler Topic: Landscape Plan �hQ� ��' e'er' . Number: 54 Created: 3/26/2008 O � +��;��U,�� [3/26/08] Previous comment #20 dealt with Tim Buchanan's (City Forester) comment about tree species. Part of the applicant's response to this stated: "There is a. statement on the plans questioning adequate screening of the plant materials in the sight triangles. Typically these areas are not used for screening, we have provided plat material that creates seasonal interest and complements the layering of materials." Still a question about the 3 "Petite" Indigo Butterfly Bush in the middle of the planting bed along the north side of the site, adjacent to West Elizabeth Street. How tall does this plant get? Certainly not a sight distance concern here. Response: the Indigo Butterfly Bushes has been replaced with Nanho Blue Butterfly Bushes, this plant height is between 4-6' and 5' wide. Number: 55 Created: 3/26/2008 [3/26/08] To avoid problems with the City's future scanning of the Landscape Plan, please remove the shading in the planting beds at the entries to the site. Response: Shading has been removed Number: 56 Created: 3/26/2008 [3/26/08] To ensure full legibility of plans, please avoid overlapping of text with line work. . Response: Overlapping text has been relocated Galloway & Company, Inc. • Phone 303.770.8884 • Fax 303.770.3636 • 5350 DTC Parkway, Greenwood Village, CO 80111 • www.gallowayUS.com Gailloway Planning. Architecture. Engineering. May 5, 2008 City of Fort Collins 281 N. College Ave., 1 st Floor Ft. Collins, CO 80522 Attention: Steve Olt, City's Project Planner Re: King Soopers Fueling Center, PDP response to Staff Project Review Letter Dated 4/3/2008 Dear.,Steve: The following is our response to the 2n° City of Fort Collins Staff Project Review Letter Dated April 3, 2008. The original staff report comment is followed by our response in italics. Department: Current Planning Issue Contact: Steve Olt Number: 1 [12/27/07] The set of plans as submitted must be broken up into 2 sets as follows: '1 set (for Planning) ... Cover sheet Site'Plan (separated from Utility Plan) Landscape Plan ✓ Exterior Elevations and Signage Lighting Plan ✓ '1 set (for Engineering) ... Cover Sheet Alta/ACSM Land Title Survey Demolition Plan Utility Plan (separated from Site Plan) Grading and Drain a Plan Response: Seethe attached plan sets Number: 2 Created: 12/27/2007 [3/26/08] Did not receive revised Cover Sheet. These signature blocks must be on the Final Site Plan, or Cover Sheet for Site Plan, when submitted after public hearing for the Project Development Plan (PDP). [12127107] The required Owners Certification, Notary Public Certification, and Director of Planning & Zoning Approval signature blocks must be added to the Site Plan, e of these signature blocks are attached to the Staff comment letter. tc. et of plans. Examples Response: See the attached Cover Sheet for the Planning Set Number: 3 Created: 12/27/2007 (3126/08] Did not receive revised Cover Sheet: [12/27/07] General Note 16 on the Cover Sheet states that "construction is scheduled to begin in June, 2006". This note must come from a previous set of plans for another project. . l .,,,� Response: See the attached Cover Sheet for the Planning Set, general note 16 has been revised. W Number: 4 Created: 12/27/2007 (3/26/08] Did not receive revised Cover Sheet. [12/27/07] In General Note 17 on the Cover Sheet, please add: Both pole and building -mounted Galloway & Company, Inc. 9 Phone 303.770.8884 9 Fax 303.770.3636 • 5350 DTC Parkway, Greenwood village, CO 80111 9 www.gallowayUS.com