Response: The logo on the canopy has been resized to meet city code. If is understood that
signage is not approved with the approval of this planning set and a separate submittal for
signage is required.
Number:53 Created:3/25/2008
[5/15/08] The monument sign is not allowed to be in the ROW per Section 24-1 of the Municipal
Code. The sign must be on private property.
[3/25/08] Both of the monument signs appear to be in the ROW once the additional ROW is
dedicated. They have to be on private property. Additionally, Sec. 3.8.7(G) (2) requires that a
ground sign has to be at least 15' from an interior side lot line. If the facility is addressed off
Elizabeth, then the south lot line is the rear lot line and the Taft Hill sign meets this requirement, but
the Elizabeth sign is then closer than 15' to the west lot line, which becomes the side lot line. If the
address is off Taft Hill, then the opposite is true (the Elizabeth sign is ok, but the Taft sign isn't.
Response: The monument signage has been removed.
Sincerely,
Matthew F. Duhaime P.E., P.L.S
Project Manager
Galloway, Romero & Associates
File No. ks112-Comment Respons letter2.doc
CC: File
Galloway & Company, Inc, • Phone 303.770.8884 • Fax 303.770.3636 • 5350 DTC Parkway, Greenwood Village, CO 80111 0 www.gallowayUS.com
manhole.
Response: New comment. Additional note for plugging the end of the service has been added.
Number: 71 Created: 4/1/2008
[5/19/08] Back flow preventer must be upstream of frost -proof yard hydrant. Will the backflow
preventer be in a pit (separate from water meter pit)? If yes, show pit on the utility plan? If no, how
will the water service and backflow preventer be winterized?
[4/1/08] Frost free yard hydrants not allowed unless proper backflow prevention is provided. Contact
John Nelson (221-6677) for information regarding notes and details to be included on utility plans.
Response: New Comment, back flow preventer location is added to the utility plan sheet. John
Nelson at the water department agrees the backflow prevention valve detail can be part of the
construction set. The yard hydrant and backflow prevention valve are operational only during the
irrigation season and are drained before the wintedfall frost.
Number: 73 Created: 4/1/2008
[5/19/08] Revise note as shown on redlined plans.
[4/1/08] Add note to coordinate with Water Utilities (416-2165) on re-routing of the water service and
re -location of the meter pit.
Response: Note has been added to the utility plan sheet.
Number: 91 Created: 5/19/2008
[5/19/08] Show location of existing curb stop on the utility plans. The proposed re-routing of the
water service must occur downstream of the curb stop. Move the proposed water meter pit to the
location shown on the redlined plans.
Response: New comment, the curb stop is labeled on the utility plan. The water meter has been
relocated per the redlined plan.
Number: 92 Created: 5/19/2008
[5/19/08] Add water service and water meter pit standard details to the utility plans.
Response: New comment, the water service already exist, the water meter pit standard detail has
been added to the utility plan sheet.
Department: Zoning
Topic: Zoning
Number: 52
Issue Contact: Peter Barnes
Created: 3/25/2008
[5/15/08] The logo sign shown on the north elevation of the canopy is still 33" tall, when only 30" is
allowed.
[3/25/08] Per Section 3.8.7(E) (13), only 2 signs are tillowed on the canopy, one on the east fascia
and one on the north fascia. The plan shows 4 such signs, one on each fascia. The south and
west signs need to be removed. Per Section 3.8.7(E) (8), the maximum allowed height of logo and
cabinet signs is 30", the plan indicates that the logos on the canopy are 33" tall. Also, the maximum
size allowed for the one canopy sign on the north fascia is 12 sq.ft. (Sec. 3.8.7(E) (13), but the
logo and letters combined is more than 18 square feet (the logo can't be considered as one sign
and the letters as another, because then there would be two signs when only one is allowed. So
as one sign, it can't exceed 12 sq.ft.
Galloway & Company, Inc. • Phone 303.770.8884 • Fax 303.770.3636 • 5350 DTC Parkway, Greenwood Village, CO 80111 9 www.gallowayUS.com
Response: Please apply the credit towards the easement review.
Department: PFA Issue Contact: Carle Dann
Number: 46- Created: 1/442008
[5/21/08] PFA requires permits to be issued when installing and/or removing underground fuel
tanks, and requires that two sets of plans be submitted for review. Plans must show the layout of
the USTs, number of tanks, size and construction materials.
[1/4/08] PERMITS: Permits from Poudre Fire Authority are required prior to removing current fuel
storage tanks and installing new tanks.
Response: Construction plan sets will be submitted to PFA for review and permitting with the
building permit submittal.
Department: Transportation Planning
Topic: General
Number: 103
[5/20/08] No Comment
Response: No response required.
Department: Stormwater-Water-Wastewater Issue
Topic: Drainage Report
Issue Contact: Denise Weston
Created: 5/20/2008
Contact: Basil Harridan
Number: 94 Created: 5/19/2008
[5/19/08] Please provide a drainage report. Include water quality calculations as well as all other
drainage and erosion control calculations. No report was included with this latest submittal
package.
Response: New comment, a drainage letter with a historical and proposed drainage basin plan
was submitted with the first submittal. Attached are copies of the original plan submittal and a
updated drainage report. .
Topic: Water Quality design
Number: 93 Created: 5/19/2008
[5/19/08] The detail for the landscape detention should be clarified. Please provide actual
dimensions, elevations and slopes. Please provide a separator material between the native soil and
the landscape detention material. This can be in the form of a poly liner.
Why is there an impermeable liner at the bottom of the porous landscape detention pond?
It seems that a meeting to discuss adequate water quality measures is needed before the next
submittal. A representative from the Engineering Department should also be invited to this
meeting.
Response: The landscaped water quality swale/p`ond was revised after discussions with staff.
Department: Stormwater-Water-Wastewater Issue Contact: Roger Buffington
Topic: Water/Wastewater
Number: 70 Created: 4/1/2008
[5/19/08] As previously noted, in addition to the watertight plug at the main, plug the end of the
service on -site with non -shrink grout.
[4/1/08] It appears that the existing sewer service connects to the manhole in Elizabeth; therefore,
to abandon the service, excavate and cap/grout service on site AND install a watertight plug in the
Galloway & Company, Inc. 9 Phone 303.770.8884 • Fax 303.770.3636 • 5350 DTC Parkway, Greenwood Village, CO 80111 • www.gallowayUS.com
Response: Monument sign has been removed from the site plan.
Number: 95 Created: 5/20/2008
[5/20/08] Please add "Utility Plans For' on the cover sheet over the tile for the Utility Plan set.
Response: Title on the Utility Plan Cover sheet has been revised.
Number: 96 Created: 5/20/2008
[5/20/08] Please add (For Reference Only) to the Index for the ALTA survey. See redlines for
clarification.
Response: Index has been revised.
Number: 97 Created: 5/20/2008
(5/20/08] Please remove variances number 2 and 3 from cover sheet General Note 48. The
lighting is a modification to the Land Use Code processed by Planning and not a part of the Utility
Plan set. Number 3 will not be permitted by the City. The monument sign must be removed from
the ROW. See redlines.
Response: Variances number 2 and 3 have been removed. The monument sign has been
removed.
Number: 98 Created: 5/20/2008
[5/20/08] The plan shows a small portion of the canopy structure overhanging the new ROW
dedication. No part of a structure is permitted to encroach into the ROW. Please revise the plans
accordingly.
Response: The canopy does not encroach into the new ROW, the reviewer is looking at the edge
of the concrete pavement.
Number: 99 Created: 5/20/2008
[5/20/08] Please add the City's standard street cut note to the demolition plan and utility plan sheets.
I have provided this note in the redlines.
Response: Note has been added to the demolition plan and the utility plan sheets.
Number:100 Created: 5/20/2008
[5/20/08] Please call out all curb opening/chase/chase drains with the LCUASS standard detail and
provide the detail on the detail sheet 6 of 6.
Response: Curb openings are all labeled LCUASS detail has been added to the detail sheet.
Number: 101 Created: 5/20/2008
[5/20108] Please add the City standard signature block to sheet 6 - details.
Response: City standard signature block has been added
Number: 102
Created: 5/20/2008
[5/20/08] An overpayment of $250 was made. I believe this was a result of the confusion on the
ROW dedication by separate document. We can apply this "credit" toward the easement review
fee that is necessary for the off -site cross lot access arrangement and associated offsite
improvements. An email was sent to Matt regarding ROW and Easement dedications on 5-20-08.
Galloway & Company, Inc. • Phone 303.770.8884 • Fax 303.770.3636 • 5350 DTC Parkway, Greenwood village, CO 80111 • www.gallowayUS.com
Response: Landscaping conflicts with the transformer have been removed. The proposed
landscaping in the Water Quality Swales is designed to sustain short periods of saturation and
drying out.
Number: 106 Created: 5/27/2008
[5/27/08] For scan -ability purposes, there is still one area of concern: the detention pond at the
northeast corner of the site.
Response: The hatching has been lightened and text conflicts have been reduced for scanning.
Topic: Lighting Plan
Number: 62 Created: 3/27/2008
[5/27/08] Carried over just as a reminder.
[3/27/08] Section 3.2.4(B) of the City's Land Use Code (LUC) states, in part, that all development
shall submit a proposed lighting plan that meets the functional security needs of the proposed land
use without adversely affecting adjacent properties or the community. Section 3.2.4(D)(3) states, in
part, that light sources shall be concealed and fully shielded and shall feature sharp cut-off capacity
so as to minimize up -light, spill -light, glare and unnecessary diffusion on adjacent property. Under -
canopy fueling areas shall feature flush mount, flat lens light fixtures as part of any newly
constructed canopy or remodeled canopy.
Response: No response required.
Topic: Site Plan
Number: 59 Created: 3/26/2008
[5/20/08] The proposed monument sign at the northeast corner of the site cannot be in the street
right-of-way.
[3/26/08] The 2 proposed monument signs (items #31) cannot be in the street rights -of -way.
Response: Monument Sign has been removed.
Department: Engineering
Topic: Engineering
Issue Contact: Randy Maizland
Number: 78 Created: 4/1 /2008
[5/20/08] A letter of intent for the cross lot access arrangement and temporary construction
easement are needed prior to scheduling a hearing for this project.
[4/1/08] Please submit a signed letter from Cedarwood Plaza (prior to scheduling a hearing)
indicating that they are OK with the cross lot access arrangement proposed on the plans on the
NW corner of the parcel.
Response: A cross access agreement and construction easement has been drafted between the
shopping center owner and King Soopers copies of the proposed legal documents are included
with the resubmittat
Number: 79
Created: 4/1/2008 [5/20/08}-T-
he-monument sign is -still -shown -in -the -ROW No signs will be permitted in the ROW. Please also
see Zoning department comments from Peter Barnes.
[411/08] Monument signs may not encroach into the new ROW area. Please pull these signs out
of the ROW limits.
Galloway & Company, Inc. 9 Phone 303.770.8884 • Fax 303.770.3636 • 5350 DTC Parkway, Greenwood Village, CO 80111 • www.gallowayUS.com
a. A letter of intent is needed from the property owner to the west (the shopping center) for
the drive connection between the properties.
Response: A cross access agreement and construction easement has been drafted between the
shopping center owner and King Soopers copies of the proposed legal documents are included
with the resubmittal.
b. The proposed monument sign cannot be in the right-of-way (ROW).
Response: The proposed monument sign has been removed from the plan set.
C. The standard street cut note must be added to the utility plans.
Response: Standard street cut note has been added on the Demolition Plan and the Utility Plan
sheets.
d. Sheet 6 of the utility plans is missing the standard signature block.
Response: Standard signature block has been added.
Light & Power / Rob Irish:
a. Light & Power needs an 8' clearance in front of the transformer (east side, for access) at the
northwest corner of the site.
Response: Landscape material has been removed to provide the 8' clearance.
Stormwater / Basil Hamdan:
a. The water quality details as submitted are not acceptable.
Poudre Fire Authority / Cane Dann:
Response: The water quality details have been revised after discussions with City Staff.
a. Storage tank permits are needed.
Response: The Underground Fuel Storage Tanks (UST) will be permitted with the State, tank,
piping, leak detection specifications and plans will be submitted with the building permit submittal.
b. The address for this site will be on the kiosk.
Response: The address will be posted on the kiosk.
Topic: Landscape Plan
Number: 56 Created: 3/26/2008
[5/20/08] Still one area of concern - detention pond along the north side.
[3/26/08] To ensure full legibility of plans, please avoid overlapping of text with line work.
Number: 105 Created: 5/27/2008
[5/27/08] The transformer at the northwest corner of the site must have 8' clearance on the east side
for access by Light & Power. However, there must be landscaping as possible to provide adequate
screening of the transformer box.
Galloway & Company, Inc. • Phone 303.770.6884 • Fax 303.770.3636 • 5350 DTC Parkway, Greenwood Village, CO 80111 • www.gallowayUS.com
GaAftoway I now
Planning, architecture. Engineering.
June 30, 2008
City of Fort Collins 281 N. College Ave., 1 st Floor
Ft. Collins, CO 80522
Attention: Steve Olt, City's Project Planner
Re: King Soopers Fueling Center, PDP response to Staff Project Review Letter Dated 5/27/2008
Dear Steve:
The following is our response to the 3rd City of Fort Collins Staff Project Review Letter Dated May
27, 2008. The original staff report comment is followed by our response in italics.
Department: Planning Issue Contact: Steve Olt
Number: 3 Created 12/27/2007
[5/19/081 This is now General Note 8 on the Cover Sheet.
[3/26/08]- Did not receive revised Cover Sheet.
[12/27/07] General Note 16 on the Cover Sheet states that "construction is scheduled to begin in
June, 2006". This note must come from a previous set of plans for another project.
VV " Response: No revision required Note 16 was changed to Note 8 and revised in previous
submittal.
umber: 4 Created: 12/27/2007
[5/19/081 This is now General Note 9 on the Cover Sheet.
[3/26/081 Did not receive revised Cover Sheet.
[12/27/071 In General Note 17 on the Cover Sheet, please add: Both pole and building mounted
fixtures, including under -canopy lighting, will feature down directional and full cutoff luminaries. The
word 'cutoff is inappropriately shown twice in this note. t,
Response: No revision required Note 17 was changed to Note 9 and revised in previous.
submittal.
Nu ber:50 Created:l/4/2008
19/08] The project signage will not be approved by the Hearing Officer at the re uired
administrative public hearing. The information provided on this Exter' a Ions - Prcjec
Development Plan drawing is for reference only. The actual ' nage (content an ize) will be
reviewed with the Building Permit application. Therefore, a reference to "AND SIGNAGE"
ould be removed from the title.
[3/26/08] Repeat. See Zoning comments #52 & #53.
[1/4/08] All project signage is subject to the City's Sign Code that is administered by the Zoning
Department. Please contact Zoning for information on the sign allowance and locations for this
development proposal. They can be reached at 970-416-2745.
Response: Understood, the signage is not approved by the planning documents. The canopy
elevation sheets title is revised and the requested signage disclaimer note has been added.
Number: 104 Created: 5/27/2008
[5/27/08] The following comments were expressed by City staff at the review meeting on May 21 st
with staff and the applicant:
Engineering / Randy Maitland:
Galloway & Company, Inc. 9 Phone 303.770.8884 • Fax 303.770.3636 • 5350 DTC Parkway, Greenwood Village, CO 80111 • www.gallowayUS.com