HomeMy WebLinkAboutKING SOOPERS FUELING STATION (CEDARWOOD PLAZA) - PDP - 40-07 - CORRESPONDENCE -Peter approved the location and size of a monument sign on site (the proposed
location is not in the existing or proposed right-of-way); the monument sign is shown on
the planning site plan and is bubble noted at #40 on the site plan and a monument
signage elevation added to the elevation sheet. It is understood that signage is not
approved with this planning approval and a signage permit needs to be obtained before
construction.
Attached with this submittal is a $2,000 check for the final review fee and the TDRF.
Sincerely,
Matthew F. Duhaime P.E., P.L.S
Project Manager
Galloway, Romero & Associates
ks112-mfd- Comment Respons letter4.doc
Galloway & Company, Inc. • Phone 303.770.8884 • Fax 303.770.3636 • 5350 DTC Parkway, Greenwood Village, CO 80111 • www.gallowayUS.com
N'
Gauloway
Planning. Architecture. Engineering.
October 23, 2008
City of Fort Collins 281 N. College Ave., 1st Floor
Ft. Collins, CO 80522
Attention: Steve Olt, City's Project Planner
Re: King Soopers Fueling Center, PDP response to Final Staff Project Review from
planning hearing
Dear Steve
The following response is to the City of Fort Collins planning hearing held on August 6,
2008. We received no formal staff report or comments but the following issues King
Soopers agreed to do investigate and respond to, our response follows and is in italic:
1) Review the water quality pond between the sidewalk and Taft Hill Road with city staff
for the pond lining and the requirement for trees to be placed in this landscape buffer.
Response:
Reviewed with Basil Y. Hamdan and Randy Maizland, staff directed us to show a 4' deep
concrete cut off wall under the curb along the water quality pond perimeter along Taft Hill
Road, the proposed concrete cut off wall is shown on the water quality pond detail
section B-B on sheet 5 of 6 in the Utility Set.
2) Review the installation of trees in the landscape buffer between Taft Hill Road and the
sidewalk (water quality pond) with staff and comply with city code:
Response:
Installation of the concrete cut off wall instead of an impermeable liner allows the
installation trees in the landscape buffer, two trees were added see the revised
landscape plan.
3) Install a bicycle rack for one bicycle parking.
Response:
A single bicycle rack is shown on the site under the canopy in front of the kiosk see
bubble note #39 on the site plan, a detail of the bicycle rack is shown on sheet 6 of 6 of
the Utility set.
4) Install landscape screening between the ATM machine and Taft Hill Road on the
adjoining property south of our site.
Response:
8 Sea Green Juniper shrubs are proposed at this location see the Landscape plan (sheet
3 of 6).
5) A signage review meeting with City staff (Peter Barnes) on
Response:
Galloway & Company, Inc. • Phone 303.770.8884 • Fax 303.770.3636 9 5350 DTC Parkway, Greenwood Village, CO 80111 9 www.gallowayUS.com