HomeMy WebLinkAboutNORTH COLLEGE MARKETPLACE - WETLANDS PDP - 39-08 - CORRESPONDENCE -Page 2 of 2
Total = $9,309.75 (+ APO fee, once determined)
These numbers come from 2 separate applications, being the TDRF application and the Development Review
application. Both must be completed and submitted with your PDP documentation.
If an Overall Development Plan is required then the total fee would increase by $1,399.00.
The actual North College Marketplace PDP (shopping center) fees will be substantially more, when submitted.
Steve
>>> "Blaine Rappe" <bra ppe@lovela ndcommercial.com> 11/19/2008 12:16 PM >>>
Steve,
I wanted to confirm all the submittal fee calculations with you, see below:
Project Fee
$2,000
PDP Plan Review Fee
$7,059.75 ($250 per acre, total is 28.239 acres)
Sign Posting Fee
$50
APO list
TBD ($.75 per address)
Total
$9,147.25
Please comment, thank you.
Blaine Rapp6, CCIM
Loveland Commercial, LLC
1043 Eagle Drive
Loveland, CO 80537
Phone (970) 667-7000 ext. 101
Fax (970) 635-2514
Cell (970) 566-4929
web: www.lovelandcommercial.com
file://CADocuments and Settings\soft\Local Settings\Temp\GW}00001.HTM 11/21/2008
Page 1 of 2
Steve Olt - RE: North College Marketplace - Wetland Submittal Fees
From: "Blaine Rappe"<brappe(aalovelandcommercial.com>
To: "'Sheri Langenberger"' <slangenberger@fcgov.com>, "'Steve Olt"' <SOLT@fcgov.com>
Date: 11/21/2008 10:09 AM
Subject: RE: North College Marketplace - Wetland Submittal Fees
Thank you.
Blaine Rapp6, CCIM
Loveland Commercial, LLC
1043 Eagle Drive
Loveland, CO 80537
Phone (970) 667-7000 ext. 101
Fax (970) 635-2514
Cell (970) 566-4929
web: www.lovelandcommercial.com
From: Sheri Langenberger [mailto:slangenberger@fcgov.com]
Sent: Wednesday, November 19, 2008 11:02 AM
To: Steve Olt; Blaine Rappe
Subject: Re: North College Marketplace - Wetland Submittal Fees
Assuming that the acreage number is what is on the submitted plat those numbers are correct for the TDRF
PDP. If an ODP is needed the TDRF for an ODP is $500.
1 have attached a copy of the TDRF application form if you don't already have one.
Sheri
Sheri Langenberger, P.E.
Engineering Development Review Manager
City of Fort Collins, Engineering Dept
970-221-6605
>>> Steve Olt 11/19/2008 11:56 AM >>>
Blaine,
Re: North College Marketplace - Wetland PDP
Your calculations of $2,000.00 and $7,059.75 are only for the Transportation Development Review Fees
(TDRF). There is a Planning Development Review Fee to be paid and in this case it can be the Small Project
Fee of $200.00 because there are no buildings in the Wetiand PDP. Assuming Engineering is OK with your
calculations (they determine the TDRF), the total amount would be:
Plannina
ProjectFee................................................................ $ 200.00
Sign Posting Fee ..................................................... $ 50.00
APOlist fee................................................................ TBD
Engineering
ProjectFee............................................................ I.... $2,000.00
Size of Development ............................................... $7,059.75
- $250/acre x 28.239 acres (on subdivision plat)
file://C:\Documents and Settings\colt\Local Settings\Temp\GW100001.HTM 11/21/2008