HomeMy WebLinkAboutKAUFMAN & ROBINSON OFFICE DEVELOPMENT - PDP - 40-08 - CORRESPONDENCE - (4)Steve Olt - Re: Kaufman & Robinson Off' Development, PDP Page 1
From: Roger Buffington
To: Steve Olt
Date: 5/12/2009 12:07:22 PM
Subject: Re: Kaufman & Robinson Office Development, PDP
The letter contains my comment, and I am okay with going to hearing.
Roger
>>> Steve Olt 05/12/2009 12:04:42 >>>
Re: Kaufman & Robinson Office Development, PDP - #40-08
This development proposal has been through 3 rounds of review for the PDP and was supposed to be
discussed at staff review last Wednesday, May 6th. Somehow it was missed.
The "DRAFT' comment letter from last Wednesday is attached. It contains all comments that are in DMS
as of today. Does anyone have additional comments; and, is there any objection to allowing this request to
be scheduled for an administrative public hearing? Current Planning is OK with it going to hearing. The
applicant is inquiring about the status of the project.
Thanks,
Steve
Steve Olt - Re: Kaufman &Robinson OffI 7evelopment, PDP Page 1
From: Peter Barnes
To: Steve Olt
Date: 5/12/2009 1:12:38 PM
Subject: Re: Kaufman & Robinson Office Development, PDP
My only comment is the additional info needed to analyze the parking.
Peter
>>> Steve Olt 5/12/2009 12:04 PM >>>
Re: Kaufman & Robinson Office Development, PDP - #40-08
This development proposal has been through 3 rounds of review for the PDP and was supposed to be
discussed at staff review last Wednesday, May 6th. Somehow it was missed.
The "DRAFT' comment letter from last Wednesday is attached. It contains all comments that are in DMS
as of today. Does anyone have additional comments; and, is there any objection to allowing this request to
be scheduled for an administrative public hearing? Current Planning is OK with it going to hearing. The
applicant is inquiring about the status of the project.
Thanks,
Steve
Steve Olt - Re: Kaufman & Robinson Off' Development, PDP Page 1
From: Andrew Carney
To: Barnes, Peter; Buffington, Roger; Dann, Carie; Irish, Rob; Olson, Joe; Olt, Steve;
Wempe, Matthew
Date: 5/12/2009 1:52:06 PM
Subject: Re: Kaufman & Robinson Office Development, PDP
Engineering is ok with the project going to hearing and all of my comments are in DMS
Thanks,
Andrew
>>> Steve Olt 5/12/2009 12:04 PM >>>
Re: Kaufman & Robinson Office Development, PDP - #40-08
This development proposal has been through 3 rounds of review for the PDP and was supposed to be
discussed at staff review last Wednesday, May 6th. Somehow it was missed.
The "DRAFT" comment letter from last Wednesday is attached. It contains all comments that are in DMS
as of today. Does anyone have additional comments; and, is there any objection to allowing this request to
be scheduled for an administrative public hearing? Current Planning is OK with it going to hearing. The
applicant is inquiring about the status of the project.
Thanks,
Steve
Page 1 of 1
Steve Olt - Re: Fwd: Kaufman & Robinson Office Development, PDP
From: Ward Stanford
To: Joe Olson; Steve Olt
Date: 5/12/2009 2:11 PM
Subject Re: Fwd: Kaufman & Robinson Office Development, PDP
I've not seen this submittal.
Ward.
>>> Joe Olson 5/12/2009 12:56 PM >>>
>>> Steve Olt 5/12/2009 12:04 PM >>>
Re: Kaufman & Robinson Office Development, PDP - #40-08
This development proposal has been through 3 rounds of review for the PDP and was supposed to be discussed
at staff review last Wednesday, May 6th. Somehow it was missed.
The "DRAFT" comment letter from last Wednesday is attached. It contains all comments that are in DMS as of
today. Does anyone have additional comments; and, is there any objection to allowing this request to be
scheduled for an administrative public hearing? Current Planning is OK with it going to hearing. The applicant is
inquiring about the status of the project.
Thanks,
Steve
file://CADocuments and Settings\solt\Local Settings\Temp\GW}00001.HTM 5/12/2009
Page 1 of 1
Steve Olt - Re: Kaufman & Robinson Office Development, PDP
From: Rob Irish
To: Steve Olt
Date: 5/12/2009 2:22 PM
Subject:. Re: Kaufman & Robinson Office Development, PDP
Steve, Light & Power is OK with this going to hearing.
e
Robert Irish
Electric Project Manager
Fort Collins Utilities
700 Wood St.
PO Box 580
Fort Collins, CO 80522
Tel: 970-224-6167
Fax:970-221-6619
rirish a fcgov.com
>>> Steve Olt 5/12/2009 12:04 PM >>>
Re: Kaufman & Robinson Office Development, PDP - #40-08
This development proposal has been through 3 rounds of review for the PDP and was supposed to be discussed
at staff review last Wednesday, May 6th. Somehow it was missed.
The "DRAFT' comment letter from last Wednesday is attached. It contains all comments that are in DMS as of
today. Does anyone have additional comments; and, is there any objection to allowing this request to be
scheduled for an administrative public hearing? Current Planning is OK with it going to hearing. The applicant is
inquiring about the status of the project.
Thanks,
Steve
file://C:\Documents and Settings\solt\Local Settings\Temp\GW}00001.HTM 5/12/2009