Contained in this letter are the Boxelder Sanitation District comments for #18-10 Maple Hill
Phase 7, a Filing PDP-Type 1 Project Development Plan dated July 21, 2010.
Sheet #2: The record drawings the District has on file for Maple Hill indicate that there is a
sanitary sewer stub out located on Maple Hill Drive approximately 341 feet east of the sewer
manhole at the intersection of Forecastle Drive and Maple Hill Drive. The same type of note
about abandonment of this sewer access should be shown.
Sheet #4, Note 2: Boxelder staff has met with Maple Hill representatives on a number of
occasions since their decision to submit a change in the type of residential housing in this
phase. Boxelder and Maple Hill have not agreed on a layout of the sewer service laterals that
will connect to its collector lines within the Maple Hill development. Until there is agreement,
Boxelder will not provide service to this phase.
Thank you for the opportunity to comment.
Sincerely,
Fred E. Walker
General Manager