DATE: April 24, 2009
TO: Building Inspection
PROJECT
COMMENT
PROJECT PLANNER: Emma McArdle
SHEET
# 20-09 COLORADO IRON AND METAL PDP - TYPE I
Please return all comments to the project planner no later than
the staff review meeting:
May 13, 2009
Note - Please identify your redlines for future
reference
❑ No Problems
❑ Problems or Concerns (see below, attached, or DMS)
SEE 1'1tzTP'CC0M cotes t s7Pvrr�ps , sit t�uc�
f"a R.�c�v � REA GoP� Pig- S vBM i TTRI- 1" � �'Z'�►G
f-1 L--r f/Z`=
Name (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
_Plat _Site _Drainage Report _Other_
_Utility _Redline Utility _Landscape
L-A
MW
City of
Fort Collins
Current
Planning
PO Box 580 ' Fort Collins, CO 80522
970.221.6750 ' 970.224.6134 - fax
DATE: April 24, 2009
TO: Comcast
PROJECT
COMMENT
PROJECT PLANNER: Emma McArdle
SHEET
# 20-09 COLORADO IRON AND METAL PDP - TYPE I
Please return all comments to the project planner no later than
the staff review meeting:
May 13, 2009
Note - Please identify your redlines for future
reference
❑ No Problems
[�] Problems or Concerns (see below, attached, or DMS)
Comcast requires a 2" conduit from the data/communication out toward
Buckingham St. if they want our service in the future.
Name (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
_Plat _Site
_Utility _Redline Utility
_Drainage Report _Other.
_Landscape
IV
City of
Fort Collins
1 Current
Planning
PO Box 580 " Fort Collins, CO'80522
970.221.6750' 970.224.6134 - fax
DATE: April 24, 2009
TO: Post Office
PROJECT
COMMENT
PROJECT PLANNER: Emma McArdle
SHEET
# 20-09 COLORADO IRON AND METAL PDP - TYPE I
Please return all comments to the project planner no later than
the staff review meeting:
May 13, 2009
Note - Please identify your redlines for future
reference
No Problems
Problems or Concerns (see below, attached, or DMS)
7
DI& 1, LAe f-_5
Name (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
XPlat _Site _Drainage Report _Other.
_Utility _Redline Utility _Landscape
1
Staff Review Comments City of
F„r.,t` Collins
Department: Stormwater•Water•Wastewater Issue Contact: Roger Buffington
Topic: WaterMastewater
Number:49 Created:5/15/2009 Pending
[5/15/091 The sewer service for the proposed building must connect at a manhole.
Department: Zoning Issue Contact: Jenny Nuckols
Topic: Zoning
Number:1 Created:4/30/2009 Pending
[4/30/09] Parking. The maximum number of parking spaces is based on the number of total employees.
63 proposed spaces exceeds what is allowed. If you are seeking "alternative compliance", please review
section 3.2.2(K)(3) for the process to request alternative compliance
Number:2 Created:4/30/2009 Pending
[4/30/09] Please show bicycle parking and locate near the main entrance.
Number:3 Created:4/30/2009 Pending
[4/30/09] Handicapped parking spaces are based on the overall number of parking spaces. 34 Parking
spaces would require 2 handicap spaces, 63 parking spaces would require 3 handicap spaces. Of those
HC spaces, one needs to be van accessible with an overall width of 16' and signed as "Van Accessible"
Please note parking stall dimensions on the site plan and label all HC spaces.
Number:4 Created:4/30/2009 Pending
[4/30/09] On the site plan please show and label the new building envelope since there is proposed
changes to the north side.
Number:5 Created:4/30/2009 Pending
[4/30/09] There are some parking spaces to the East that seem to be located on two lots. Are they part of
this development?
Number:6 Created:4/30/2009 Pending
[4/30/091 Please show building height at the top roof line on the elevation drawings.
Number:7 Created:4/30/2009 Pending
[4/30/09] How will trash and recyclables be handled? Will there be an exterior enclosure? If so please
note location on site plan and provide an elevation on the elevation sheets.
Number:8 Created:5/1/2009 Pending
[4/30/09] Please note colors, materials etc of the buildings on the elevation drawings.
l�
Staff Review Comments
City of
Fort Collins
facility or any portion of an exterior wall of the first story of the building is located more than 150 feet from
fire apparatus access as measured by an approved route around the exterior of the building or facility. This
fire lane shall be visible by painting and signage, and maintained unobstructed at all times. A fire lane plan
shall be submitted for approval prior to installation. In addition to the design criteria already contained in
relevant standards and policies, any new fire lane must meet the following general requirements:
• Be designed as a flat, hard, all-weather driving surface (asphalt or concrete) capable of supporting
fire apparatus weights. Compacted road base shall be used only for temporary fire lanes or at
construction sites.
• Have appropriate maintenance agreements that are legally binding and enforceable.
• Be designated on the plat as an Emergency Access Easement.
• Maintain the required minimum width of 20 feet throughout the length of the fire lane (30 feet on at
least one long side of the building when the structures are three or more stories in height).
If the building is equipped throughout with an approved automatic fire -sprinkler system, the fire code official
is authorized to increase the dimension of 150 feet. NOTE: Please contact me to determine specific EAE
location.
2006 International Fire Code 503.1.1, 503.2.3, 503.3, 503.4 and Appendix D
Number:43 Created:5/14/2009 Pending
HMIA: The requested Hazardous Materials Impact Analysis is excellent. Thank you.
Number:44 Created:5/14/2009 Pending
FUEL TANK: The proposed diesel/gasoline tank is required to meet all applicable requirements set forth in
the 2006 IFC.
Department: Stormwater•Water-Wastewater Issue Contact: Wes Lamarque
Topic: Stormwater
Number:45 Created:5/15/2009 Pending
[5/15/091 Retention ponds are only allowed after all other options for detention have been exhausted.
There is still the option of expanding the existing detention pond, which detains the existing site. Also,
groundwater in this area is most likely higher than the 12-foot deep proposed retention pond, which would
make this pond not feasible. In general, retention ponds need to still have an outfall. This could be
percolation only if a soils report confirmed acceptable percolation rates. A backup option would also be
required, like a gravity or pumped delayed release to an irrigation ditch.
Number:46 Created:5/15/2009 Pending
[5/15/091 Drainage easements are required for all ponds and other drainage improvements. The proposed
drainage pan along the east side of the property would need a drainage easement for the on -site and off -
site portions. For any off -site drainage easements, a letter of intent is required before the public hearing.
Number:47 Created:5/15/2009 Pending
[5/15/09] Please include all hydrology calculations in the drainage report. Please compare existing flows
with proposed flows as well.
Number:48 Created:5/15/2009 Pending
[5/15/09] All detention calculations need to include half of Buckingham Street along the site's frontage.
Staff Review Comments
Number: 17 Created: 5/12/2009
[5/12/091 The truck scale has not been shown on the utility plans.
City of
Pending
Topic: Plat
Number:18 Created:5/12/2009 Pending
[5/12/091 The plat indicates that there is 58 feet of existing row on Buckingham Street. From prior plats
and that dedicated by separate document last fall I calculate that it is 76 feet in width.
Number:19 Created:5/12/2009 Pending
[5/12/09] Label the additional row that was dedicated last fall by this property.
Number:20 Created:5/12/2009 Pending
[5/12/091 The very west portion of the property — row needs to be dedicated so that it is in line with the rest
of the property.
Number:21 Created:5/12/2009 Pending
[5/12/091 What part of the drainage and access easement is proposed for vacation? And before the
access easement can be vacated need to see some sort of verification that x-access is not necessary for
the property to the south.
Number:22 Created:5/12/2009 Pending
[5/12/09] A detention easement needs to be dedicated for the new pond area and overflow path.
Department: Light & Power Issue Contact: Rob Irish
Topic: General
Number:9 Created:5/12/2009 Pending
[5/12/09] Please show existing transformer on site plan. Also, show existing electric oval vault adjacent to
this site on Buckingham. Coordinate with Light & Power if either of these will need to be relocated.
Number:10 Created:5/12/2009 Pending
[5/12/09] Any relocation or modification to existing electric facilities will be at the owner's expense.
Number:11 Created:5/12/2009 Pending
[5/12/09] Owner will need to submit a C-1 form and One -Line diagram for any increase or change in power
requirements. If a new transformer is needed owner will need to coordinate a transformer location within
10' of an all weather driveover surface with Light & Power.
Number:12 Created:5/12/2009 Pending
[5/12/091 Owner is responsible for Electric Capacity Fees and Building Site charges for the unpaid area
where the Infultration/Detention Pond will be and any additional increase in power requirements.
Department: PFA Issue Contact: Carle Dann
Topic: Fire
Number:42 Created:5/14/2009 Pending
REQUIRED ACCESS: Fire access roads (fire lanes) shall be provided for every facility, building or portion
of a building hereafter constructed or moved into or within the PFA's jurisdiction when any portion of the
Staff Review Comments
Fort Collins
Number:27 Created: 5/12/2009 Pending
[5/12/09] This project is shown tying into an existing detention pond to the south and east of the site. From
what I could find on the existing plats and documents that we have on file a drainage easement does not
exist to tie these two sites together. A prior plan seemed to indicate that an easement existed, but I didn't
find a record of it in our files. If it exists please provide a copy of the recorded document. If it doesn't exist
an off -site drainage easement(s) will need to be dedicated and a letter or letters of intent from the adjacent
property(ies) will be needed prior to being able to schedule the hearing.
Number:28 Created: 5/12/2009 Pending
[5/12/091 For the south profile to the east of the site. What is being shown? It looks as if you are tying into
the existing curb and gutter in the plan view, but the profile appears to be all new and not matching the
existing grade.
Number:29 Created: 5/12/2009 Pending
[5/12/09] The street cross section provided is incorrect. Buckingham is considered a Minor Collector
Street in this section.
Number: 30 Created: 5/12/2009
[5/12/09] A soils report will need to be submitted with the final submittal.
Number: 31 Created: 5/12/2009
[5/12/09] A striping plan will need to be submitted with the final plans.
Number: 32 Created: 5/12/2009
[5/12/091 Technical Services had the following comments -
1. Boundary Closes, legal closes, but which one reflects the limits of the property?
2. Please remove "PDP" from the title and statement of ownership and subdivision.
3. Please add the legal description to the site plan.
4. Scanning issues on Landscape, Site and Plat.
5. Please change subtitle. See note on the Plat for changed verbiage.
Pending
Pending
Pending
Topic: Landscaping
Number:14 Created: 5/12/2009 Pending
[5/12/09] The parking spaces on the east side of the property straddling the property line are not currently
shown existing or to be constructed on the utility plans. To construct these, a construction easement will be
needed from the adjacent property owner. You might also want an easement or agreement with them
regarding the use of the spaces.
Number:15 Created: 5/12/2009 Pending
[5/12/09] There are several GATES indicated on the plans. Are these new or existing and is there any
other fence that is new or existing? Currently as labeled there are only gates and no fences on the site.
Number:16 Created: 5/12/2009 Pending
[5/12/091 The office trailer is not shown on the utility plans. Is this a temporary or permanent structure?
Staff Review Comments C'' 'of
�t�t Collins
Topic: Lighting Plan
Number:38 Created:5/13/2009 Pending
[5/13/09] Where are the existing street lights?
Is there no lighting at the north entrance?
Topic: Planning Objectives
Number:33 Created:5/13/2009 Pending
[5/13/09] Please provide a short summary paragraph of what you are proposing. Explain the uses please.
Topic: Site Plan
Number:36 Created:5/13/2009 Pending
[5/13/09] Please add the following to the Site Plan:
North Arrow on Vicinity and Site Plan
Percentage and square footage of driveway and parking
Percentage and square footage of landscaped area
Show # of spaces and decipher handicap
Where is bicycle parking?
Please label existing and proposed s.f. on footprint
Show some context, what is beyond these boundaries (1501)
What is the proposed treatment of the perimeter, fencing?
Please label land uses, heavy ind, recycling...
What are Recycling Roll-ons?
What is happening with the temporary parking spaces on the west side of the building?
Department: Current Planning
Topic: General
Number: 41
[5/13/09] No comment.
Issue Contact: Dana Leavitt
Created:5/13/2009 Pending
Department: Engineering Issue Contact: Sheri Langenberger
Topic: General
Number:13 Created:5/12/2009 Pending
[5/12/09] See plans for additional redline comments.
Number:23 Created:5/12/2009 Pending
[5/12/09] Is the sidewalk shown along the frontage of the property the existing sidewalk?
Number:24 Created:5/12/2009 Pending
[5/12/09] Need to label the drainage pans and widths.
Number:25 Created:5/12/2009 Pending
[5/12/09] IF you are planning on phasing construction you will need to include phase lines and notes as a
part of the final plans.
Number:26 Created:5/12/2009 Pending
[5/12/09] Few grade lines at the property lines do not tie to anything.
Staff Review Comments City of
Fort Cothns
Date: 5/15/2009
COLORADO IRON AND METAL PDP - TYPE I
SELECTION CRITERIA: Status = Unresolved
ISSUES:
Department: Current Planning Issue Contact: Emma McArdle
Topic: General
Number:34 Created:5/13/2009 Pending
[5/13/091 Is this property under single ownership? If multiple owners please provide information on each.
Number:35 Created:5/13/2009 Pending
[5/13/091 When do you expect facilities to be up and running?
Number:39 Created:5/13/2009 Pending
[5/13109] Is recycling done on site?
Are the Roll -offs for the public to bring recycling?
Number:40 Created:5/13/2009 Pending
[5/13/09] Is the north parking lot for employees, customers, all? Or will west parking be maintained for
employees? Please make clear on plans what the plan is, reference note.
Number: 50 Created: 5/13/2009
[5/13/09] The proposed additions to the existing building will enhance the character of the building.
Topic: Landscaping
Number:37 Created:5/13/2009 Pending
[5/13/091 Please address the following issues on the Landscape Plan:
Are there any trees to be removed?
Hard to decipher sidewalk, label or use fill.
Full stocking of trees not met in front of Building 2. Recycling Roll-ons in place of potential landscaping,
may need mod. Of standard.
There is a fence and gate shown, what type please describe.
Parking lot perimeter trees and street trees are not adequate, there needs to be shrubs and trees between
sidewalk and parking lot. There are too many street trees, street lights are not shown, street canopy/shade
trees need to be 40' from street lights.
Landscape islands shall have a shade tree with at least 80 s.f. of ground to support.
Is there fencing along the sides and rear of the property?
Show existing street lights
Show where bike parking is.
Is the walk through the parking lot raised?
Please label existing trash enclosure. Will this still be used?
N
1W
,�of
t� Collins
May 15, 2009
Troy Jones
MTA Planning and Architecture
171 N College Ave
Fort Collins, CO 80524
Dear Troy,
Current Planning
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6750
970.224.6134 - fax
fcgo v. com/currentplanning
The attached are comments from City Staff conceming the request for Colorado Iron and Metal, PDP,
which was presented before Staff Review on May 13, 2009.
This is a request to replat parts of Lot 1, 2 and 3 of Vanworks Subdivision, Lot 3 of Odell, Lot 23 of a Replat
of North Lemay Subdivision, and Lot 1 of 2nd Replat of North Lemay Subdivision. The proposal also
includes the addition of heavy industrial and recycling uses and two additional buildings on the lot. The
property is in the I, Industrial Zone District. The proposed uses are permitted in the zone district subject to
administrative review.
Following Staff Review, it was determined that staff shall require a second round of review for this proposal.
Please make revisions per staffs comments prior to next submittal. If you have questions regarding any
comments please get in touch with the contact that raised the particular issue.
Sincerely,
Emma McArdle
City Planner
CC: File
Sheri Langenberger, Engineering
Rob Irish, Light and Power
Carte Dann, Poudre Fire Authority
Wes Lemarque, Stormwater
Roger Buffington, Wastewater
Jenny Nuckols, Zoning