HomeMy WebLinkAboutCOLORADO IRON & METAL - PDP - 20-09 - CORRESPONDENCE - REVISIONSi Number: 72 Created: 10/16/2009 [4/7/10] OK for final compliance. [10/16/09] The slope of the detention pond bottom should be 2% or .5% with a drainage pan. Number: 73 Created: 10/16/2009 [4/7/101 OK for final compliance. [10/16/09] The City's standard water quality outlet structure needs to be incorporated into the design. Department: Stormwater-Water-Wastewater Issue Contact: Roger Buffington Topic: WaterMastewater Number: 94 Created: 4/6/2010 [4/6/10] An additional note may be needed on the fire hydrant relocation. It will be field checked soon to determine if needed. Department: Zoning Issue Contact: Jenny Nuckols Topic: Zoning Number: 4 Created: 4/30/2009 [4/7/10] [4/30/09] On the site plan please show and label the new building envelope since there is proposed changes to the north side. Be sure and return all of your redlined plans when you re -submit. If you have any questions regarding these issues or any other issues related to this project, please feel free to call me at (970) 221-6750. Sincerely, Emma McArdle City Planner Page 5 ., [4/6/10] The concrete sidewalk culvert should be used since water is entering the site from the roadway. I taped a copy of this detail to the plans. Topic: Landscaping Number: 89 Created: 4/6/2010 [4/6/10] What landscaping is in Phase 1 and what is in Phase 2? This has been updated in the Hearing Plan Set (4/12/10). Topic: Site Plan Number: 86 . Created: 4/6/2010 [4/6/10] The site plan is not showing the screening fence on the north side of the parking lot. If planning doesn't feel that this is to be shown on the site plan — I am okay with that. Number: 87 Created: 4/6/2010 [4/6/10] Where will the handicap parking be with Phase 1? Currently all the handicap parking is shown in the front lots that are identified as Phase 2. Number: 88 Created: 4/6/2010 [4/6/10] What is to be built to connect the buildings to the public sidewalk with phase 1? Department: Technical Services Issue Contact: Jeff County Topic: Landscape Plans Number: 97 Created: 4/7/2010 [4/7/10] Sheets 3 & 4 of the Landscape Plans have minor line over text issues. Topic: Plat Number: 64 Created: 10/14/2009 [4/7/10] The boundary & perimeter legal close. 110/14/09] The boundary and perimeter legal description close. Topic: Utility Plans Number: 67 Created: 10/14/2009 [4/7/10] There are still minor line over text issues on the Utility Plans. [10/14/09] There are several line over text issues. Number: 68 Created: 10/14/2009 [4/7/10] Please fix the text on the Water Meter Detail on Sheet 9 of the Utility Plans. [10/14/09] Two details on sheet 9 have text that is illegible. Department: Stormwater-Water-Wastewater Issue Contact: Wes Lamarque Topic: Stormwater Number: 70 Created: 10/16/2009 [4/7/10] Reminder comment. [10/16/09] The outfall for this site is proposed to drain into the Lincoln Channel. Larimer County needs to approve this outfall location. The County owns and maintains this channel. Number: 71 Created: 10/16/2009 [4/7/10] OK for hearing. Can discuss during final compliance. [10/16/09] Please provide documentation to back up the 20% reduction in volume and reduced drainage easement for the existing detention pond. Page 4 [5/12/09] IF you are planning on phasing construction you will need to include phase lines and notes as a part of the final plans. Number: 26 Created: 5/12/2009 [4/6/10]Letter of intent received. Final easement will be needed prior to approval of plans. Processing and filling fees will be due for the processing and filing of off -site easements. [10/12/09] Need to show how the grading at the SW corner of the site will tie back into existing grades. It appears that off -site grading or construction easements will be needed. Letters of intent to grant these easements will need to be provided prior to the project being scheduled for hearing. [5/12/09] Few grade lines at the property lines do not tie to anything. Number: 30 Created: 5/12/2009 [4/6/10] [10/12/09] Still applicable. [5/12/09] A soils report will need to be submitted with the final submittal. Number: 31 Created: 5/12/2009 [4/6/10] [10/12/09] Still applicable [5/12/09] A striping plan will need to be submitted with the final plans. Number: 53 Created: 10/12/2009 [4/6/10] [10/12/09] The building square footages have changed since the last review. The application fees (TDRF) increased due to the increase in the size of the buildings. The project owes an additional $349. This can be paid at the time of final submittal with the final submittal fees. Number: 56 Created: 10/12/2009 [4/6/10] Letter of intent received. Final easement will be needed prior to approval of plans. Processing and filling fees will be due for the processing and filing of off -site easements. [10/12/09] An off -site easement for the storm pipe is needed with this design. A letter of intent from the off -site property owner(s) is needed prior to being able to schedule this project for hearing. Number: 81 Created: 4/6/2010 [4/6/10] Is there any fencing or other improvements that are to be installed with the minor amendment that need to be removed with this project? You might want to at least note what they might be. Number: 82 Created: 4/6/2010 [4/6/10] Please note what material the raised crosswalk is to be. Number: 83 Created: 4/6/2010 (4/6/10] Final will need to show what erosion control will be needed for Phase 2. Number: 84 Created: 4/6/2010 [4/6/10] Since the north flowline is not existing. Please show the proposed north flowline, to the east of the site, with the minimum .5% grade. The centerline and south flowline appear to be existing so they are okay to be shown at the .4%. Number: 85 Created: 4/6/2010 Page 3 [4/6/10] What is happening to the plants that will screen the fencing for the Minor Amendment? Will they be moved? Or thrown out? Please show them on the Existing Tree Plan Topic: Site Plan Number: 36 Created: 5/13/2009 [4/6/10] 1 asked in my original comment to show at least 150' of off -site context, it is still not shown. You will need to change the scale of the drawings to do this. [10/22/09] All addressed but no more context has been shown. 15/13/09] Please add the following to the Site Plan: North Arrow on Vicinity and Site Plan Percentage and square footage of driveway and parking Percentage and square footage of landscaped area Show # of spaces and decipher handicap Where is bicycle parking? Please label existing and proposed s.f. on footprint. Show some context, what is beyond these boundaries (150') What is the proposed treatment of the perimeter, fencing? Please label land uses, heavy ind, recycling... What are Recycling Roll-ons? What is happening with the temporary parking spaces on the west side of the building? Number: 76 Created: 10/22/2009 [4/6/10] Either take it all off or show all existing, there is some still there, west of the building. [10/22/09] Take landscape info off the Site Plan, trees, turf, mulch... Leave paving details on though. Number: 90 Created: 4/6/2010 [4/6/10] Either show all existing landscaping or don't show any, grey it out so I know it is existing, landscaping added in the minor amendment should be included also if you choose to show it. Number: 91 Created: 4/6/2010 [4/6/10] Will any of the fencing that will be added through the minor amendment stay? Number: 92 Created: 4/6/2010 [4/6/10] Please show me what the minor amendment is approving with lighter line weights. Department: Engineering Issue Contact: Sheri Langenberger Topic: General Number: 13 Created: 5/12/2009 [4/6/10] [10/12/09] [5/12/09] See plans for additional redline comments. Number: 25 Created: 5/12/2009 [4/6/10] May need separate sheets showing what is to be done with each phase. Need to show how sidewalks from the buildings will be constructed out to the public sidewalk through Phase 2 for Phase 1. How will the street drainage go through Phase 2 until the parking lots are built? Are swales to be constructed? [10/12/09] Repeat at final will need to provide phasing plans showing what is to be built, graded and installed with each phase. Page 2 City of Fort Collins STAFF PROJECT REVIEW Troy Jones Date: 4/29/2010 MTA Planning & Architecture 171 N. College Avenue Fort Collins, CO 80524 Staff has reviewed your submittal for COLORADO IRON AND METAL PDP - TYPE I, and we offer the following comments: ISSUES: Department: Current Planning Issue Contact: Emma McArdle Topic: Fencing Number: 93 Created: 4/6/2010 [4/6/10] Please see the redlined Fencing Plan. There are several things that I need clarification on: -Darken line weight of fencing; there is barely a difference in some places, - What is happening along the east property line? Is there fencing? -Either label something's or take them off this plan completely, the grayed out items should only be the basics. Topic: General Number: 98 Created: 4/29/2010 [4/29/10] Please clean up plan sets to show curb/gutter info everywhere, currently it is missing in some areas. Number: 99 Created: 4/29/2010 [4/29/10] Let's discuss the addition of notes regarding phasing; there is two options to address parking lot landscaping. I want to make sure that staff reviews the parking lot and landscaping even if the entry feature is not built. So the parking lot shall either be tied to a certificate of completion or the CO of the entry feature. Number: 100 Created: 4/29/2010 [4/29/10] The entry feature does not show the entry door very clearly; let's get a little definition on this elevation. Topic: Landscaping Number: 80 Created: 10/22/2009 [4/6/10] Please make them add up to 100% (10/22/09] Please show % of trees. Number: 95 Created: 4/6/2010 [4/6/10] Please double check the "Jumperus Chinenis 'Armstrong"' plant, this does not appear on the City's Approved Plant List. Number: 96 Created: 4/6/2010 Page 1 Fort Collins Planning, Development & Transportation Community Development & Neighborhood Services 281 North College Avenue P_O. Box 580 Fort Collins, CO 80522.0580 Phone: (970) 221-6760 Letter of Tranemi*+all To: ►�(O� (aniz Date: Project: T SMITTED HEREWITH ARE: Redlined Utility Plans �4 'tioES ro + V�c� - 5 0S'1 See attached sheet for numb Vol copies to resubmit waC ❑ Redlined Storm Drainage Report �r>' ❑ Development Agreement Please sign, seal, date, and return all copies of this agreement. Changes in the agreement take two (2) days to process if they are acceptable to the City. Please take this into account in your schedule. Again, all copies must be returned. ❑ Original Mylars Needing Revisions Please return with the "post -it" notes intact. ❑ Original Mylars with City Signatures Please return one (1) mylar and signed and stamped blueline print copies for our files. ❑ Development Construction Permit Application Please fill out and return to the front counter with application fee and all required attachments. ❑ Development Construction Permit for your Signatures Please sign (but do not date) and return. ❑ Attached is your Copy of the Development Construction Permit ❑ Draft Development Agreement For your review and comments. Please Call with your comments or questions. Let me know if everything is okay. ❑ Attached is your Copy of the Development Agreement Other: