HomeMy WebLinkAbout1993-158-10/19/1993-PROJECT SCOPE ALTERATIONS RESOLUTION 92-149 SENIOR CITIZEN CENTER RESOLUTION 93-158
OF THE COUNCIL OF THE CITY OF FORT COLLINS
CONCERNING THE SCOPE OF THE NEW SENIOR CITIZEN CENTER
WHEREAS, in Resolution 92-149, the Council of the City of Fort Collins
formally gave its support to the interior composition of the new Senior Citizen
Center to include a lobby, reception area, lounge, public restrooms, offices,
multi-use room, kitchen, classrooms/meeting rooms, media center/library,
billiards/pool room, fitness center, jog/walk track, four-lane lap pool and spa,
locker rooms, wet craft room and storage; the total to equal approximately 40,000
square feet; and
WHEREAS, the estimated cost to construct the new Senior Citizen Center
Project was estimated to be $3,913,800, and this money was available in the
project budget; and
WHEREAS, the City has received bids for the construction of the new Senior
Citizen Center Project, and the low bid exceeds the estimated construction costs
by the amount of $456,000; and
WHEREAS, the Project Team, working with the low bidder, has developed a
list of alterations in the scope of the project and is recommending the Council
approve these alterations in the scope of the project; and
WHEREAS, there are presently sufficient funds in the total project budget
to allow the City to enter into the contract for construction of the project; and
WHEREAS, the City's Parks and Recreation Board and the Senior Advisory
Board recommend that construction of the project not be rebid and should proceed
as expeditiously as possible.
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF FORT COLLINS
as follows:
Section 1. That the Council hereby approves the alterations in scope of
the new Senior Citizen Center Project as listed on Exhibit "A," which is attached
hereto and incorporated herein by this reference, and authorizes the City to
proceed with the construction of this project; provided, however, that the
anticipated costs of the project shall first be further reduced by the additional
sum of $100,000, in such manner as the Council may subsequently approve by
Resolution.
Section 2. That a resolution approving the method of reducing the project
budget by $100,000 shall be presented for Council consideration at its regular
meeting on November 2, 1993.
Passed and adopted at a regular meeting of the Council of the City of Fort
Collins held this 19th day of October, A.D. 1993.
ATTEST: ayor
City Clerk
EXHIBIT A
SENIOR CITIZEN CENTER
Project Scope Alterations
October 19, 1993
1. Change the pool filtration system from gutter to skimmer system:
save $25,000.
2. Change plastic laminate lockers to painted metal :
save $18,500.
3. Delete wood ceiling in port cochere and replace with painted surface:
save $8,000.
4. Delete skylights in fitness center and pool roof:
save $24,700.
5. Delete outdoor pool terrace and re-landscape:
save $7,000.
6. Use Colorado native sandstone instead of other:
save $43,000.
TOTAL: $126,200