WHEREAS, Fort Collins Utilities currently has certain infrastructure (a 42-inch sanitary
sewer and a 12-inch water main) that needs to be relocated to accommodate the Colorado
Department of Transportation (CDOT) proposed construction of a new bridge over the Poudre
River at Mulberry Street; and
WHEREAS, the estimated total cost of the relocation is estimated to be $106,179, with
80% coming from the Wastewater Fund ($84,943) and 20% coming from the Water Fund
($21,236), which cost will be reimbursed by the Colorado Department of Transportation
(CDOT); and
WHEREAS, Article V, Section 9, of the City Charter authorizes the City Council to
make supplemental appropriations by ordinance at any time during the fiscal year, provided that
the total amount of such supplemental appropriations, in combination with all previous
appropriations for the fiscal year, does not exceed the current estimate of actual and anticipated
revenues to be received during the fiscal year; and
NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF
FORT COLLINS as follows:
Section 1. That there is hereby appropriated from unanticipated revenue in the
Wastewater Fund the sum of EIGHTY FOUR THOUSAND NINE HUNDRED FORTY THREE
DOLLARS ($84,943) to relocate utility facilities in conflict with the CDOT proposed
construction of a new bridge over the Poudre River at Mulberry street.
Section 2. That there is hereby appropriated from unanticipated revenue in the Water
Fund the sum of TWENTY ONE THOUSAND TWO HUNDRED THIRTY SIX DOLLARS
($21,236) to relocate utility facilities in conflict with the CDOT proposed construction of a new
bridge over the Poudre River at Mulberry street.
Introduced, considered favorably on first reading, and ordered published this 5th day of
June, A.D. 2012, and to be presented for final passage on the 17th day of July, A.D. 2012.
OF FORtCO`
U��. .,,...... ., ` Nta or
ATTEST: 4erk
� �� c2n
co Qo0.
1eteFibi Ci ..A
Passed and adopted on final reading on the 17th day of July, A.D. 2012.
OF FORT CO
<<i i�/L.2riJ
'•.ZNMAyor
ATTEST: ��AL
&�a L6 / o
•C LORPO
City Clerk
2