HomeMy WebLinkAbout143 - 11/01/2011 - AMENDING CHAPTER 26 OF THE CITY CODE TO REVISE ELECTRIC DEVELOPMENT FEES AND CHARGES ORDINANCE NO. 143, 2011
OF THE COUNCIL OF THE CITY OF FORT COLLINS
AMENDING CHAPTER 26
OF THE CODE OF THE CITY OF FORT COLLINS
TO REVISE ELECTRIC DEVELOPMENT FEES AND CHARGES
WHEREAS, the City Council is empowered and directed by Article XII, Section 6, of the
City Charter to fix, establish, maintain and provide for the collection of such rates, fees or charges
for utility services furnished by the City as will produce revenues sufficient to pay the costs,
expenses and other obligations of the electric utility, as set forth therein; and
WHEREAS, the City Council has determined that it is appropriate for new development to
contribute its proportionate share of providing capital improvements; and
WHEREAS,Section 26-471 of the City Code requires the City Manager and staffto annually
consider the parameters and rates related to setting electric development fees and charges; and
WHEREAS, Section 26-471 of the City Code requires that the electric development fees be
presented to the City Council for approval no less frequently than biennially; and
WHEREAS, on November 16, 2010 the City Council adopted Ordinance No. 115, 2010,
which established the electric development fees now in effect; and
WHEREAS,the City Manager and staff have recommended to the City Council the following
adjustments to the electric development fees and charges for all invoices paid on or after January 1,
2012; and
WHEREAS, based on the foregoing, it is the desire of the City Council to amend Chapter
26 of the City Code to revise electric development fees and charges.
NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF FORT
COLLINS as follows:
Section 1. That Section 26-471 the Code of the City of Fort Collins is hereby amended
by the addition of a new subsection (e) which reads in its entirety as follows:
(e) This Section does not apply to wholesale energy transactions, as defined in
this Article. Any applicable fees and charges will be addressed in a written services
agreement subject to approval by City Council in accordance with Section 6 of
Article XII of the Charter, if applicable.
Section 2. That Section 26-472(b) and (c) of the Code of the City of Fort Collins is
hereby amended to read as follows:
Sec. 26-472. Residential electric development fees and charges.
r
(b) The ECF shall be the total of the site footage charge,,dwelling charge and
systems modification charge, to be determined as follows:
(1) the site footage charge shall be the combined total of:
a. four and nine hundred fifty thousandths cents($0.04950)per square
foot of developed site square footage, including all applicable tracts
but excluding the area dedicated public rights-of-way; and
b. ten dollars and eight cents ($10.08) per lineal foot of the developed
site abutting a dedicated street or roadway.
(2) the dwelling unit charge shall be as follows:
a. for a single-family panel size with one-hundred-fifty-amp service
(nonelectric heat), one thousand two hundred eighty-one dollars
($1,281.) per dwelling unit;
b. for a single-family panel size with two-hundred-amp service or with
one-hundred-fifty-amp service (electric heat), two thousand one
hundred sixty-five dollars ($2,165.) per dwelling unit;
C. for a multi-family panel size with one-hundred-fifty-amp service
(nonelectric heat), eight hundred fifty-four dollars ($854.) per
dwelling unit;
d. for a multi-family panel size with two-hundred-amp service or with
one-hundred-fifty-amp service (electric heat), one thousand five
hundred nineteen dollars ($1,519.)per dwelling unit.
(3) a system modifications charge will apply when a new or modified service will
require infrastructure in addition to or different from the standard base
electrical system model. The differential costs associated with such system
modifications will be included in the calculated ECF.
(c) A Building Site Charge("BSC")for any new or modified residential service
shall be paid prior to issuance of a building permit for the related construction or
modification. The BSC shall be based upon the current rates as of the time of
issuance of the building permit. The BSC shall be the total of the secondary service
charges, and any additional charges, determined as follows:
(1) the secondary service charge shall be as follows:
-2-
Secondary Charge Plus Per Foot
Service Size (up to 65 feet) Charge For Each
Foot Over 65
1/0 service $642.00 $4.65/Foot
4/0 service $821.00 $5.82/Foot
350 kCM Service $818.00 $6.54/Foot
1/0 Mobile Home $503.00 N/A
Service
4/0 Mobile Home $646.60 N/A
Service
(2) actual special costs to the utility of installation of secondary service resulting
from site conditions shall be included in the BSC as additional charges. Such
conditions may include,but are not limited to,frozen or rocky soil, concrete
cutting and asphalt replacement.
Section 3. That Section 26-473(b) and (c) of the Code of the City of Fort Collins is
hereby amended to read as follows:
Sec. 26-473. Nonresidential electric development fees and charges.
(b) The ECF shall be the total of the site footage charge,kVA service charge and
systems modification charge, to be determined as follows:
(1) the site footage charge shall be the combined total of:
a. four and nine hundred fifty thousandths cents ($0.04950) per square
foot of developed site square footage, including all applicable tracts
but excluding the area of dedicated public rights-of-way; and
b. thirty-eight dollars and thirty cents ($38.30) per lineal foot of the
developed site abutting a dedicated street or roadway.
(2) the kVA service charge shall be determined as follows:
a. for customer electric loads served by the utility the kVA service
charge shall be:
i. utility owned transformers: the kVA service charge shall be
fifty-nine dollars and four cents ($59.04) per kilovolt-amp
(kVA) of service load rating.
-3-
ii. customer owned transformers: the kVA service charge shall
be forty-eight dollars and fifty-nine cents ($48.59) per
kilovolt-amp (kVA) of service load rating.
b. for the utility to receive customer generation in excess of the
customer's electric service provided by the utility,the following KVA
service charge will also apply:
i. utility owned transformers: the kVA service charge shall be
forty-eight dollars and fifty-nine cents($48.59)per kilovolt-
amp (kVA) of generation service rating in excess of the
service load rating as paid per subparagraph (2)a.i. above.
Such ratings shall be determined by the Utilities Executive
Director.
ii. customer owned transformers: the kVA service charge shall
be thirty-eight dollars and nine cents ($38.09) per kilovolt-
amp (kVA) of generation service rating in excess of the
service load rating paid per subparagraph(2)a.ii.above. Such
ratings shall be determined by the Utilities Executive
Director.
(3) a system modifications charge will apply when a new or modified service will
require infrastructure in addition to or different from the standard base
electrical system model. The differential costs associated with such system
modifications will be included in the calculated ECF.
(c) A Building Site Charge ("BSC") for extending primary,circuitry to the
transformer for any new or modified nonresidential service shall be invoiced and paid
in the same manner and at the same time as the ECF is invoiced and paid pursuant
to Subsection (a) of this Section. The BSC shall be the total of the primary circuit
charge, transformer installation charge and any additional charges, determined as
follows:
(1) the primary circuit charge for service from the utility source to the
transformer shall be as follows:
a. for single-phase service, a charge of nine dollars and fifteen cents
($9.15)per foot of primary circuit;
b. for three-phase service, a charge of eighteen dollars and zero cents
($18.00) per foot of primary circuit.
(2) the transformer installation charge shall be as follows:
-4-
a. for single-phase service, a charge of one thousand two hundred
seventy-eight dollars ( $1,278.) per transformer;
b. for three-phase service, a charge of two thousand three hundred
eighty-five dollars ( $2,385.) per transformer.
(3) actual special costs to the utility of installation of service resulting from site
conditions shall be included in the BSC as additional charges. Such
conditions may include,but are not limited to,frozen or rocky soil, concrete
cutting and asphalt replacement.
Section 4. That the amendments to Chapter 26 of the City Code contained herein shall
go into effect as of January 1, 2012.
Introduced, considered favorably on first reading, and ordered published this 18th day of
October, A.D. 2011, and to be presented for final passage on the 1 st day of November, A.D. 2011.
OF FORTc
V; ,<� Ma or
ATTEST: Y � `�� tccoo
.
c�<ARA�0
City Clerk
Passed and adopted on final reading on the 1 st day of November, A.D. 2011.-
C. FORT O M or
ATTEST: `-�• •' • • ''c
SEAL
City Clerk
C�<ORAoO
-5-