HomeMy WebLinkAbout418 E Foothills Pkwy - Special Inspections/Engineering - 01/18/20183990 Fox Street TEL 303.237.2072 www.olssonassociates.com Denver, CO 80216 FAX 303.237.2659 January 18, 2018 McWhinney Attn: Tucker Isgrig 1800 Wazee Street Suite 200 Denver, CO 80202 RE: Foothills Mall Multifamily – Building 08 – Final Inspection Report Permit No. B1601385 418 E. Foothills Parkway Fort Collins, Colorado Olsson Associates Project No. 016-1668 Dear Mr. Isgrig: In accordance with your request, representatives of Olsson Associates have provided Special Inspections and Construction Materials Testing services at the above referenced site. The items observed include foundation bearing materials, structural fill placement, reinforced concrete, post-tension tendon placement and elongation measurement, structural steel observation, and placement of the ATS shear wall hold downs. Our services were provided on a part to full-time basis between October 21, 2016 and December 27, 2017 as scheduled by the general contractor. Summary of Activities Foundation Bearing Materials The bearing materials in the bases of the grade-beam footing excavations in the following locations were observed during this reporting period: November 3, 2016 - Bearing evaluation along Lines A-C, 1-5 November 4, 2016 - Hand auger testing along Line B, 1-5 The bearing materials were evaluated with respect to the 1,500-psf design bearing pressure. Hand auger testing was performed to sample material beneath the bearing materials to delineate areas of deleterious debris. Encountered deleterious material beneath the foundation systems and “ribs” of the post-tensioned floor slab between Lines A-C, 1-5 was removed. Page 2 of 3 Earthwork Observation Samples of on-site and imported materials were obtained for laboratory moisture-density (standard Proctor), P-200, and Atterberg Limits testing. Field moisture-density tests were performed on the structural fill placed in the following locations during this reporting period: October 21, 2016 - Utility trench backfill along Line B, 2-3 November 2, 2016 - Structural fill between Lines A-C, 1-5 Results of the field density tests are summarized in the attached reports. Concrete Observation Placement of the reinforcing steel and concrete in the following locations was observed during this reporting period: November 7, 2016 - Foundations and grade beams between Lines A-C, 1-5 November 8, 2016 - Foundations and grade beams between Lines A-C, 1-5 November 16, 2016 - Post-tensioned floor slab between Lines A-C, 1-5 November 19, 2016 - Post-tensioned floor slab between Lines A-C, 1-5 Placement of the reinforcing steel in the above referenced locations was observed on a part-time basis. Field tests were performed and test specimens were cast with concrete placed in these locations. Olsson’s field representatives observed the placement of concrete on a full-time basis. Results of the compressive strength tests can be found in the attached reports. Post-Tensioned Concrete Observation Olsson observed the marking and stressing of the post-tensioned tendons within the floor slab of Building 8 on a full-time basis during this reporting period: November 16, 2016 - Tendon layout in the floor slab between Lines A-C, 1-5 December 1, 2016 - 100% stressing of post-tension tendons Lines A-C, 1-5 December 22, 2016 - 100% stressing of post-tension tendons Lines A-C, 1-5 Olsson prepared post-tensioned tendon layouts to number and reference each individual tendon. Final elongations were measured and reported to the post-tension slab designer for approval. The measured elongations can be found in the attached reports. Shear Wall Hold Down Observation On November 15, 2017 and December 27, 2017, the placement of the ATS hold down system hardware was observed including plate to anchor bolt welds, rod sizes and nut connections. Status of Compliance This report represents Olsson's final inspection report for Building 8 at the Foothills Mall Multifamily Apartment Complex in Fort Collins, Colorado. The special inspection items observed and tested by our field personnel include foundation bearing materials, structural fill placement, reinforced concrete, post-tensioned tendon placement, and elongation measurements and placement of the ATS shear wall hold-down system. To the best of our belief and knowledge, the items observed and/or tested by our field personnel and explicitly reported in the attached test and inspection reports were in general compliance with the project specifications or recommendations of the design engineer. If you have any questions regarding this report, or if we may be of any further service, please contact us at 303.237.2072. Respectfully Submitted; OLSSON ASSOCIATES Attachments Compaction Test Reports Compressive Strength of Concrete Reports Post-Tension Observation Reports Special Inspection Daily Reports Page 3 of 3 Braden Hirsch, PE Associate Engineer Colorado License No. 51920 Test Results Test # Retest Of Test Date Proctor ID Method Soil Classification Optimum Moisture (%) Maximum Dry Density (pcf) In Place Moisture (%) In Place Dry Density (pcf) Probe Depth (in) Percent Compaction Min/Max Comp. (%) Optimum Moisture Tolerance (%) Remark 401 10/21/16 3 C SP-SC 12.2 122.1 11.2 118.3 8 97 95 / 103 -2 / 2 A 402 10/21/16 3 C SP-SC 12.2 122.1 12.0 115.4 8 95 95 / 103 -2 / 2 A Test Information Test # Test Location Elevation Reference Gauge Make / Model / SN Field Technician 401 Utility Trench Backfill: Building 8- Interior Water Grid B-2 0.0 FSE Troxler 3440 23106 Sheppard, Jordan 402 Utility Trench Backfill: Building 8; Interior water Grid B-3 0.0 FSE Troxler 3440 23106 Sheppard, Jordan Remarks A: Tests results comply with specifications Comments Tests are "Direct Transmission" (Method A) unless probe depth is noted as "Backscatter". Gauge calibration data on file with the testing agency. Page 1 of 1 Compaction Test Report Test Method: ASTM D 6938 Report #: SNG-000090 Client: McWhinney Real Estate Services, Inc. Loveland, CO 80538 2725 Rocky Mountain Ave Ste 200 Project: McWhinney Foothills Mall Multifamily 016-1668 3990 Fox Street Fort Collins, CO Denver, CO 80216 Phone: 303-237-2072 | Fax: 303-237-2659 Denver Braden Hirsch Test Results Test # Retest Of Test Date Proctor ID Method Soil Classification Optimum Moisture (%) Maximum Dry Density (pcf) In Place Moisture (%) In Place Dry Density (pcf) Probe Depth (in) Percent Compaction Min/Max Comp. (%) Optimum Moisture Tolerance (%) Remark 414 11/4/16 4 B SM 7.2 125.2 7.4 125.5 8 100 95 / 103 -2 / 2 A 415 11/4/16 4 B SM 7.2 125.2 8.4 121.9 8 97 95 / 103 -2 / 2 A 416 11/4/16 4 B SM 7.2 125.2 9.2 119.8 8 96 95 / 103 -2 / 2 A Test Information Test # Test Location Elevation Reference Gauge Make / Model / SN Field Technician 414 Structural Fill: Building 8, Line 2, A-B 0.0 FSE Troxler 3440 23106 Sheppard, Jordan 415 Structural Fill: Building 8; Line B, 3-4 0.0 FSE Troxler 3440 23106 Sheppard, Jordan 416 Structural Fill: Building 8; Line C,4-5 0.0 FSE Troxler 3440 23106 Sheppard, Jordan Remarks A: Tests results comply with specifications Comments Tests are "Direct Transmission" (Method A) unless probe depth is noted as "Backscatter". Gauge calibration data on file with the testing agency. Page 1 of 1 Compaction Test Report Test Method: ASTM D 6938 Report #: SNG-000099 Client: McWhinney Real Estate Services, Inc. Loveland, CO 80538 2725 Rocky Mountain Ave Ste 200 Project: McWhinney Foothills Mall Multifamily 016-1668 3990 Fox Street Fort Collins, CO Denver, CO 80216 Phone: 303-237-2072 | Fax: 303-237-2659 Specimen Number Test Age Days Test Date Field / Lab Cure Days Average Cylinder Diameter (in) Cylinder Area (in²) Max Load (lbs) Strength (psi) Fracture Type Break Remark Capping Method 99-1 7 11/16/16 0 / 7 4.00 12.57 57,990 4,610 2 A1 U 99-2 28 12/07/16 0 / 28 4.01 12.63 77,990 6,180 2 B1 U 99-3 28 12/07/16 0 / 28 4.01 12.63 72,680 5,760 2 B1 U 99-4 28 12/07/16 0 / 28 4.01 12.63 77,160 6,110 3 B1 U 99-5 28 H 12/07/16 0 / 28 Test Age Average Strengths (psi): 7 Day - 4610, 28 Day - 6010 Break Remarks A1: Test result meets or exceeds 75% of the 28 day specified strength. B1: Test result meets or exceeds the 28 day specified strength. Capping Methods U: Unbonded Caps (ASTM C1231) Set #: 99 Specimen Size: 4" X 8" Specimens In Set: 5 Truck / Ticket #: 1622 / 49097617 Contractor: GBC Concrete Technician: Sheppard, Jordan Cast By: Sheppard, Jordan Date Cast: 11/09/16 Sampled From: End of Pump Placement Method: Pump Sample Details Batched: 08:35 MST Sampled: 09:20 MST Cast: 09:35 MST Truck Empty: 09:33 MST Placement Time: 58 (min) Placement Location: Footing Location Details: Building 8; Line A, 1-3 Sample Location / Notes: Grid A-1 Batch Log Strength: 4000 (psi) Air: 0.0 - 4.0 (%) Slump: 4 - 7 (in) Specifications Supplier: Martin Marietta Materials Plant: 751 Rigden 16349 Mix Design: N4513SP Specimen Number Test Age Days Test Date Field / Lab Cure Days Average Cylinder Diameter (in) Cylinder Area (in²) Max Load (lbs) Strength (psi) Fracture Type Break Remark Capping Method 100-1 7 11/15/16 1 / 6 4.01 12.63 43,730 3,460 2 A1 U 100-2 28 12/06/16 1 / 27 4.01 12.63 61,810 4,890 2 B1 U 100-3 28 12/06/16 1 / 27 4.01 12.63 63,610 5,040 3 B1 U 100-4 28 12/06/16 1 / 27 4.01 12.63 67,080 5,310 2 B1 U 100-5 28 H 12/06/16 1 / 27 Test Age Average Strengths (psi): 7 Day - 3460, 28 Day - 5080 Break Remarks A1: Test result meets or exceeds 75% of the 28 day specified strength. B1: Test result meets or exceeds the 28 day specified strength. Capping Methods U: Unbonded Caps (ASTM C1231) Set #: 100 Specimen Size: 4" X 8" Specimens In Set: 5 Truck / Ticket #: 1732 / 49097636 Contractor: GBC Concrete Technician: Sheppard, Jordan Cast By: Sheppard, Jordan Date Cast: 11/08/16 Sampled From: End of Pump Placement Method: Pump Sample Details Batched: 09:44 MST Sampled: 10:22 MST Cast: 10:35 MST Truck Empty: 10:30 MST Placement Time: 46 (min) Placement Location: Footing Location Details: Building 8; Line C,3-5 Sample Location / Notes: Grid C-3 Batch Log Strength: 4000 (psi) Air: 0.0 - 4.0 (%) Slump: 4 - 7 (in) Specifications Supplier: Martin Marietta Materials Plant: 751 Rigden 16349 Mix Design: N4513SP Specimen Number Test Age Days Test Date Field / Lab Cure Days Average Cylinder Diameter (in) Cylinder Area (in²) Max Load (lbs) Strength (psi) Fracture Type Break Remark Capping Method 109-1 3 11/22/16 3 / 0 4.01 12.63 33,310 2,640 2 A2 U 109-2 9 11/28/16 2 / 7 4.01 12.63 61,130 4,840 2 A1 U 109-3 30 12/19/16 2 / 28 4.01 12.63 79,700 6,310 2 B1 U 109-4 30 12/19/16 2 / 28 4.03 12.76 72,900 5,710 2 B1 U 109-5 30 12/19/16 2 / 28 4.02 12.69 70,060 5,520 2 B1 U 109-6 30 H 12/19/16 2 / 28 Test Age Average Strengths (psi): 3 Day - 2640, 9 Day - 4840, 30 Day - 5850 Break Remarks A2: Test result is less than 75% of the 28 day specified strength. A1: Test result meets or exceeds 75% of the 28 day specified strength. B1: Test result meets or exceeds the 28 day specified strength. Capping Methods U: Unbonded Caps (ASTM C1231) Set #: 109 Specimen Size: 4" X 8" Specimens In Set: 6 Truck / Ticket #: 510 / 49098726 Contractor: GBC Concrete Technician: Kozlowski, John Cast By: Kozlowski, John Date Cast: 11/19/16 Sampled From: End of Pump Placement Method: Pump Sample Details Batched: 06:58 MST Sampled: 08:00 MST Cast: 08:15 MST Truck Empty: 08:25 MST Placement Time: 87 (min) Placement Location: Slab on Grade - Interior Location Details: Building 8 Sample Location / Notes: Lines A.1-4 Batch Log Strength: 4000 (psi) Air: 0.0 - 4.0 (%) Slump: 4 - 7 (in) Specifications Supplier: Martin Marietta Materials Specimen Number Test Age Days Test Date Field / Lab Cure Days Average Cylinder Diameter (in) Cylinder Area (in²) Max Load (lbs) Strength (psi) Fracture Type Break Remark Capping Method 110-1 3 11/22/16 3 / 0 4.01 12.63 34,420 2,730 2 A2 U 110-2 9 11/28/16 2 / 7 4.01 12.63 69,410 5,500 2 A1 U 110-3 30 12/19/16 2 / 28 4.01 12.63 83,850 6,640 3 B1 U 110-4 30 12/19/16 2 / 28 4.01 12.63 84,670 6,700 2 B1 U 110-5 30 12/19/16 2 / 28 4.01 12.63 81,500 6,450 3 B1 U 110-6 30 H 12/19/16 2 / 28 Test Age Average Strengths (psi): 3 Day - 2730, 9 Day - 5500, 30 Day - 6600 Break Remarks A2: Test result is less than 75% of the 28 day specified strength. A1: Test result meets or exceeds 75% of the 28 day specified strength. B1: Test result meets or exceeds the 28 day specified strength. Capping Methods U: Unbonded Caps (ASTM C1231) Set #: 110 Specimen Size: 4" X 8" Specimens In Set: 6 Truck / Ticket #: 509 / 49098737 Contractor: GBC Concrete Technician: Kozlowski, John Cast By: Kozlowski, John Date Cast: 11/19/16 Sampled From: End of Pump Placement Method: Pump Sample Details Batched: 08:11 MST Sampled: 08:55 MST Cast: 09:10 MST Truck Empty: 09:30 MST Placement Time: 79 (min) Placement Location: Slab on Grade - Interior Location Details: Building 8 Sample Location / Notes: Lines B.2-4.1 Batch Log Strength: 4000 (psi) Air: 0.0 - 4.0 (%) Slump: 4 - 7 (in) Specifications Supplier: Martin Marietta Materials Specimen Number Test Age Days Test Date Field / Lab Cure Days Average Cylinder Diameter (in) Cylinder Area (in²) Max Load (lbs) Strength (psi) Fracture Type Break Remark Capping Method 111-1 3 11/22/16 3 / 0 4.01 12.63 33,650 2,660 3 A2 U 111-2 9 11/28/16 2 / 7 4.01 12.63 63,210 5,010 2 A1 U 111-3 30 12/19/16 2 / 28 4.01 12.63 75,250 5,960 3 B1 U 111-4 30 12/19/16 2 / 28 4.00 12.57 76,810 6,110 2 B1 U 111-5 30 12/19/16 2 / 28 4.02 12.69 73,310 5,780 3 B1 U 111-6 30 H 12/19/16 2 / 28 Test Age Average Strengths (psi): 3 Day - 2660, 9 Day - 5010, 30 Day - 5950 Break Remarks A2: Test result is less than 75% of the 28 day specified strength. A1: Test result meets or exceeds 75% of the 28 day specified strength. B1: Test result meets or exceeds the 28 day specified strength. Capping Methods U: Unbonded Caps (ASTM C1231) Set #: 111 Specimen Size: 4" X 8" Specimens In Set: 6 Truck / Ticket #: 1408 / 49098748 Contractor: GBC Concrete Technician: Kozlowski, John Cast By: Kozlowski, John Date Cast: 11/19/16 Sampled From: End of Pump Placement Method: Pump Sample Details Batched: 09:05 MST Sampled: 09:50 MST Cast: 10:05 MST Truck Empty: 10:10 MST Placement Time: 65 (min) Placement Location: Slab on Grade - Interior Location Details: Building 8 Sample Location / Notes: Lines B.1-2.2 Batch Log Strength: 4000 (psi) Air: 0.0 - 4.0 (%) Slump: 4 - 7 (in) Specifications Supplier: Martin Marietta Materials Specimen Number Test Age Days Test Date Field / Lab Cure Days Average Cylinder Diameter (in) Cylinder Area (in²) Max Load (lbs) Strength (psi) Fracture Type Break Remark Capping Method 112-1 3 11/22/16 3 / 0 4.01 12.63 33,100 2,620 2 A2 U 112-2 9 11/28/16 2 / 7 4.01 12.63 59,290 4,690 2 A1 U 112-3 30 12/19/16 2 / 28 4.00 12.57 75,240 5,990 2 B1 U 112-4 30 12/19/16 2 / 28 4.01 12.63 71,000 5,620 2 B1 U 112-5 30 12/19/16 2 / 28 4.02 12.69 74,840 5,900 3 B1 U 112-6 30 H 12/19/16 2 / 28 Test Age Average Strengths (psi): 3 Day - 2620, 9 Day - 4690, 30 Day - 5840 Break Remarks A2: Test result is less than 75% of the 28 day specified strength. A1: Test result meets or exceeds 75% of the 28 day specified strength. B1: Test result meets or exceeds the 28 day specified strength. Capping Methods U: Unbonded Caps (ASTM C1231) Set #: 112 Specimen Size: 4" X 8" Specimens In Set: 6 Truck / Ticket #: 510 / 49098748 Contractor: GBC Concrete Technician: Kozlowski, John Cast By: Kozlowski, John Date Cast: 11/19/16 Sampled From: Truck Chute Placement Method: Pump Sample Details Batched: 10:15 MST Sampled: 10:50 MST Cast: 11:05 MST Truck Empty: 11:05 MST Placement Time: 50 (min) Placement Location: Slab on Grade - Interior Location Details: Building 8 Sample Location / Notes: Lines A.2-2.1 Batch Log Strength: 4000 (psi) Air: 0.0 - 4.0 (%) Slump: 4 - 7 (in) Specifications Supplier: Martin Marietta Materials Specimen Number Test Age Days Test Date Field / Lab Cure Days Average Cylinder Diameter (in) Cylinder Area (in²) Max Load (lbs) Strength (psi) Fracture Type Break Remark Capping Method 113-1 3 11/22/16 3 / 0 4.01 12.63 32,880 2,600 2 A2 U 113-2 9 11/28/16 2 / 7 4.01 12.63 56,690 4,490 2 A1 U 113-3 30 12/19/16 2 / 28 4.01 12.63 70,740 5,600 2 B1 U 113-4 30 12/19/16 2 / 28 4.01 12.63 68,060 5,390 2 B1 U 113-5 30 12/19/16 2 / 28 4.02 12.69 73,210 5,770 2 B1 U 113-6 30 H 12/19/16 2 / 28 Test Age Average Strengths (psi): 3 Day - 2600, 9 Day - 4490, 30 Day - 5590 Break Remarks A2: Test result is less than 75% of the 28 day specified strength. A1: Test result meets or exceeds 75% of the 28 day specified strength. B1: Test result meets or exceeds the 28 day specified strength. Capping Methods U: Unbonded Caps (ASTM C1231) Set #: 113 Specimen Size: 4" X 8" Specimens In Set: 6 Truck / Ticket #: 1507 / 49098774 Contractor: GBC Concrete Technician: Kozlowski, John Cast By: Kozlowski, John Date Cast: 11/19/16 Sampled From: Truck Chute Placement Method: Pump Sample Details Batched: 11:15 MST Sampled: 12:00 MST Cast: 12:15 MST Truck Empty: 12:30 MST Placement Time: 75 (min) Placement Location: Slab on Grade - Interior Location Details: Building 8 Sample Location / Notes: Lines B.4-2 Batch Log Strength: 4000 (psi) Air: 0.0 - 4.0 (%) Slump: 4 - 7 (in) Specifications Supplier: Martin Marietta Materials Specimen Number Test Age Days Test Date Field / Lab Cure Days Average Cylinder Diameter (in) Cylinder Area (in²) Max Load (lbs) Strength (psi) Fracture Type Break Remark Capping Method 114-1 3 11/22/16 3 / 0 4.01 12.63 31,630 2,500 2 A2 U 114-2 9 11/28/16 2 / 7 4.01 12.63 54,010 4,280 2 A1 U 114-3 30 12/19/16 2 / 28 4.01 12.63 69,940 5,540 2 B1 U 114-4 30 12/19/16 2 / 28 4.02 12.69 71,270 5,620 3 B1 U 114-5 30 12/19/16 2 / 28 4.01 12.63 71,100 5,630 2 B1 U 114-6 30 H 12/19/16 2 / 28 Test Age Average Strengths (psi): 3 Day - 2500, 9 Day - 4280, 30 Day - 5590 Break Remarks A2: Test result is less than 75% of the 28 day specified strength. A1: Test result meets or exceeds 75% of the 28 day specified strength. B1: Test result meets or exceeds the 28 day specified strength. Capping Methods U: Unbonded Caps (ASTM C1231) Set #: 114 Specimen Size: 4" X 8" Specimens In Set: 6 Truck / Ticket #: 306 / 49098783 Contractor: GBC Concrete Technician: Kozlowski, John Cast By: Kozlowski, John Date Cast: 11/19/16 Sampled From: End of Pump Placement Method: Pump Sample Details Batched: 12:28 MST Sampled: 13:05 MST Cast: 13:20 MST Truck Empty: 13:30 MST Placement Time: 62 (min) Placement Location: Slab on Grade - Interior Location Details: Building 8 Sample Location / Notes: Lines A.2-1.2 Batch Log Strength: 4000 (psi) Air: 0.0 - 4.0 (%) Slump: 4 - 7 (in) Specifications Supplier: Martin Marietta Materials M1 M2 3.0000 2.7500 2.8750 8.5000 0.8750 X 8.8750 0.5000 X 8.5000 1.0000 X 8.7500 0.7500 X 8.6250 1.1250 X 8.3750 1.0000 X 8.1250 1.3750 X 8.7500 1.1250 X 8.0000 1.6250 X 8.5000 1.2500 X 8.7500 0.6250 X 8.6250 1.0000 X 8.7500 0.8750 X 8.6250 1.0000 X 9.0000 0.3750 X 8.7500 0.6250 X 8.5000 0.8750 X 8.8750 1.0000 X 8.0000 1.7500 X 8.1250 1.1250 X 7.8750 1.3750 X 8.6250 0.8750 X 8.3750 1.1250 X 8.5000 0.8750 X 8.3750 1.1250 X 7.8750 1.5000 X 3.3750 Technican: Jordan Sheppard Date: 12/1/2016 Location: Building 8 Post Tension Observation Report Re-Stress Double Pull % Elongation 3 5600 3.0000 0 100.00% Tendon No. Tendon Mark Design Elongation Jack Pressure Total Elongation Elongation Difference Measured Elongation PT8-2 19 20 21 22 23 PT8-11 PT8-12 PT8-13 PT8-14 PT8-15 M1 M2 Technican: Jordan Sheppard Date: 12/1/2016 Location: Building 8 Post Tension Observation Report Re-Stress Double Pull % Elongation 3 5600 3.0000 0 100.00% Tendon No. Tendon Mark Design Elongation Jack Pressure Total Elongation Elongation Difference Measured Elongation 1 PT8-1 3.3750 3.5000 2.0000 2.0000 1.6250 1.5000 2.2500 2.3750 5.1250 5.1250 5.2500 5.0000 5.0000 5.1250 5.0000 5.1250 5.0000 5.1250 5.0000 5.0000 5.1250 5.1250 5.0000 5.0000 5.0000 5.0000 4.7500 4.7500 50 51 52 53 42 43 44 45 46 47 36 37 48 M1 M2 Technican: Jordan Sheppard Date: 12/1/2016 Location: Building 8 Post Tension Observation Report Re-Stress Double Pull % Elongation 3 5600 3.0000 0 100.00% Tendon No. Tendon Mark Design Elongation Jack Pressure Total Elongation Elongation Difference Measured Elongation 1 PT8-1 4.8750 4.6250 4.5000 4.7500 4.5000 4.6250 4.6250 4.7500 4.6250 4.6250 4.7500 4.6250 4.7500 4.8750 4.6250 4.5000 4.7500 4.5000 4.5000 4.6250 4.5000 4.6250 4.8750 4.8750 5.0000 4.8750 4.8750 5.0000 5.0000 4.8750 66 67 68 69 70 71 61 62 63 64 65 M1 M2 Technican: Jordan Sheppard Date: 12/1/2016 Location: Building 8 Post Tension Observation Report Re-Stress Double Pull % Elongation 3 5600 3.0000 0 100.00% Tendon No. Tendon Mark Design Elongation Jack Pressure Total Elongation Elongation Difference Measured Elongation 1 PT8-1 4.8750 5.0000 2.8750 3.0000 7.6250 7.2500 3.5000 3.7500 6.2500 6.5000 1.7500 1.8750 6.8750 7.0000 2.6250 2.5000 4.7500 5.0000 0 0.25 100.00% 96.49% 110 111 112 113 5.0000 102 103 104 105 106 107 96 97 98 99 100 101 91 92 M1 M2 3.0000 2.7500 2.8750 8.5000 0.8750 X 8.8750 0.5000 X 8.5000 1.0000 X 8.7500 0.7500 X 8.6250 1.1250 X 8.3750 1.0000 X 8.1250 1.3750 X 8.7500 1.1250 X 8.0000 1.6250 X 8.5000 1.2500 X 8.7500 0.6250 X 8.6250 1.0000 X 8.7500 0.8750 X 8.6250 1.0000 X 9.0000 0.3750 X 8.7500 0.6250 X 8.5000 0.8750 X 8.8750 1.0000 X 8.0000 1.7500 X 8.1250 1.1250 X 7.8750 1.3750 X 8.6250 0.8750 X 8.3750 1.1250 X 8.5000 0.8750 X 8.3750 1.1250 X 7.8750 1.5000 X 3.3750 Technican: Jordan Sheppard Date: 12/22/2016 Location: Building 8 Post Tension Observation Report Re-Stress Double Pull % Elongation 3 5600 3.0000 0 100.00% Tendon No. Tendon Mark Design Elongation Jack Pressure Total Elongation Elongation Difference Measured Elongation PT8-2 19 20 21 22 23 PT8-11 PT8-12 PT8-13 PT8-14 PT8-15 M1 M2 Technican: Jordan Sheppard Date: 12/22/2016 Location: Building 8 Post Tension Observation Report Re-Stress Double Pull % Elongation 3 5600 3.0000 0 100.00% Tendon No. Tendon Mark Design Elongation Jack Pressure Total Elongation Elongation Difference Measured Elongation 1 PT8-1 3.3750 3.5000 2.0000 2.0000 1.6250 1.5000 2.2500 2.3750 5.0000 5.1250 5.1250 5.1250 5.2500 5.0000 5.0000 5.1250 5.0000 5.1250 5.0000 5.1250 5.0000 5.0000 5.1250 5.1250 5.0000 5.0000 5.0000 5.0000 4.7500 4.7500 50 51 52 53 42 43 44 45 46 47 36 M1 M2 Technican: Jordan Sheppard Date: 12/22/2016 Location: Building 8 Post Tension Observation Report Re-Stress Double Pull % Elongation 3 5600 3.0000 0 100.00% Tendon No. Tendon Mark Design Elongation Jack Pressure Total Elongation Elongation Difference Measured Elongation 1 PT8-1 4.8750 4.6250 4.5000 4.7500 4.5000 4.6250 4.6250 4.7500 4.6250 4.6250 4.7500 4.6250 4.7500 4.8750 4.6250 4.5000 4.7500 4.5000 4.5000 4.6250 4.5000 4.6250 4.8750 4.8750 5.0000 4.8750 4.8750 5.0000 5.0000 4.8750 66 67 68 69 70 71 61 62 63 64 65 M1 M2 Technican: Jordan Sheppard Date: 12/22/2016 Location: Building 8 Post Tension Observation Report Re-Stress Double Pull % Elongation 3 5600 3.0000 0 100.00% Tendon No. Tendon Mark Design Elongation Jack Pressure Total Elongation Elongation Difference Measured Elongation 1 PT8-1 4.8750 5.0000 2.8750 3.0000 7.6250 7.2500 3.5000 3.7500 6.2500 6.5000 1.7500 1.8750 6.8750 7.0000 2.6250 2.5000 5.1250 5.0000 4.7500 5.0000 0 0.25 100.00% 96.49% 110 111 112 113 5.0000 102 103 104 105 106 107 96 97 98 99 100 101 General Information Project Phase: Inspection and Testing Technician: Sheppard, Jordan Temperature (°F): 64 Date: 10/21/2016 Weather: Sunny Work Completed Inspection Item: Location Details: Utility Trench Backfill Building 8; Line B, 2-3 Tests Performed: Frequency: Field Density Tests Periodic Work Completed Description: OlssonAssociates arrived on-site to observe placement of utility trench backfill within interior plumbing along the referenced location. Field Density Tests were performed to evaluate the moisture content and in-place dry density of placed utility trench backfill. The results of the field density tests indicated that the backfill placed along the referenced location had met moisture specifications and compaction specifications later out by the projects geotechnical report. On-site utility contractor was notified of these observations and test results. Determination As Specified Special Inspection Daily Report Report #: SI3-000146 Report Date: 10/25/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 1 of 2 Image Description Compaction of utility trench backfill; Building 8 Special Inspection Daily Report Report #: SI3-000146 Report Date: 10/25/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 2 of 2 General Information Project Phase: Additional Services Technician: Goetz, Steve Temperature (°F): 70 Date: 11/03/2016 Weather: Sunny Start Time:13:30 End Time:14:30 Work Completed Inspection Item: Location Details: Foundation Bearing Materials Lot 3 Building 8 Tests Performed: Frequency: None Periodic Work Completed Description: Olsson Associates arrived on-site to perform observations of the foundation bearing conditions for building 8. Olsson observed that the bearing conditions on line 5 between A and C of building 8 appeared to be free of any deleterious materials and bared on native brown soils. Olsson however did observe trace amounts of deleterious materials throughout the side walls during excavations. Due to the findings of asphalt Olsson notified the contractor and site superintendent John w/ Weitz that hand auger test pits would need to be performed upon Olsson's arrival on 11/4/16. The site superintendent was notified of these observations. Determination As Specified Special Inspection Daily Report Report #: SI3-000206 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 1 of 2 Image Description Footing excavation bldg. 8 Special Inspection Daily Report Report #: SI3-000206 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 2 of 2 General Information Project Phase: Additional Services Technician: Sheppard, Jordan Temperature (°F): 61 Date: 11/04/2016 Weather: Sunn Start Time:08:00 End Time:12:00 Work Completed Inspection Item: Location Details: Foundation Bearing Materials Building 8; Lines 1-5 Tests Performed: Frequency: Hand Auger Periodic Work Completed Description: Olsson Associates arrived on site to observe underlying material within the Building 8 along proposed thickened slab section within the referenced location. Four test holes were hand augered along the referenced line to a depth of approximately 32" to evaluate the underlying material. Olsson encountered structural fill on top of a apparently native soil placed up to a depth of 32". These test results and observations were shared with the on-site superintendent for Weitz and the on-site concrete foreman for GBC Concrete. Determination As Specified Special Inspection Daily Report Report #: SI3-000205 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 1 of 3 Image Description Test Hole; Building 8 Special Inspection Daily Report Report #: SI3-000205 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 2 of 3 Image Description Line B, Building 8 Special Inspection Daily Report Report #: SI3-000205 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 3 of 3 General Information Project Phase: Inspection and Testing Technician: Sheppard, Jordan Temperature (°F): 62 Date: 11/04/2016 Weather: Sunny Work Completed Inspection Item: Location Details: Structural Fill Building 8; Lines A-C, 1-5 Tests Performed: Frequency: Field Density Tests Periodic Work Completed Description: Olsson Associates arrived on-site to observe placement of structural fill within the referenced location. Field Density tests were performed to evaluate the moisture content and in-place dry density of placed structural fill. The results of the field density tests indicated that the structural fill placed along the referenced location had met moisture and compaction specifications layed out by the projects geotechnical report. On-site Concrete contractors for GBC Concrete and on-site superintendent for Weitz were notified of these observations and test results. Determination As Specified Special Inspection Daily Report Report #: SI3-000215 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 1 of 2 Image Description Building 8 Special Inspection Daily Report Report #: SI3-000215 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 2 of 2 General Information Project Phase: Inspection and Testing Technician: Kozlowski, John Temperature (°F): 65 Date: 11/07/2016 Weather: Sunny Start Time:14:30 End Time:15:10 Work Completed Inspection Item: Location Details: Reinforcing Steel Building 8 - Foundation Tests Performed: Frequency: None Periodic Work Completed Description: Olsson Associates arrived on-site to observe the placement reinforcing steel and post tensioned tendons for the shallow foundations in Building 8. The size, spacing and orientation of the reinforcing steel and tendons were observed and appeared to be consistent with the project's structural plans. The on-site superintendent was notified of these observations. Determination As Specified Special Inspection Daily Report Report #: SI3-000228 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 1 of 3 Image Description Building Eight, Footer, Reinforcing Steel, Lot Three Special Inspection Daily Report Report #: SI3-000228 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 2 of 3 Image Description Lot Three, Building Eight, Reinforcing Steel, Footer Special Inspection Daily Report Report #: SI3-000228 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 3 of 3 General Information Project Phase: Inspection and Testing Technician: Sheppard, Jordan Temperature (°F): 59 Date: 11/08/2016 Weather: Sunny Work Completed Inspection Item: Location Details: Footing Building 8; Lines A-C,1-5 Tests Performed: Frequency: ASTM C143, C231, C1064, C31 Periodic Work Completed Description: Olsson Associates arrived on-site to observe placement of concrete into the referenced footing. Olsson observed consolidation of placed concrete around reinforcement with use of vibrator. Olsson sampled concrete with accordance to ASTM C172. The sampled concrete was then tested with accordance to ASTM C143, C231, and C1064. The sampled concrete had conformed to project specifications for slump and entrained air. Five 4"x8" concrete cylinder specimens were prepared with accordance to ASTM C31 per sample and stored in cooler on-site. On-site Superintendent for Weitz and on-site foreman for GBC Concrete were notified of these observations and test results. Determination As Specified Special Inspection Daily Report Report #: SI3-000227 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 1 of 2 Image Description Placement of Concrete; Building 8 footing Special Inspection Daily Report Report #: SI3-000227 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 2 of 2 General Information Project Phase: Inspection and Testing Technician: Sheppard, Jordan Temperature (°F): 61 Date: 11/16/2016 Weather: Sunny Start Time:07:30 End Time:09:30 Work Completed Inspection Item: Location Details: Reinforcing Steel Building 8 Post-Tensioned Slab Tests Performed: Frequency: None Periodic Work Completed Description: Olsson Associates arrived on-site to observe placement of reinforcing steel and post-tension cables within the referenced location. Olsson observed horizontal reinforcement, spacing, lap splice lengths, clear space distances, as well as post-tension cable placement and spacing. The observations made showed that the steel reinforcement as well as post-tension cable placement had appeared to conform to project structural plans and post-tension cable shop drawings. On-site concrete foreman for GBC Concrete and on-site superintendent for Weitz were notified of these observations. Determination As Specified Special Inspection Daily Report Report #: SI3-000222 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 1 of 4 Image Description Reinforcing steel; Building 8 Special Inspection Daily Report Report #: SI3-000222 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 2 of 4 Image Description Reinforcing steel; Building 8 Special Inspection Daily Report Report #: SI3-000222 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 3 of 4 Image Description Post tension cables; Building 8 Special Inspection Daily Report Report #: SI3-000222 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 4 of 4 General Information Project Phase: Inspection and Testing Technician: Kozlowski, John Temperature (°F): 45 Date: 11/19/2016 Weather: Sunny Start Time:07:30 End Time:14:00 Work Completed Inspection Item: Location Details: Post-Tensioned Slab Building 8 Tests Performed: Frequency: Concrete Testing Continuous Work Completed Description: Olsson Associates arrived on-site to observe and perform testing on the interior slab for building 8. Olsson observed the placement of the concrete done with a pump for the grid lines 1-5 and A-C. Olsson performed several sets of field test and test specimens were cast from the concrete placed. The on-site contractor was notified of these observations and test results. Determination As Specified Special Inspection Daily Report Report #: SI3-000199 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 1 of 4 Image Description Building 8, Slab on grade, Southwest Special Inspection Daily Report Report #: SI3-000199 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 2 of 4 Image Description Building 8, Slab on grade, North East Special Inspection Daily Report Report #: SI3-000199 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 3 of 4 Image Description Building 8, Slab on grade, South East Special Inspection Daily Report Report #: SI3-000199 Report Date: 11/23/2016 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: McWhinney Real Estate Services, Inc. 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 4 of 4 General Information Project Phase: Inspection and Testing Technician: Sheppard, Jordan Temperature (°F): 43 Date: 12/01/2016 Weather: Sunny Start Time:11:00 End Time:13:30 Work Completed Inspection Item: Location Details: Post-Tensioned Slab Building 8 Tests Performed: Frequency: None Continuous Work Completed Description: Olsson Associates arrived on-site to observe post-tensioning of tendons within post-tension slab along the referenced location. Upon arrival Olsson observed marking of tendons for measurement datum using a 6" wood block. Olsson observed the use of an hydraulic pressure jack to pull tendons to 100% of design elongation. Olsson notes that tendons PT8-39, PT8-40, PT8GB-15 and PT8GB-16 were not pulled due to excessive honeycombing and recommended that voids be patched prior to stressings. Olsson will provide a completed post-tension observation report to the client at a later date once all tendons have been stressed. On-site concrete foreman for GBC Concrete and on-site superintendent for Weitz were notified of these observations. Determination Discrepancy Noted Discrepancy Description: Olsson observed four (4) tendons in the Building 08 post-tensioned slab that had excessive honeycombing in the concrete at the stressing ends. Per recommendations from Monroe & Newell, the concrete in these locations should be grouted or patched and re-observed by Olsson prior to stressing. Status: Closed Resolution Date: Resolution Technician: 12/22/2016 Sheppard, Jordan Resolution Description: The four (4) tendons in Building 08 post-tensioned slab were repaired and stressed. The PT EOR reviewed and accepted the measured elongations. Special Inspection Daily Report Report #: SI3-000293 Report Date: 3/6/2017 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: FMFPE, LLC 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 1 of 4 Image Description Marking of tendons; Building 8 Special Inspection Daily Report Report #: SI3-000293 Report Date: 3/6/2017 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: FMFPE, LLC 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 2 of 4 Image Description Stressing of tendons; Building 8 Special Inspection Daily Report Report #: SI3-000293 Report Date: 3/6/2017 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: FMFPE, LLC 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 3 of 4 Image Description Honeycombing around tendons; Building 8 Special Inspection Daily Report Report #: SI3-000293 Report Date: 3/6/2017 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: FMFPE, LLC 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 4 of 4 General Information Project Phase: Inspection and Testing Technician: Sheppard, Jordan Temperature (°F): 29 Date: 12/22/2016 Weather: Cloudy Start Time:09:30 End Time:11:00 Work Completed Inspection Item: Location Details: Post-Tensioned Slab Building 8 Tests Performed: Frequency: None Continuous Work Completed Description: Olsson Associates arrived on-site to observe post-tensioning of previously in-stressed tendons within post-tension slab along the referenced location. Upon arrival Olsson observed that honeycombing around previously un-stressed tendons had been patched. Olsson observed the use of an hydraulic pressure jack to pull tendons to 100% of design elongation. Tendons PT8-39, PT8-40, PT8GB-15 and PT8GB-16 were Pulled. Olsson will provide a completed post-tension observation report to the client at a later. On-site concrete foreman for GBC Concrete and on-site superintendent for Weitz were notified of these observations. Determination As Specified Special Inspection Daily Report Report #: SI3-000281 Report Date: 2/1/2017 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: FMFPE, LLC 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 1 of 2 Image Description Patched Voids around tendons; Building 8 Special Inspection Daily Report Report #: SI3-000281 Report Date: 2/1/2017 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Client: FMFPE, LLC 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016-1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 2 of 2 General Information Project Phase: Inspection and Testing Technician: Goetz, Steve Temperature (°F): 50 Date: 11/15/2017 Weather: Partly Cloudy Arrival Time: 11:30 Departure Time: 14:15 Work Completed Inspection Item: Location Details: Shear Walls ATS Hold downs; Building 8 Tests Performed: Frequency: None Periodic Work Completed Description: Olsson Associates arrived on­site to perform observations of the ATS shear wall hold downs systems. Olsson met with Trevor the sub­contractor and walked all three buildings to verify that hardware was installed as per plan. Upon observations of building 8 there were several sections that were not completed, Olsson informed the contractor and Weitz that these sections should be completed and then re­scheduled for re­inspections. Determination Discrepancy Noted Description: Building 8 had hardware missing hardware for the (3) T1.4 rods, two on Grid C, 3 and one on Grid B.5, 5. Olsson also was unable to view T3.7 rods at Grid C.2, 2.2 and C.2, 3.8 as these were covered by sheeting and will need to be exposed for visual observations. Olsson should be notified of when these have been fixed for re­inspection. Status: Closed Resolution Date: Resolution Technician: 11/27/2017 Shaffer, Austin Resolution Description: Olsson verified all the missing hardware was in place and was able to visual reinspect all the referenced hold downs. Special Inspection Daily Report Report #: SIR­000376 Report Date: 1/2/2018 Denver 3990 Fox Street Denver, CO 80216 Phone: 303­237­2072 Fax: 303­237­2659 Client: FMFPE, LLC 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016­1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 1 of 2 1 General Information Project Phase: Additional Services Technician: Shaffer, Austin Temperature (°F): 46 Date: 12/27/2017 Weather: Sunny Arrival Time: 14:00 Departure Time: 15:00 Work Completed Inspection Item: Location Details: Shear Walls ATS Hold downs; Building 8 Tests Performed: Frequency: None Periodic Work Completed Description: Olsson Associates arrived on­site to perform re­inspection on the ATS shear wall for referenced building. Olsson was able to visually inspect all referenced hold downs and verify all previously missing hardware was in place. The on­site framing foreman was notified of these observations. Determination As Specified Special Inspection Daily Report Report #: SIR­000377 Report Date: 1/2/2018 Denver 3990 Fox Street Denver, CO 80216 Phone: 303­237­2072 Fax: 303­237­2659 Client: FMFPE, LLC 2725 Rocky Mountain Ave Ste 200 Loveland, CO 80538 Project: 016­1668 McWhinney Foothills Mall Multifamily Fort Collins, CO Page 1 of 2 1 91 92 93 94 95 108 109 118 119 120 117 114 115 116 PT8GB-9 PT8GB-12 PT8GB-13 PT8GB-14 PT8GB-3 PT8GB-4 PT8GB-5 PT8GB-6 PT8GB-7 PT8GB-8 PT8-91 PT8-92 PT8GB-1 PT8GB-2 PT8GB-10 PT8GB-11 PT8GB-18 PT8GB-15 PT8GB-16 PT8GB-17 6 3/8 1 7/8 7 1/8 2 1/2 3 8 1/4 8 1/4 3 3/4 3 3/4 6 3/8 5 1/8 5 1/8 3 1 7/8 7 1/8 5 2 1/2 5 3/8 5 3/8 5 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 3.7500 6.2500 6.5000 1.7500 5.0000 2.8750 3.0000 7.6250 7.2500 3.5000 4.8750 1.8750 6.8750 7.0000 2.6250 2.5000 5.1250 5.0000 4.7500 0.25 0 0.125 0.125 0.125 0.25 0.125 0.125 0 0.625 1 0.25 0.125 0.125 0 0.25 0.375 0 97.56% 95.83% 100.00% 92.42% 87.88% 93.33% 95.12% 98.25% 105.00% 100.00% 95.35% 93.02% 95.00% 100.00% 98.04% 101.96% 93.33% 100.00% 84 85 86 87 88 89 78 79 80 81 82 83 72 73 74 75 76 77 90 PT8-65 PT8-66 PT8-67 PT8-68 PT8-69 PT8-70 PT8-61 PT8-62 PT8-63 PT8-64 PT8-83 PT8-84 PT8-85 PT8-86 PT8-87 PT8-88 PT8-77 PT8-78 PT8-79 PT8-80 PT8-81 PT8-82 PT8-71 PT8-72 PT8-73 PT8-74 PT8-75 PT8-76 PT8-89 PT8-90 4 3/4 4 3/4 4 3/4 4 3/4 4 3/4 4 3/4 4 5/8 4 5/8 4 5/8 4 3/4 5 1/8 5 1/8 5 1/8 5 1/8 5 1/8 4 5/8 4 5/8 4 5/8 4 5/8 4 3/4 4 3/4 4 3/4 4 3/4 4 3/4 4 3/4 4 3/4 4 5/8 5 1/8 5 1/8 5 1/8 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 4.6250 4.5000 4.7500 4.5000 4.6250 4.6250 4.8750 4.6250 4.5000 4.6250 4.8750 4.8750 5.0000 4.8750 4.6250 4.5000 4.7500 4.5000 4.5000 4.7500 4.6250 4.6250 4.7500 4.6250 4.7500 4.8750 4.8750 5.0000 5.0000 4.8750 0.25 0 0.125 0 0.25 0.125 0.125 0.125 0.25 0.125 0.25 0.25 0 0.125 0 0.125 0.125 0.125 0.125 0 0.125 0.125 0 0.125 0.125 0.25 0.25 0.125 0.125 0.25 105.41% 102.63% 100.00% 97.30% 102.70% 97.30% 97.30% 100.00% 97.37% 97.37% 100.00% 97.37% 100.00% 100.00% 97.30% 100.00% 94.74% 97.37% 97.37% 95.12% 95.12% 97.56% 97.56% 95.12% 97.37% 94.74% 97.37% 95.12% 95.12% 97.56% 37 48 49 31 32 33 34 35 38 39 40 41 60 54 55 56 57 58 59 PT8-31 PT8-32 PT8-33 PT8-34 PT8-47 PT8-48 PT8-49 PT8-50 PT8-51 PT8-52 PT8-41 PT8-42 PT8-43 PT8-44 PT8-45 PT8-46 PT8-35 PT8-36 PT8-37 PT8-38 PT8-39 PT8-40 PT8-59 PT8-60 PT8-53 PT8-54 PT8-55 PT8-56 PT8-57 PT8-58 3 1/2 3 1/2 2 5 1/4 5 1/4 5 1/4 5 1/4 5 1/4 5 1/4 5 1/4 5 1/4 5 1/4 5 1/4 5 1/4 5 1/4 2 1 5/8 1 5/8 2 3/8 2 3/8 5 1/4 5 1/8 4 5/8 4 5/8 5 1/4 5 1/4 5 1/4 5 1/8 5 1/8 5 1/8 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 3.3750 5.0000 5.0000 5.1250 5.0000 5.1250 5.0000 2.3750 5.0000 5.1250 5.1250 5.1250 5.2500 3.5000 2.0000 2.0000 1.6250 1.5000 2.2500 5.0000 5.0000 5.0000 4.7500 4.7500 5.1250 5.0000 5.0000 5.1250 5.1250 5.0000 0 0.25 0.25 0.125 0.25 0.125 0.125 0 0.25 0.125 0.125 0.125 0.125 0 0 0 0 0.125 0.125 0.125 0.125 0.125 0.125 0.125 0.25 0.125 0.25 0.25 0.125 0.125 100.00% 95.24% 97.62% 97.62% 97.62% 100.00% 100.00% 100.00% 100.00% 100.00% 92.31% 94.74% 96.43% 97.56% 97.56% 97.56% 102.70% 102.70% 97.62% 95.24% 95.24% 97.62% 97.62% 97.56% 95.24% 95.24% 97.62% 95.24% 97.62% 95.24% PT8-16 28 29 18 PT8-3 12 13 14 15 16 17 6 7 8 9 10 11 1 PT8-1 2 3 4 5 30 24 25 26 27 PT8-4 PT8-5 PT8-6 PT8-7 PT8-8 PT8-9 PT8-10 PT8-29 PT8-30 PT8-23 PT8-24 PT8-25 PT8-26 PT8-27 PT8-28 PT8-17 PT8-18 PT8-19 PT8-20 PT8-21 PT8-22 9 3/4 9 3/4 9 3/4 9 3/4 9 3/4 9 3/4 3 3 9 3/4 9 3/4 9 3/4 9 3/4 9 3/4 9 3/4 9 5/8 9 5/8 3 1/2 9 5/8 9 5/8 9 5/8 9 5/8 9 5/8 9 5/8 9 3/4 9 5/8 9 5/8 9 5/8 9 5/8 9 5/8 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 9.7500 9.3750 9.5000 9.8750 9.6250 9.7500 2.8750 2.7500 9.3750 9.3750 9.5000 9.5000 9.5000 9.3750 9.5000 9.3750 3.3750 9.3750 9.8750 9.7500 9.2500 9.2500 9.5000 9.3750 9.6250 9.6250 9.6250 9.3750 9.3750 0.25 0 0.375 0.25 0.125 0.125 0.25 0.125 0.375 0.375 0.25 0.125 0.125 0.25 0.125 0.25 0.125 0.25 0.25 0.25 0.125 0.375 0.375 0 0.375 0.125 0.125 0 0.25 91.67% 95.83% 96.15% 96.15% 97.44% 97.44% 97.40% 102.60% 101.30% 96.10% 96.10% 98.70% 96.15% 98.72% 98.72% 100.00% 97.40% 97.40% 100.00% 96.15% 97.44% 101.28% 98.72% 100.00% 98.70% 97.40% 98.70% 97.40% 96.43% 93 94 95 108 109 118 119 120 117 114 115 116 PT8GB-9 PT8GB-12 PT8GB-13 PT8GB-14 PT8GB-3 PT8GB-4 PT8GB-5 PT8GB-6 PT8GB-7 PT8GB-8 PT8-91 PT8-92 PT8GB-1 PT8GB-2 PT8GB-10 PT8GB-11 PT8GB-18 PT8GB-15 PT8GB-16 PT8GB-17 6 3/8 1 7/8 7 1/8 2 1/2 3 8 1/4 8 1/4 3 3/4 3 3/4 6 3/8 5 1/8 5 1/8 3 1 7/8 7 1/8 5 2 1/2 5 3/8 5 3/8 5 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 3.7500 6.2500 6.5000 1.7500 5.0000 2.8750 3.0000 7.6250 7.2500 3.5000 4.8750 1.8750 6.8750 7.0000 2.6250 2.5000 4.7500 0.25 0 0.125 0.125 0.125 0.25 0.125 0.125 0 0.625 1 0.25 0.125 0.125 0 0 97.56% 95.83% 100.00% 92.42% 87.88% 93.33% 95.12% 98.25% 105.00% 100.00% 95.00% 100.00% 98.04% 101.96% 93.33% 100.00% 84 85 86 87 88 89 78 79 80 81 82 83 72 73 74 75 76 77 90 PT8-65 PT8-66 PT8-67 PT8-68 PT8-69 PT8-70 PT8-61 PT8-62 PT8-63 PT8-64 PT8-83 PT8-84 PT8-85 PT8-86 PT8-87 PT8-88 PT8-77 PT8-78 PT8-79 PT8-80 PT8-81 PT8-82 PT8-71 PT8-72 PT8-73 PT8-74 PT8-75 PT8-76 PT8-89 PT8-90 4 3/4 4 3/4 4 3/4 4 3/4 4 3/4 4 3/4 4 5/8 4 5/8 4 5/8 4 3/4 5 1/8 5 1/8 5 1/8 5 1/8 5 1/8 4 5/8 4 5/8 4 5/8 4 5/8 4 3/4 4 3/4 4 3/4 4 3/4 4 3/4 4 3/4 4 3/4 4 5/8 5 1/8 5 1/8 5 1/8 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 4.6250 4.5000 4.7500 4.5000 4.6250 4.6250 4.8750 4.6250 4.5000 4.6250 4.8750 4.8750 5.0000 4.8750 4.6250 4.5000 4.7500 4.5000 4.5000 4.7500 4.6250 4.6250 4.7500 4.6250 4.7500 4.8750 4.8750 5.0000 5.0000 4.8750 0.25 0 0.125 0 0.25 0.125 0.125 0.125 0.25 0.125 0.25 0.25 0 0.125 0 0.125 0.125 0.125 0.125 0 0.125 0.125 0 0.125 0.125 0.25 0.25 0.125 0.125 0.25 105.41% 102.63% 100.00% 97.30% 102.70% 97.30% 97.30% 100.00% 97.37% 97.37% 100.00% 97.37% 100.00% 100.00% 97.30% 100.00% 94.74% 97.37% 97.37% 95.12% 95.12% 97.56% 97.56% 95.12% 97.37% 94.74% 97.37% 95.12% 95.12% 97.56% 49 31 32 33 34 35 38 39 40 41 60 54 55 56 57 58 59 PT8-31 PT8-32 PT8-33 PT8-34 PT8-47 PT8-48 PT8-49 PT8-50 PT8-51 PT8-52 PT8-41 PT8-42 PT8-43 PT8-44 PT8-45 PT8-46 PT8-35 PT8-36 PT8-37 PT8-38 PT8-39 PT8-40 PT8-59 PT8-60 PT8-53 PT8-54 PT8-55 PT8-56 PT8-57 PT8-58 3 1/2 3 1/2 2 5 1/4 5 1/4 5 1/4 5 1/4 5 1/4 5 1/4 5 1/4 5 1/4 5 1/4 5 1/4 5 1/4 5 1/4 2 1 5/8 1 5/8 2 3/8 2 3/8 5 1/4 5 1/8 4 5/8 4 5/8 5 1/4 5 1/4 5 1/4 5 1/8 5 1/8 5 1/8 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 3.3750 5.0000 5.0000 5.1250 5.0000 5.1250 5.0000 2.3750 5.1250 5.1250 5.2500 3.5000 2.0000 2.0000 1.6250 1.5000 2.2500 5.0000 5.0000 5.0000 4.7500 4.7500 5.1250 5.0000 5.0000 5.1250 5.1250 5.0000 0 0.25 0.25 0.125 0.25 0.125 0.125 0 0.125 0.125 0.125 0 0 0 0 0.125 0.125 0.125 0.125 0.125 0.125 0.125 0.25 0.125 0.25 0.25 0.125 0.125 100.00% 97.62% 97.62% 100.00% 100.00% 100.00% 100.00% 100.00% 92.31% 94.74% 96.43% 97.56% 97.56% 97.56% 102.70% 102.70% 97.62% 95.24% 95.24% 97.62% 97.62% 97.56% 95.24% 95.24% 97.62% 95.24% 97.62% 95.24% PT8-16 28 29 18 PT8-3 12 13 14 15 16 17 6 7 8 9 10 11 1 PT8-1 2 3 4 5 30 24 25 26 27 PT8-4 PT8-5 PT8-6 PT8-7 PT8-8 PT8-9 PT8-10 PT8-29 PT8-30 PT8-23 PT8-24 PT8-25 PT8-26 PT8-27 PT8-28 PT8-17 PT8-18 PT8-19 PT8-20 PT8-21 PT8-22 9 3/4 9 3/4 9 3/4 9 3/4 9 3/4 9 3/4 3 3 9 3/4 9 3/4 9 3/4 9 3/4 9 3/4 9 3/4 9 5/8 9 5/8 3 1/2 9 5/8 9 5/8 9 5/8 9 5/8 9 5/8 9 5/8 9 3/4 9 5/8 9 5/8 9 5/8 9 5/8 9 5/8 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 9.7500 9.3750 9.5000 9.8750 9.6250 9.7500 2.8750 2.7500 9.3750 9.3750 9.5000 9.5000 9.5000 9.3750 9.5000 9.3750 3.3750 9.3750 9.8750 9.7500 9.2500 9.2500 9.5000 9.3750 9.6250 9.6250 9.6250 9.3750 9.3750 0.25 0 0.375 0.25 0.125 0.125 0.25 0.125 0.375 0.375 0.25 0.125 0.125 0.25 0.125 0.25 0.125 0.25 0.25 0.25 0.125 0.375 0.375 0 0.375 0.125 0.125 0 0.25 91.67% 95.83% 96.15% 96.15% 97.44% 97.44% 97.40% 102.60% 101.30% 96.10% 96.10% 98.70% 96.15% 98.72% 98.72% 100.00% 97.40% 97.40% 100.00% 96.15% 97.44% 101.28% 98.72% 100.00% 98.70% 97.40% 98.70% 97.40% 96.43% Plant: 751 Rioden Mix Design: N4513SP On-Site Admixtures: None Location Field Measurements Plastic Unit Weight: 148.6 (lb/ft³) (C138) Air Content: 1.5 (C231) Load Volume: 10 (yd³) Weather: Sunny Slump (in): 5-1/2 (C143) Air Temperature (F): 45 Concrete Temp (F): 65 (C1064) Lab Test Results Testing Lab: Denver, 3990 Fox Street, Denver, CO, 80216 Page 1 of 1 Client: FMFPE, LLC Loveland, CO 80538 2725 Rocky Mountain Ave Ste 200 Project: McWhinney Foothills Mall Multifamily 016-1668 Fort Collins, CO Compressive Strength of Concrete Test Method: ASTM C39; C31; C172 Sample: 24953 Report #: CC-000302 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Braden Hirsch Project Manager Plant: 751 Rioden Mix Design: N4513SP On-Site Admixtures: None Location Field Measurements Plastic Unit Weight: 149.2 (lb/ft³) (C138) Air Content: 1.7 (C231) Load Volume: 10 (yd³) Weather: Sunny Slump (in): 5-3/4 (C143) Air Temperature (F): 42 Concrete Temp (F): 65 (C1064) Lab Test Results Testing Lab: Denver, 3990 Fox Street, Denver, CO, 80216 Page 1 of 1 Client: FMFPE, LLC Loveland, CO 80538 2725 Rocky Mountain Ave Ste 200 Project: McWhinney Foothills Mall Multifamily 016-1668 Fort Collins, CO Compressive Strength of Concrete Test Method: ASTM C39; C31; C172 Sample: 24952 Report #: CC-000306 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Braden Hirsch Project Manager Plant: 751 Rioden Mix Design: N4513SP On-Site Admixtures: None Location Field Measurements Plastic Unit Weight: 148.1 (lb/ft³) (C138) Air Content: 1.7 (C231) Load Volume: 10 (yd³) Weather: Sunny Slump (in): 6-1/4 (C143) Air Temperature (F): 40 Concrete Temp (F): 64 (C1064) Lab Test Results Testing Lab: Denver, 3990 Fox Street, Denver, CO, 80216 Page 1 of 1 Client: FMFPE, LLC Loveland, CO 80538 2725 Rocky Mountain Ave Ste 200 Project: McWhinney Foothills Mall Multifamily 016-1668 Fort Collins, CO Compressive Strength of Concrete Test Method: ASTM C39; C31; C172 Sample: 24948 Report #: CC-000310 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Braden Hirsch Project Manager Plant: 751 Rioden Mix Design: N4513SP On-Site Admixtures: None Location Field Measurements Plastic Unit Weight: 148.6 (lb/ft³) (C138) Air Content: 2.0 (C231) Load Volume: 10 (yd³) Weather: Sunny Slump (in): 5-1/2 (C143) Air Temperature (F): 35 Concrete Temp (F): 64 (C1064) Lab Test Results Testing Lab: Denver, 3990 Fox Street, Denver, CO, 80216 Page 1 of 1 Client: FMFPE, LLC Loveland, CO 80538 2725 Rocky Mountain Ave Ste 200 Project: McWhinney Foothills Mall Multifamily 016-1668 Fort Collins, CO Compressive Strength of Concrete Test Method: ASTM C39; C31; C172 Sample: 24947 Report #: CC-000300 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Braden Hirsch Project Manager Plant: 751 Rioden Mix Design: N4513SP On-Site Admixtures: None Location Field Measurements Plastic Unit Weight: 149.2 (lb/ft³) (C138) Air Content: 1.7 (C231) Load Volume: 10 (yd³) Weather: Sunny Slump (in): 6 (C143) Air Temperature (F): Concrete Temp (F): 62 (C1064) Lab Test Results Testing Lab: Denver, 3990 Fox Street, Denver, CO, 80216 Page 1 of 1 Client: FMFPE, LLC Loveland, CO 80538 2725 Rocky Mountain Ave Ste 200 Project: McWhinney Foothills Mall Multifamily 016-1668 Fort Collins, CO Compressive Strength of Concrete Test Method: ASTM C39; C31; C172 Sample: 24946 Report #: CC-000308 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Braden Hirsch Project Manager Plant: 751 Rioden Mix Design: N4513SP On-Site Admixtures: None Location Field Measurements Plastic Unit Weight: 148.7 (lb/ft³) (C138) Air Content: 1.7 (C231) Load Volume: 10 (yd³) Weather: Sunny Slump (in): 5-1/2 (C143) Air Temperature (F): 35 Concrete Temp (F): 64 (C1064) Lab Test Results Testing Lab: Denver, 3990 Fox Street, Denver, CO, 80216 Page 1 of 1 Client: FMFPE, LLC Loveland, CO 80538 2725 Rocky Mountain Ave Ste 200 Project: McWhinney Foothills Mall Multifamily 016-1668 Fort Collins, CO Compressive Strength of Concrete Test Method: ASTM C39; C31; C172 Sample: 24945 Report #: CC-000299 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Braden Hirsch Project Manager On-Site Admixtures: 10.00 Gal Water (10 yd³) Location Field Measurements Plastic Unit Weight: Air Content: 3.5 (C231) Load Volume: 10 (yd³) Weather: Sunny Slump (in): 6-1/4 (C143) Air Temperature (F): 54 Concrete Temp (F): 68 (C1064) Lab Test Results Testing Lab: Denver, 3990 Fox Street, Denver, CO, 80216 Page 1 of 1 Client: FMFPE, LLC Loveland, CO 80538 2725 Rocky Mountain Ave Ste 200 Project: McWhinney Foothills Mall Multifamily 016-1668 Fort Collins, CO Compressive Strength of Concrete Test Method: ASTM C39; C31; C172 Sample: 24356 Report #: CC-000279 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Braden Hirsch Project Manager On-Site Admixtures: None Location Field Measurements Plastic Unit Weight: Air Content: 3.3 (C231) Load Volume: 11 (yd³) Weather: Sunny Slump (in): 4-1/4 (C143) Air Temperature (F): 48 Concrete Temp (F): 69 (C1064) Lab Test Results Testing Lab: Denver, 3990 Fox Street, Denver, CO, 80216 Page 1 of 1 Client: FMFPE, LLC Loveland, CO 80538 2725 Rocky Mountain Ave Ste 200 Project: McWhinney Foothills Mall Multifamily 016-1668 Fort Collins, CO Compressive Strength of Concrete Test Method: ASTM C39; C31; C172 Sample: 24346 Report #: CC-000281 Denver 3990 Fox Street Denver, CO 80216 Phone: 303-237-2072 Fax: 303-237-2659 Braden Hirsch Project Manager Denver Braden Hirsch Project Manager Project Manager