July 6; 2020
CSURF
2537 Research Boulevard, Suite 200
Fort Collins, CO 80526
Attn: Mr. Michael `Bo' Brown Bo.Brown(a-)colostate.edu)
Re: Construction Observation and Materials Testing Report — Submittal No. 7
Sunshine House — FC #213 V/
NEC of Lake Street and Shields Street —1080 West Lake Street
Fort Collins, Colorado
EEC Project No. 1194141
Mr. Brown:
4 qQ W-.WOF
0
EARTH ENGINEERING
CONSULTANTS, LLC
As requested, during the period May 18 through June 13, 2020, Earth Engineering Consultants,
LLC (EEC) personnel provided construction observation and testing services for the proposed
Sunshine House — FC #213 project located at the northeast corner (NEC) of Lake Street and
Shields Street in Fort Collins, Colorado. Those services were provided on a part-time/on-call
basis and included observation and evaluation of "open hole"/foundation bearing material for the
proposed playground equipment, observation and/or field density testing of pavement aggregate
base and curb -and -gutter subgrade material as described herein along with testing of cast -in -
place concrete for the referenced project. The results of the observation and testing services
completed by EEC personnel during the referenced period are included with this report.
Open Hole/Foundation Bearing Observations
On June 8, 2020, EEC personnel conducted a site visit to observe and evaluate the exposed
subgrade foundation bearing materials for the proposed playground foundation systems on the
north and south sides of the new building to verify general subsurface conditions in comparison
with the structural plans prepared by Soney FM LLC, dated April 30, 2020 and June 1, 2020 and
associated assumptions provided regarding bearing capacity. The proposed playground
foundations had been excavated to approximate foundation bearing elevations, in general,
approximately 30 inches below ground surface elevation. The exposed soils, in general,
consisted of apparent native and/or reworked sandy lean clay / clayey sand material.
4396 GREENFIELD DRIVE
WINDSOR, COLORADO 80550
(970) 545-3908 FAX (970) 663-0282
EARTH ENGINEERING CONSULTANTS, LLC
SUMMARY OF LABORATORY CLASSIFICATION/MOISTURE-DENSITY RELATIONSHIP
�oo^io
so% -
so^io
.. �o^io
L
m
.>�
} 60%
�
N
c 50%
ll
C
L� 40%
a
30°/a
20%
10% -
�%
�Q� �� � �.� �.�� �.�Q�
Grain Size in Millimeters
Sieve Size Peroent Passing
No.4 92%
No.10 83%
No.40 63%
No.200 34.9%
Material Designation: C
Sample Location: OnSite Overburden Subsoils
Material Descripfion: Dark Brown Clayey Sand with Gravel(SC)
Project: Sunshine House No.213-N/E/C of Lake and Shields ,-
Fort Collins,Colorado
Project No: 1194141
Date June 2020
Earth Engineering Consultants,LLC
EEC Project No. 1194141
July 6,2020
Page 2
Based on our observations, the foundation subgrades for the proposed playground equipment as
indicated herein, in general, have been prepared and appeared capable of supporting the
foundation footings using the maximum net allowable total load soil bearing pressure as
recommended in the structural plans provided by Soney FM LLC.
Observation,Laboratory and Field Densitv Testing Services
On May 21 and 22, 2020, EEC personnel provided preliminary and final observations of
aggregate base preparation at the intersection of the existing on-site pavement area and the new
parking lot south of the Sunshine House building. During our preliminary site visit on May 21,
2020, the excavation contractor was in the process of removing previously placed flow-fill at
several on-site utility tie-in locations generally east and northeast of the new building to
accommodate new asphalt surfacing. The excavated flow fill material appeared to be graded
similarly to an aggregate base material and was being placed at the intersection of the new
parking lot and the existing on-site pavement. At the time of our final site visit on May 22, 2020,
the processed material indicated herein was placed and compacted and, in general, appeared
suitable for asphalt surfacing.
During the referenced period, EEC personnel visited the site and obtained one (1) sample of the
on-site subgrade materials (EEC Sample ID "C"). The sample was retumed to our office for
further laboratory testing, evaluation and classification. Laboratory testing performed on the
sample included washed sieve analysis (ASTM C117 and C136), Atterberg limits (ASTM
D4398) and standard Proctor (ASTM Specification D698) tests. Results of the laboratory testing ,
completed by EEC personnel during the referenced period are shown on the attached summary
sheets. The recently completed Proctor test results were used to evaluate the relative compaction
of materials placed in the field.
During the referenced period, EEC personnel performed field density tests on sidewalk and curb-
and-gutter subgrade material as described herein, that was placed/prepared prior to our site visits.
The field density tests were completed at random locations within the areas tested and were
performed in general accordance with ASTM Specification D6938. The field density test results
and approximate location of each test completed during the referenced period are indicated on
the attached stunmary sheet and appropriate site diagram, respectively. With exception to
Consecutive Test Number 91, the final field density test results, after several areas were
reworked and retested as indicated herein by Retest of Consecutive Test No. (xx), conformed to
. �
Eanh Gngineering Consultanis,LLC
EEC Project No. 1194141
July 6,2020
Page 3
the project specific compaction requirement of at least 95% of standard Proctor maximum dry
density (ASTM D698) and were within t2% of the material's optimum moisture content.
Consecutive Test Number 91 was for the contractor's information only. We understand that area
was going to be prepared and tested at a later date.
� Testing of Cast-in-Place Concrete �
During the referenced period, EEC personnel tested Portland cement concrete delivered to the
site for placement as indicated on the enclosed daily repoits for the referenced project, (please
refer to EEC Set Nos. 10, 1 l and 11.5). Field testing performed on the plastic concrete included
slump, air content, unit weight, and concrete temperature. The ambient air temperature at the
time of placement was also recorded. A minimum of five (4-inch diameter by 8 inches in height)
concrete test cylinders were cast from representative samples on each respective date, for
laboratory curing and compressive strength testing. Results of the field and 7-day laboratory
� compressive strength test results performed during the referenced period are included herein,
while the 28-day results will be provided as they become available.
We appreciate the opporeunity to be of service to you on this project. If you have any questions �
concerning this report, or if we can be of further service to you in any other way, please do not
hesitate to contact us.
Very truly yours, ,
Earth Engineering Consultants,LLC
�o�PpO L/���
� ' �.S�tV'•..S'cn
c,� , O
,o �75
(%
�p�•.�'/gla�•'��i
'o � ••.J.....
��?
�sS��NAI.ENG
Jacob J. Silverman, P.E.
Project Engineer
Reviewed by: David A. Richer, P.E.
Senior Project Engineer
cc: GCH Construction Company—Rocky Ernest (rernest(u�chconstruction.com)
EARTH ENGINEERING CONSULTANTS, LLC
REPORT OF CAST-IN-PLACE CONCRETE TESTS
GENERALINFORMATION
Placement Date: 6/8/2020 Test No.: 10
Placement Location: Playground Structure Footings North Side of Building
Concrete Supplier: Sakrete High Strength Type of Placement: Hand
Ticket Number: N/A Truck Number: N/A
Mix Code: N/A Water Added on Site: None
Batch Time: N/A Sample Time: 10:15 AM Yards: N/A of N/A
Required 28 Day Compressive Strength(psi): 2500 EEC Technician: Matt
Comments:
FIELD TEST DATA
TEST RESULTS SPECIFICATIONS
Slump(in) ASTM C143
Air Content(%) ASTM C231
Unit Weight(pc� ASTM C138 ----
Concrete Temperature(deg F) ASTM C1064 73 90°Max
Air Temperature at Placement(deg F) ____
Comments:
COMPRESSIVE STRENGTH OF FIELD CASTTEST SPECIMENS(ASTM C39/C31)
Average
Maximum Cylinder Cylinder Compressive Compressive
Specimen Date Age Applied Load Height Diameter Area Failure Strength Strength
Number Tested days Ibs in) in) inZ T pe si si
10 B O6l15/20 7 32320 8 4 12.57 Shear 2570 2570
Project: Sunshine House No.213-N/E/C of Lake and Shields
Praject Number: 1194141 Report Distribution:
CSURF Real Estate Office-Bo.Brown@colostate.edu
,
EARTIi ENGINEERING CONSULTANTS,LLC
� REPORT OF CAST-IN-PLACE CONCRETE TESTS
GENERAL INFORMATION
Placement Date: 6/10/2020 Test No.: 11
Placement Location: Sidewalk-North Side of Lake at Shields
Concrete Supplier: Martin Marietta Type of Placement: Chute
Ticket Number: 49172420 Truck Number: 1716
Mix Code: A4780 Water Added on Site: NOne
Batch Time: 2:27 PM Sample Time: 3:15 PM Yards: 10 of 20.01
Required 28 Day Compressive Strength(psi): 4000 EEC Technician: Matt �
Comments:
FIELD TEST DATA
TEST RESULTS SPECIFICATIONS
Slump(in) ASTM C143 5.5"
Air Content(%) ASTM C231 6.3%
Unit Weight(pc� ASTM C138 146.0 ----
Concrete Temperature(deg F) ASTM C1064 73 90°Max
Air Temperature at Placement(deg F) 77 ____
Comments:
COMPRESSIVE STRENGTH OF FIELD CAST TEST SPECIMENS(ASTM C39/C31)
Average
Maximum Cylinder Cylinder Compressive Compressive
Specimen Date Age Applied Load Height Diameter Area Failure Strength Strength
Number Tested da s) Ibs in in in2 Type si psi)
11 B 06/17/20 7 42810 8 4 12.57 Shear 3410 3410
Project: Sunshine House No.213-N/E/C of Lake and Shields
Project Number: 1194141 Report Distribution:
CSURF Real Estate Office-Bo.Brown@colostate.edu
EARTH ENGINEERING CONSULTANTS,LLC
REPORT OF CAST-IN-PLACE CONCRETE TESTS
� GENERAL INFORMATION
Placement Date: 6/11/2020 Test No.: 11.5
Placement Location: Sidewalk Patches East Side of Shields
Concrete Supplier: Martin Marietta Type of Placement: Chute
Ticket Number: 49172489 Truck Number: 1738
Mix Code: A4780 WaterAdded on Site: None
Batch Time: 1:12 PM Sample Time: 2:05 PM Yards: 10 of 20.01
Required 28 Day Compressive Strength(psi): 4000 EEC Technician: SAY
Comments: ,
FIELD TEST DATA
TEST RESULTS SPECIFICATIONS
Slump(in) ASTM C143 3.75"
Air Content(%) ASTM C231 5.4%
Unit Weight(pc� ASTM C138 146.0 ---
Concrete Temperature(deg F) ASTM C1064 " 73 90°Max
Air Temperature at Placement(deg F) 81 ----
Comments:
COMPRESSIVE STRENGTH OF FIELD CAST TEST SPECIMENS(ASTM C39/C31)
Average
Maximum Cylinder Cylinder Compressive Compressive
Specimen Date Age Applied Load Height Diameter Area Failure Strength Strength
Number Tested da s Ibs in in inZ Ty e si psi
11.5 B 06/18/20 7 55870 8 4 12.57 Shear 4450 4450
Project: Sunshine House No.213-N/E/C of Lake and Shields
Project Number: 1194141 Report Distribution:
CSURF Real Estate Office-Bo.Brown@colostate.edu
� �
EARTH ENGINEERING CONSULTANTS,LLC
SUMMARY OF FIELD DENSTI'Y TESTS
Project Name: Sunshine House No.213-N/E/C of Lake and Shields Project No: 1194141
Location: Fort Collins,Colorado Date: June 2020
Prodor Designation C
Maximum Dry Density(pc� 115.5
Optimum Moisture Content(%) 73.5%
Required Moisture Variance OMC+/-Z/o
Required Percent Compaction 95%
Leboratory Method ASTM D-698
m `m � Compliance wi�h
Field Test ResulLs
? � m F a m �' �� ProjectSpecs
d z �^ >. E Approximate Test LocaUon f Notes � � e �
� � � �t0 Z' Elev./Lift Matenal Percent D �� �`m v E Moisture %,Comp.
V� � No. (Practor) Moisture De sity � � a V (Fall)/ (Fail)/
84 61B 1 SidewalkSuhgrade-SeeDiagram 0.0 C 75.6% 104.4 2.1% 90% •FA/L• •FAII`
85 618 2 Sidewalk Suhgrade•See Dfagrem 0.0 C 13.8°/, 103.8 0.3% 90% Pass 'FAIL•
86 6I8 3 Sldewalk Su6grede•See Oiagrem 0.0 C 14.1% 104,7 0.6% 91% Pass •FAIL•
87 618 4 SidewalkSubgrede-SeeDiagram 0.0 C 15.3% 105.3 1.8% 97% Pass •FAIL•
88 6/10 1 Retest of Conseeutive Test Nos.86 and 77 0.0 C 12.2% 117.9 -1.3% 102% Pass Pass
89 6/10 2 Retest of Consecutive Test No.85 0.0 C 12.4% 113.6 -1.1% 98% Pass Pass
90 6/70 3 Retest of Consacutivo Test No.84 0.0 C 12.6% 112.3 -0.9°/a 97% Pass Pass
91 6111 1 Curb$GutterSubgrede-SeeDiagram 0.0 C 19.8% ForConiractorslnformationOnly
�
z,
�_i" i.,
i �.:i� �'ta,- '' ...' �+�'+�u,y � � ;�ya=� auscnkoeN � � ����oawwx � � ' I
i.•I ,n�L�w�o � � � � aonmon '�° � "°'• i
J•\ M1�M11or f1W RV.N�bIu1P1
i H I '���•' � �-�[ �I,—�._,�� � 3 I 9�ocK, s.,.r.m aµv:"o,;.vu m I i
N � _ LOT� �
o � � -��.�..�.�__.,� _...� � � i::i � , ;
I W� �� ; _.�__._��___. �.. — ��, � II�� i i i i
� Y ____.__�,______arw.reaww JAh1ESC0URT nnn+�nay.•eax�a � �
a.
� � .; - _ _ ______ ----��----� _ C PUSGARO 9
��`
� �� i • � i � ma�wmex�mwr r I ��OCK3E i ..
(1
� d I .::-. . _. OT1 I.
,[.' — _ .. . .�. �. .' .. -
..__, . ...... ,.. �..._� ._ I
i.I I
' �` I � L0T2 ; Lp73 -i L0T4
__ I �__—__ �vonuw . '_ .. '__�_ _ ,-,� ' � _--_
I. mawwco I� t
rora�aA " �y T 4�mcnuml..Z I 1 _f� . � � � .� � ' . . ..\. � rtemi¢Eu�v..��
Lvummumenr r
-�I ,/, I� _ -�t� Enemaz ovmno� � \ m�nueeusruert __ _ ____ /
o ; �Ur�o� '� oa�ueuaeuoon r I � � �y�nv�ram � �zpweuxm 1 \ �'
�� � I I� � � I `._______ .' aeevre�c �m� _� y
____ __ _ rc
rerµ
� I i� I uerri � c I I meemvu� Ic�mr �•���� .
I � j� � i asevm xO�YAfE E�miaw Q��� \ CO . �
j �� kv�mm i 11•�rN% . Rm �� ��x�uev..eomw n I i
� I is�mm �ew�'' I � I E�missr i��un�e.n , � 1 �- � , '
�umm
� i ' ` � �� i'�eumva� � i `i Ewavn rnsrwc - � �ggg9 � �
-- . 1 I al � �ucniiui.mmrz �!r e�Ism� I % ��� � , w��rnu.a� \1,\� eosrxa�rwv � I I _ / .
I �y� wuoar I I �
y wnn aairrv�c � � �
'/! ;�/ icutinensamrt
�� I I � I � I� o�'.�w�x.oi� �evia�zve � � 4 � 1 msrvmrv.e � � �
•ew
Si � � I .''�� � .-��� �� � ;i ��� �`` � � �..,H,� � i 4
,
I_� : �C° � ; , ._ , , • u•� m�.�„ i ^ �
i i . - , k�,.�.�. 1-�.,�„ , � yr
� i I �. � I � ' LOT1 � ���ecm¢_eimr-n-. _____ ____'_______'� ` .°'awea�aiwe&c- � � ^
• I! �sw�irnanH¢
1 I, �:I � I 'C mcmvzc�o� . � na1nrE_--_nTsi•n2auoi ~ ��.��ea�is) I I
I r � . .. :a I __ _-���ems.n's ___' _—_-___."" __'___'___ �
1 Id° - �1 mmm � I
� I �+� �e rry wrv�msn�m �'�I. ' ireP�uvm I � \ � �rxo-sraa � � �I !
�5 rr.•ern.0
Emrwow�w �I I am�r�r � � � � i � .1� x@
xu.w.uivnro �F w�rnmmce \ Y s
xv.w•noio°�°c.v� I I . � o �' rnw`�Y°.°'`rimns \ f ;� o�j
I wv.art, m �I � I I °Gn � . wv.x.ama�ero X
�� I � I II . �� : I I m'wr��rr� 1 � I I I i ' ,o x
� I � w
� I 'I6 :. �� �ra ' I F��v�`Gma L0T2 � ��v�ury : � I pw
i q � ra.e�ei I � (( � i rwsusm � I ! O U
m , p i � ,l�V�,I��l _ II `ear +'v y t...� � � I I Q \ a
i "�' I I I �°` � .S
_� � m� A I � ���m�n L. . Y � I r �. '4m .�' �' i � � ' ' • �i � �' i .
� � N d � ' — " __ -- - -- *
_ , ,
�_I _ I � � _
=T� � � � � �y � emrxamwc I I
�J � ' � .
I � . mon� 1 °V°��' � I
� aramracr -_ ' � � �
� �t � ! ' � � I 03/lII"i mwsrwan .. ..— — '.— - — - - —..—..- . +
s�iixu�
� I._ � . .i �elw.. .�r___"_'"'F'"'� I w I .
I I � C' - / __' " .... '___1_ '______'_ , I I
� � � � � 1--irl� ^ . ���„ ;J I ; �� ; , m��,,,� � ;-
�, � ;,
� � � �:. � � � e �
_
;r�----e---- - -- - -- --- �
I '
; i ; I,� . � i ' II�� ,;;::: -_- ------ -- r, . , � `-
�,...1 �i I � .. _�1.1..._..- II n ��,a,", i _ ;
_. .
1 � —�i i ` ' T _____'__f_f �j �
"' �y-�� -- �`-�� 1 � � 03/184 I __;5/64-'-- 1 I � �
x-' I � smwmrond d �I sme1uee ` on+xuzewg.mrt
��� i I 1'_ '"" i� q 1�umc�ar 5,�6�4'�"Q3/2 r-ro�i�e�w mowa✓`fv.sm.�r i9 i i w�0re e�ay..ma��ie�
� � II mv�weew�v.mn I I
0 5 �` � ! �I �� . • i , a3���''-' — — _ _ '
�� � � . $
I I.�II S/63 �,�p�e+c�xr I
i..
! ' i
a� � I � �� �uPw�mrt � uxee �I S/6.2mrwvHert I i
j II . ♦ p - rvmuer�wmrd'�~� I� �ami I -
� - �• Y- d m d I� II. N om�e :ewaam�oo:a I
• '^____
-�h�--v7-��- _a LL__ umdrooevuem� m I
` II r V f u � � '____\ �.__'mmrxcnwxaouwsrzevux� - _ ' ____"_________ _ 8 I
_ � ��o - u a :A �
'_ �mn�oux�m .._ �='�^�-�--����t�� 1-_—�_�_'— - _ - _ I .
.wwawon '. '— .. .• -
erv.x.emant0 �..,f "— .---- � � � • ' i ommoaww�
v�r.eo�n+em " wim
o� � iawmr.0 ' � .. • --"-_ - '—_" .-- °Ni+:n-mnnm�i
w� I ���. _____ __ wrsrvw _ LAKE$ EET � xu.aur.eoiau�
t I - - _ e¢xranmlM_u__�-____ _ - _____ _— .
nV.art•unm�
rc.wua
Field Density Test Location Diagram
Sunshine House No. Z 13 - N/E/C of Lake & Shields
EEC Project#: 1 194141
North Fill, Subgrade, &Aggregate Base '
Not to Seale
EARTH ENGINEERING CONSULTANTS, LLC
i
EARTH ENGINEERING CONSULTANTS, LLC
SUMMARY OF LABORATORY CLASSIFICATION/MOISTURE-DENSITY
RELATIONSHIl'
-�..
" 145 Material Designation: C
Sample Location: OnSite Overburden Subsoils
Description: Dark Brown Clayey Sand with Gravel(SC)
140
Atterberq Limits(ASTM D-43181
Liquid Limit: 33
135 PlasticLimit: �g
Plasticity Index: �q .
Passing No.200 Sieve(AASHTO T 11/ASTM C 117): 34.9%
130 Standard Proctor(ASTM D-698)
«
Maximum Dry Density: 115.5 pcf
LL125 Optimum Moisture Content: 13.5°/a
u
'a
�
v Curves for 100%Saturation
a 120 For Specific Gravity Equal to:
N
L
C 2.8�
7
a 115 2.70
� 2.60
.y
G
0 110
�
0
105
100
95
90
0 5 10 15 20 25 30 35
Percent Moisture
Project: Sunshine House No.213-N/E/C of Lake and Shields
FoR Collins,Colorado
Praject No: 1194141
Date June 2020