HomeMy WebLinkAbout3301 Stanford Rd - Special Inspections/Engineering - 04/13/2017�O LSSO N A S S O C I A T E S ril 13, 2017 McWhinney Attn: Tucker Isgrig 1800 Wazee Street Suite 200 Denver, CO 80202 RE: Foothills Mall Multifamily — Building 12 - Final Inspection Report Fort Collins, Colorado PGUWL IT 4 81140 1314 Olsson Associates Project No. 016-1668 33o f, Sl'J►p flip PQhD Dear Mr. Isgrig: In accordance with your request, representatives of Olsson Associates have provided Special Inspections and Construction Materials Testing services for Building 12 at the above referenced site. The items observed include foundation bearing materials, structural fill placement, reinforced concrete, post -tension tendon placement and elongation measurement and placement of the ATS shear wall hold down system. Our services were provided on a part to full-time basis between July 7, 2016 and March 16, 2017, as scheduled by the general contractor. Summary of Activities Foundation Bearing Materials The bearing materials in the bases of the grade beam footing excavations in the following locations were observed during this reporting period: August 02, 2016 - Hand auger testing between Lines 1-5, A-C August 31, 2016 - Line A, 1-5; Line 1, A-C September 01, 2016 - Line C, 1-5; Line 5, A-C The bearing materials were evaluated with respect to the 1,500-psf design bearing pressure. Hand auger testing was performed to sample material beneath the bearing materials to delineate areas of deleterious debris. Deleterious material was encountered beneath the foundation systems and "ribs" of the post -tensioned floor slab between lines A-C, 1-5. The contractor elected to over -excavate and backfill the material in these locations. 3990 Fox Street TEL 303.237.2072 www.olssonassociates.com Denver, CO 80216 FAX 303.237.2659 Earthwork Observation Samples of on -site and imported materials were obtained for laboratory moisture -density (standard Proctor), P-200, and Atterberg Limits testing. Field moisture -density tests were performed on the structural fill placed in the following locations during this reporting period: July 13, 2016 - 2 to 3-feet below Finished Floor Elevation along Line A, 1-5 July 14, 2016 - 1.5-feet below Finished Floor Elevation between Lines B-C, 1-5 July 15, 2016 - 1-foot below Finished Floor Elevation between Lines B-C, 1-5 July 18, 2016 - 0.5 to 1-feet below Finished Floor Elevation between Lines A-C,1-5 August 26, 2016 - 0.5 to 3-feet below Finished Floor Elevation for plumbing between Lines B-C, 1-5 August 29, 2016 - 0.5-feet below Finished Floor Elevation for plumbing along Line B, 1-5 Results of the field density tests are summarized in the attached reports. Reinforced Concrete Placement of the reinforcing steel and concrete in the following locations was observed during this reporting period: September 08, 2016 - Shallow foundations and grade beams between Lines A-C, 1-5 September 29, 2016 - Post -tensioned floor slab between Lines A-C, 1-5 October 03, 2016 - Post -tensioned floor slab between Lines A-C, 1-5 Placement of the reinforcing steel in the above referenced locations was observed on a part-time basis. Field tests were performed and test specimens were cast with concrete placed in these locations. Olsson's field representatives observed the placement of concrete on a full-time basis. Results of the compressive strength tests can be found in the attached reports. Post -Tensioned Concrete Olsson observed the marking and stressing of the post -tensioned tendons within the floor slab of Building 12 on a full-time basis: September 29, 2016 -Tendon layout in the floor slab between Lines A-C, 1-5 October 04, 2016 - 50% stressing of post -tension tendons October 11, 2016 - 100% stressing of post -tension tendons Olsson prepared post -tensioned tendon layouts to number and reference each individual tendon. Intermediate and final elongations were measured and reported to the post - tension slab designer for approval. The measured elongations can be found in the attached reports. ATS Shear Wall Hold Downs Placement of the ATS hold down system hardware was observed during this reporting period. On March 16, 2017, the placement of ATS hold down system hardware including plate to anchor bolt welds, rod sizes and nut connections, stud nailing patterns and plate to floor heights were observed Status of Compliance This report represents Olsson's final inspection report for Building 12 at the Foothills Mall Multifamily Apartment Complex in Fort Collins, Colorado. The special inspection items observed and tested by our field personnel include foundation bearing materials, structural fill placement, reinforced concrete, post -tensioned tendon placement and elongation measurements and placement of the ATS shear wall hold-down system. To the best of our belief and knowledge, the items observed and/or tested by our field personnel and explicitly reported in the attached test and inspection reports were in general compliance with the project specifications or recommendations of the design engineer. If you have any questions regarding this report, or if we may be of any further service, please contact us at 303.237.2072. Respectfully Submitted; OLSSON ASSOCIATES Juruan 01 ltypolu Assistant Project Manager Braden Hirsch, PE Colorado License No. 51920 Associate Engineer Monroe & Newell Engineers, Inc. Vail • Denver September 11, 2017 Johnson Nathan Strohe 1600 Wynkoop St., Ste. 100 Denver, CO 80202 Attn: Dale Sanders Re: Foothills Mall Multifamily Apartments Lot 4 Bldg 12 3301 Stanford Rd., Fort Collins, CO 80525 (M&N#9929) Dear Mr. Sanders, Monroe & Newell Engineers, Inc. observed Lot 4 Building 12, 3301 Stanford Rd. Permit #B 1601314 during construction. To the best of our knowledge and belief, based on our visual observations, and the information provided to us, the foundation and wood framing appears to be constructed in compliance with the intent of the construction documents prepared by our office and approved by the Building Department. If you have any questions or comments, please call. Very truly yours, MONROE & NEWELL ENGINEERS, INC. CA a:•t; 6N-in2pal rroll, P.E. www.monroe-newell.com 1400 Glenarm • Suite 101 • Denver, Colorado 80202 znz r,')z_ao')7 0 i:aVznz