LETTER OF FOUNDATION GENERAL CONFORMANCE
August 13, 2014
Aspen Heights
330 S. College Ave. #200
Fort Collins, CO 80525
ATTN: Roger Frakes
Project: Aspen Heights Student Housing
488 Lupine Dr. (Steamboat Unit 2)
Fort Collins, CO 80524
Permit #: B1400311
Mr. Frakes,
Per your request, our office has performed the Construction Phase Consulting Services for the above mentioned
project including the following:
• Review of concrete mix designs supplied by Innovative Concrete Solutions.
• Review of stressing equipment calibration logs supplied by Innovative Concrete Solutions.
• Review of observation logs for post-tension concrete stressing supplied by Terracon.
• Request For Information (RFI) submittal review and response.
Based on our review of the information noted above, Anchor Engineering, Inc. feels that the post-tension
concrete slab-on-grade foundation for the above mentioned project has been completed in general
conformance with the structural foundation drawings prepared by our office.
Should questions arise, or if further information is required, please contact our office.