HomeMy WebLinkAbout1933 Jessup Dr - Correspondence/Health Department - 04/14/2015DEPARTMENT OF HEALTH AND ENVIRONMENT
1525 Blue Spruce Drive
Fort Collins, Colorado 80524-2004
General Health (970) 498-6700
Environmental Health (970) 498-6775
Fax (970) 498-6772
April 14, 2015
Jessup Farm, LLC
dba Bindle Coffee
3702 Manhattan Avenue
Fort Collins, Colorado 80525
To the Involved Parties,
The plans and specifications submitted for the construction of Bindle Coffee to be
located at 1933 Jessup Drive in Fort Collins, Colorado, have been reviewed by this
department. The following items are specific to the submitted plans and must be
completed in order to maintain compliance with the Colorado Retail Food Establishment
Rules and Regulations. The plans are approved at this time.
PLEASE NOTE: This letter contains important information and advisements for the
construction of the establishment. Establishment owners are responsible for items
noted in this letter. Please share this letter with all involved parties, including the
construction superintendent and contractors at the construction site. If there are any
questions regarding information in this letter or anything else related to the construction
and operation of the establishment, please call at (970) 498-6833.
Menu and Food Handling:
1. A revised menu (received April 13, 2015) was provided as a separate submittal,
greatly reducing the items to be prepared on-site. The menu will include various
espresso, coffee, tea and other hot beverages, as well as shelf-stable baked
goods including scones, muffins and cookies. Yogurt bowls and savory English
muffins with herbed cream cheese will also be offered.
a. The establishment will also roast their own coffee beans using a vented
roaster.
b. Even with the reduced menu, the refrigeration on the premises is still
inadequate. Additional refrigeration must be provided to maintain the
temperatures of the back-up gallons of milk, the milk alternatives (soy,
coconut), cream cheese, tomatoes, sprouts, eggs, yogurt, butter, etc., all
used in beverages or as ingredients to other items.
i. Originally proposed for the kitchen and coffee bar were the single
door under counter, a single door merchandiser (True) and a single
door freezer.
1. The single door True refrigerator is not approved for
potentially hazardous foods so a single door Supera cooler
has been proposed.
2. Per the April 14th
electronic mail received from Andrew
Webb, a 2-door upright Supera reach-in cooler will be
installed to provide more cold holding capacity.
c. It is understood that a chicken coop will be operating on-site and is
overseen by The Farmhouse. The chicken coop eggs may not be utilized
at the coffee shop unless the eggs are an approved source per the
Colorado Department of Agriculture.
2. Written food handling procedures were not provided as part of the application.
To promote active managerial control for safe food handling, standard operating
procedures should be created and staff properly trained on the procedures. Staff
should also be regularly monitored to ensure SOPs are being followed. Please
incorporate the following:
a. A temperature log was provided for the refrigeration temperatures. It is
recommended that logs also be required for the monitoring of food
temperatures for cooling of room temperature prepared items like sliced
tomatoes and specific high hazard produce like sprouts.
b. With the menu revisions, there will be no cooling of cooked, potentially
hazardous foods. Please be advised, room temperature prepared foods
are required to under go rapid cooling. Rapid cooling requires prepared
foods to be cooled from post-preparation temperature to below 41ºF within
four hours. This is required for prepared products such as sliced/chopped
produce (sliced tomatoes) and blended/herbed cream cheeses. Covering
these items immediately after preparation and placing the products in the
refrigeration units is not approved. Only after the product has quickly
cooled to less than 41ºF may the product be covered for storage.
c. It is acknowledged that cooled food will not be reheated for hot holding.
d. An employee illness policy was provided. The policy indicated that food
employees experiencing vomiting, diarrhea, jaundice, sore throat with
fever, and infected cuts/burns, be excluded from work til 24 hours
symptom free. This is accurate, but it is recommended that employees
remain home for 48-72 hours to minimize exposure to other employees
and customers from
i. Please be advised, written policies should be in place that are more
descriptive with the reportable illnesses and must also outline
controls used to manage workers that return to work after being ill.
a. Please be advised, the Colorado Retail Food
Establishment Rule and Regulations specifically state
that an employee must be excluded from work if the
food employee is symptomatic with vomiting,
diarrhea, jaundice, sore throat with fever, except
when the symptom is from a noninfectious condition
(examples: allergic reaction/intolerance). Employees
shall not return to work til they are symptom free for
24 hours (48 to 72 hours recommended).
b. Employees diagnosed with a Health Department
reportable illness such as Norovirus, Hepatitis A virus,
Shigella spp., Enterohemorrhagic or Shiga Toxin-
Producing Escherichia coli, Salmonella Typhi; or other
enteric bacterial pathogen such as Salmonella or
Campylobacter, must be excluded from work.
Specific exclusions and requirements to return to
work are provided in the regulations in Chapter 2 for
the reportable illnesses.
i. In most cases, negative test results, physician
and health department approval are required
prior to returning to work.
ii. The management should establish an environment that allows for
open communication between management and employees to help
in identifying employees that have been ill to assist in their task
assignments upon returning to work.
iii. Keep records to identify employee schedules to monitor scheduled
hours, sick leave and shift changes.
e. It is acknowledged that employees that experience a cut or burn will be
required to clean the injury, and then use a band aid to cover the wound
as well as a glove.
f. It was indicated in the application that employees will be required to use
utensils or gloves to handle open foods. Please be advised, employees
are required to wash hands prior to applying gloves.
Equipment, Cleaning, and Accessibility:
3. Food service equipment must be of commercial design that is certified or
classified for sanitation by an American National Standards Institute (ANSI)
accredited certification program such as NSF, ETL Sanitation, UL
Sanitation, or BISSC Certified.
a. Custom made and used equipment cannot be approved until it is
visually inspected.
b. The refrigerated display will now be replaced with a glass built-in
counter, ambient display. Inspection will be required for approval.
c. Pitcher rinser (EQ19); inspection will be required for approval.
d. A Waring commercial toaster has been proposed for install.
4. Heavy floor mounted equipment must be mounted on casters to allow for
mobility and easy cleaning of the equipment, surrounding surfaces and
adjoining equipment. The following equipment is required to be installed
on casters:
a. reach-in cooler (EQ10)
b. reach-in freezer (EQ11)
c. convection oven stand (EQ20)
d. Heavy counter mounted equipment which cannot be easily moved
for cleaning, must be installed on four inch sanitary legs or neatly
sealed to counters to facilitate cleaning.
i. Espresso machine (EQ1)
ii. Grinders (EQ2-4)
iii. Coffee roaster (if counter mounted)
e. Heavy floor mounted equipment that will require a minimum of six
inch legs include:
i. Prep table
ii. Coffee roaster (if floor mounted; may also be sealed in place)
5. Dunnage racks, shelves and other floor racking systems must be installed in a
manner that will not inhibit or prevent easy cleaning of floors and surrounding
surfaces.
a. Storage shelves located in all food preparation and storage areas must be
situated at least six inches off the floor.
b. Wooden shelving or pallets are not approved for use in storage, kitchen
and ware washing areas.
c. It has been acknowledged that wooden pallets 15 inches off the floor will
be used for burlap bags of green coffee storage on the retail sales floor.
6. Hard to clean spaces or gaps around equipment, counters, utilities and plumbing
must be eliminated to provide for easy cleaning. All equipment, cabinets or
counters that are not mounted on casters or are not easily moveable must be:
a. Spaced in accordance with Section 4-302 A and C of the Rules and
Regulations so the surfaces of the floors, walls and exterior surfaces of
equipment and cabinets can be easily cleaned; or
b. Neatly sealed to adjoining walls, equipment, cabinets or counters.
i. The front service counters and display cooler and supporting mill
work/cabinetry must be sealed to all adjoining surfaces, including
the floors and walls, and the counter top sealed to the base.
ii. The ware washing fixtures, hand sinks and the mop sink basin must
be neatly sealed to the supporting wall.
Ventilation:
7. The establishment is not approved for grease cooking.
a. A commercial convection oven with a 1.5 kW rating is proposed for
cooking baked goods.
b. A Diedrich coffee roaster with a 12,000 BTU rating is proposed for
roasting coffee on-site.
8. Mechanical plans were not submitted for review. It was indicated via
electronic mail on April 13th
, that the coffee roaster will be direct vented
using a Metalbestos vent for high temperature, model UT/ST.
a. Please be advised, the exhaust from the coffee roaster ventilation
system may not exceed 20% opacity measured outside the building
as per Colorado State Air Quality Regulations.
9. A single occupancy restroom has been proposed. Please be advised, this
restroom must be provided with mechanical exhaust ventilation to the
outside.
Plumbing:
10. A food preparation sink is proposed for installation in the kitchen.
Specification sheets were not provided. The preparation sink is required to
have an 18 inch drain board and have a waste line directed to a floor sink.
11. Ware washing sink drain boards must be self-draining and directed to the ware
washing sink bowls or dish machines.
a. The 3-compartment sink specifications were provided via electronic
mail on April 14th
. 18 inch drain boards are proposed. Per the April
13th
email, it was indicated that 24 inch drain boards would be
installed on both ends per the requirement.
b. A wire rack will be required to be installed above the 3-compartment
sink that is as long as the length of each side of the sink to
accommodate air drying of cleaned equipment, as well as storage.
12. The plans did not specify if a garbage disposal will be installed. Please be
advised, if a garbage disposal is installed, the following are required:
a. Please be advised if a garbage disposal is installed at a food preparation
sink or 3-compartment ware washing sink it must be installed in the drain
board and be directly plumbed to sewer. Garbage disposals are not
permitted to be installed within a sink basin.
b. A scupper drain must also be installed and must span the entire flat
section of the drain board of the food preparation sink.
c. An additional 18” drain board is required to be provided if installed on the
food preparation sink drain board.
13. Hand washing sinks must be easily accessible in all areas where food is
prepared, served or where utensils and equipment are washed.
a. All hand washing sinks must be provided with hot and cold running water
under pressure through a mixing valve, single service hand towels from a
dispenser and hand soap.
b. Conveniently located hand sinks are proposed for the kitchen, coffee bar
and the restroom.
14. A mop sink for the disposal of mop water and for the purpose of filling mop
buckets and cleaning mops is proposed.
a. The mop sink will be provided with hot and cold running water.
b. Mop and broom hangers must be provided at the mop sink to properly
hang and air dry mops.
c. Storage shelves must also be provided to properly store cleaning supplies.
15. It was not indicated whether chemical dispensing units will be provided at
the ware washing sink, mop sink, or food preparation sink. If installed, the
following are required:
a. Chemical dispensing units must be supplied with both hot and cold
running water at 3-compartment sinks and mop sinks.
b. A separate faucet must be provided for chemical dispensing units
installed at the mop sink, therefore resulting in two faucets with hot
and cold running water; or a faucet with no built-in vacuum breaker
may be installed at the mop sink with a chemical dispenser that has
a plain water option.
c. When installing chemical dispensers above the 3-compartment sink,
the dish detergent and the sanitizer must be stored above the soiled
drain board and/or washing basin of the 3-compartment sink, or
below the drain board/sink.
16. Restroom fixtures are based on the requirements of the 2009 International
Plumbing Code. No seating totals were proposed in the application, but 21
seats have been proposed for inside the coffee bar per the floor plan.
Please be advised, with only one restroom, the coffee shop is limited to a
total of 15 seats for indoor and outdoor seating. With 21 proposed seats
(and potentially more outdoor), the single use restroom with one toilet and
one hand sink is not approved.
a. If the City of Fort Collins building department has approved the
single restroom for 21 plus seats, please provide written
documentation.
b. If the City has not approved the seating, then remove seating and do
not provide outdoor seating.
17. No water heating system was proposed. It was indicated in the April 13th
email that the dish machine would not be installed below the 3-comp sink.
The water heating system was sized for either situation:
a. Without the dishmachine, the water heating system must have a
minimum of 32 gallons/hour recovery rate at 100°F rise and a 30,320
BTU rating.
b. With the dishmachine (estimated with a 30 gallons per hour
consumption rate), the water heating system must have a minimum
of 68 gallons/hour recovery rate at 100°F rise and a 70,809 BTU
rating.
c. Submit make, model number, recovery rate and BTU rating of a water
heater that meets the above specifications.
18. Plumbing plans were not provided. All drains from the following
equipment are required to be directed to a floor drain or floor sink and be
properly air gapped:
a. 3-compartment ware washing sink (EQ14)
b. food preparation sink (EQ17)
c. ice machine and ice bin (EQ12)
d. pitcher rinser (EQ19)
e. Espresso/drink dispensers/drink overflow drains (EQ1)
f. water heater
g. Floor sinks must not be installed under equipment or cabinetry
where they cannot be cleaned.
h. All floor sinks and floor drains must be installed so they are flush
with the finished floor.
19. Please be advised approved, properly installed, backflow devices must be
provided on all submerged inlets, hose bib, water lines for beverage dispensers
(espresso machine, pitcher rinser, ice machine). Backflow devices on water
lines subject to back pressure or continuous pressure must be equipped with
backflow preventers that are designed for continuous pressure.
20. The plans did not propose a grease trap or interceptor for the coffee shop. It is
acknowledged that there is one on the property for the restaurant. Please be
advised, the health department does not determine the need for grease trap or
interceptor. If the local wastewater authority requires one, the grease
trap/interceptor must be installed out of the food preparation areas, storage and
ware washing areas and the top of the trap must be finished flush with the
finished floor to allow for easy cleaning of surrounding surfaces.
21. All plumbing, gas lines, electrical conduit and other service utility lines
must be located behind walls, above finished ceilings or below floors in
finished rooms and areas.
a. Exposed water pipes, sewer lines, gas lines or electrical conduit
running along the surface of the walls, ceiling or floors are not
approved.
b. All drain lines, water lines, gas lines and electrical conduit running
along the walls in finished rooms must be boxed in or completely
concealed along the wall to facilitate easy cleaning.
c. Please be advised external floor or wall mounted Uni-strut or hard to
clean brackets are not approved.
Structure, Finishes, General:
22. Illumination/lighting plans were not submitted. Please be advised, the
following light levels are required in the following areas:
a. At least 50 foot candles of light are required on all surfaces where
food is prepared (back kitchen, coffee roasting, ice machine,
espresso counters) and equipment and utensils are washed
(kitchen).
i. Since open food handling does occur in the front service
counter, lighting should be sufficient to minimize physical
contamination of the open products as well as maintain
cleanliness.
b. At least 20 foot candles of light are required on all other surfaces
within restroom and custodial closet.
c. All lights in the above areas, except restroom and custodial closet,
must be shielded in an approved manner.
d. All lights inside equipment and above open food must also be
shielded.
e. Please be advised that additional light fixtures may be required if it is
determined that the light levels are inadequate during construction.
23. Please be advised, food must be adequately protected from customer
contamination, such as coughing, sneezing and handling, especially at the front
service counter.
a. All open foods in the coffee bar must be stored in the glass display,
covered or wrapped.
24. To help prevent insect and rodent entry into the building all outer openings
including doors and windows must be kept closed or permanent screens or air
curtains must be installed on outer openings that will be left open periodically.
a. Weather stripping, threshold and/or broom sweeps must be installed on all
outside doors to eliminate gaps to the outside.
b. All exit and restroom doors must be fitted with self-closures.
25. It has been acknowledged that the glass wall proposed for the south side
of the building will be a functioning garage door opening directly into the
coffee back bar area.
a. Unprotected roll-up garage doors that open directly into food
preparation areas are prohibited. Only limited food and beverage
preparation is permitted in open air bars. Roasting coffee and
grinding coffee for retail is not allowed under limited preparation.
b. The proposed layout is not approved. Please propose an alternative,
or create a glass wall that does not open.
26. Floors, walls, ceilings, counter tops, storage shelves, cabinets and all work
surfaces, located within all kitchen and food preparation areas, storage areas,
custodial closet, restroom, serving area/coffee bar, and ware washing area, must
be of an approved material that is smooth, durable, non-absorbent and easily
cleanable.
a. The floor finish proposed for the kitchen/janitor is ‘quarry tile or
equal’ and the back bar floor finish will be a ‘luxury tile or equal’.
Please be advised, if a material other than a ceramic, quarry or
commercial vinyl is used, the material must first be approved by the
health department. There are several epoxy type floor surfaces that
are not approved ad require a sample submittal for evaluation.
i. No specific cove base was proposed for the kitchen, back bar,
restroom and janitor closet.
1. Please be advised, all floor/wall junctures and stationary
equipment floor junctures in the above listed areas must
be provided with approved concave coving.
a. If ceramic/quarry tile coving is provided, the cove
base tiles must be installed flush with the finished
floor tiles. Top set of ceramic/quarry tile base is
not allowed.
b. If installing rubber/vinyl cove base, it must be
neatly sealed with silicon at the top and bottom.
b. The proposed ceiling finish for the coffee back bar and the kitchen
will be gypsum board installed directly to the existing roof frame.
Please be advised, the gypsum board must be painted to be smooth
and nonabsorbent.
c. No wall finish is proposed for the back bar area. Page A8.1 of the
plans indicates that the back walls will be comprised of horizontal
planks (wood).
i. A nonabsorbent backsplash starting at the floor and ending 12
inches above the height of the tallest equipment in the bar is
required behind the equipment of the east wood wall of the
back bar.
d. The proposed walls of the kitchen are FRP on page A1.1, but
displayed as brick and horizontal planks (wood) in the interior
elevations of page A8.1.
i. Brick and wood are not approved in the kitchen and janitor
closet. The walls must be covered with FRP.
27. The outside trash and recycling areas must be located on a cleanable surface of
concrete or machine laid asphalt.
28. Provide an approved area for adequate storage of employee’s personal items,
such as coats, clothing, backpacks and handbags that is separate from food and
clean equipment.
29. The following items are required where food handling and ware washing occur in
the establishment:
a. food product thermometers scaled 0 to 220°F, digital thermometers or
thermocouple
b. food handlers’ gloves and finger cots
c. approved sanitizer
d. test strips for the sanitizer
Please review all items, with emphasis on bolded items, including: 1, 2, 3, 4, 8, 9,
10, 11, 15, 16, 17, 18, 19, 21, 22, 25 and 26, and submit information as required. Items
requiring information can be submitted either in written form or as an addendum to the
plans submitted. The written plans are approved at this time.
Please be advised, approval of the plans, including the above modifications
outlined in this plan review letter, does not constitute acceptance of the completed
structures. Inspections of the premises must be conducted by this department prior to
approval for operation and licensure of the establishment. Failure to follow the
recommended changes may prevent or delay licensure. The establishment is required
to obtain a Retail Food Establishment License. An application for the required license
will be provided by the department prior to the opening inspection.
In addition to the $100 plan review application fee paid at the time the plans were
submitted for review, a review fee is assessed for the actual review time. The review
fee is assessed at a rate of $44 per hour. Final review cost for this project is $176.
Please be advised, before the department can give any approval for operation all plan
review fees must be paid. The plan review billing invoice for this project is attached to
the hard copy of the final approval letter.
Please feel free to contact this department if questions arise, or if I can be of
further service at 498-6833.
Sincerely,
Lea Schneider
Environmental Health Specialist
cc: City of Fort Collins Building Department via electronic mail
Andrew Webb, Bindle Coffee, via electronic mail at andrew@bindlecoffee.com
Steven Sorenson with Bellisimo Inc, via electronic mail at ssorensen@bellisiominc.com