HomeMy WebLinkAbout2302 Nancy Gray Ave - Special Inspections/Engineering - 02/23/2012ri= T2 Structural
Engineering LLC
1329 East Seventh Street, Loveland, Colorado 80537
Office, (970) 663-6016, Fax, (970) 622-9324
February 23, 2012
Jamestown Builders, LLC
3003 East Harmony Road, 4th Floor
Fort Collins, CO 80528
Foundation Reinforcement Observation
Lot 11, Block 20, Sidehill Subdivisoin
2302 Nancy Gray Avenue
Fort Collins, Colorado
Project Number: 11-107-32
Dear Mr. Everitt:
B7111 3a-?-
// /I a 8'
Today, a representative of this office visited the site referenced above to observe the foundation
wall reinforcement size, and location and to confirm the vertical reinforcement spacing in
foundation forms for both the house and the detached garage. The reinforcement appeared to be
in general compliance with the foundation drawing and details by T2 Structural Engineering,
project number: 11-003, dated February 9, 2011.
There were two Ufer bars, one on each side of the foundation. The east Ufer bar was located
approximately three feet towards the north from the front foundation wall. The west Ufer bar
was located approximately three feet towards the north from the front basement foundation wall.
There was a Ufer bar in the south garage wall. The Ufer bars were lapped and tied to the
continuous bottom row of reinforcing steel.
Protect freshly placed concrete from temperatures that will compromise the design strength of
the concrete. Concrete placement and reinforcement is to be installed in,accordance with ACI
31.8 and the 2006 IRC.
Please contact this office if there are questions, or additional information that is required. Thank
you for the opportunity to work with you on this project.
Sincerely,
Susan Tagg, P.E:
Enclosures
�1�•p° Ue�
cr
'"343
'FEB 2 3 701Y
T-2 Structural
Engineering LLc
1329 Fast Seventh Street, Loveland, Colorado 80537
Office. (970) 663-6016, Fax. (970) 622-9324
February 22, 2012
Jamestown Builders, LLC
3003 East Harmony Road, 4th Floor
Fort Collins, CO 80528
Footing Observation
Lot 11, Block 20, Sidehill Subdivision
2302 Nancy Gray Avenue
Fort Collins, Colorado
Project Number: 11-107-31
Dear Mr. Everitt:
On February 21, 2012, a representative of this office visited the site referenced above to observe
the footing form widths, depths, and reinforcement. The continuous and isolated footing widths
and depths were in general compliance with the foundation drawing by T2 Structural
Engineering, project number: 11-107, dated December 15, 2011. The reinforcement for the
interior pads was ready, to be placed in the footing forms. The dowel reinforcement was on site
and the spacing will be confirmed with the foundation wall observation.
Protect freshly placed concrete from temperatures that will compromise the design strength of
the concrete. Concrete placement and reinforcement is to be installed in accordance with ACI
318 and 2006 IRC.
Please contact this office if there are questions, or if additional information is required. Thank
you for the opportunity to work with you on this project..
Sincerely, L1,0,,c
0343
Susan Tagg, P. t'' ^ts' ,FR 2 2 Ml?
N
Enclosures "aStp�
2 Structural
Engineering LLc
1329 Fast Seventh Street. Loveland. Colorado 80537
Office, (970) 663-6016. Fax, (970) 622-9324
May 3, 2012
Jamestown Builders, LLC
3003 East Harmony Road, 41h Floor
Fort Collins, CO 80528
Perimeter Drain and Damp -proofing Verification
The Truman
Lot 11, Block 20, Sidehill Subdivision
2302 Nancy Gray Avenue
Fort Collins, Colorado
Project Number: 11-107-32
Dear Mr. Everitt:
It has come to the attention of this office that at the site referenced above we did not get an opportunity to
observe the perimeter drain and the damp -proofing of the exterior foundation walls that retain earth and
enclose habitable or usable spaces located below grade. Based on the letters sent to us for this address
and the previous experience with your work history, it is the opinion of this office that the perforated pipe
was bedded in gravel, with building paper over the pipe. There is a sump pump was located on the
interior side of the foundation walls. The exterior perimeter drain pipe should drain towards and be
connected to the subdivision storm drain.
It is out opinion that the damp -proofing adequately covers the foundation walls. The damp -proofing
application is used to help reduce moisture that can permeate through the foundation wall. Damp -
proofing is effective in the absence of hydrostatic pressure and cracks in the foundation. It is important to
keep vegetation that requires watering out of the backfill area of the foundation excavation.
Please contact this office if there are questions, or additional information that is required. Thank you for
the opportunity to work with you on this project.
Sincerely,
Russell T. Zoetewey, E.I.T.
F
Susan Tagg, P.E. r'.:
:' = 40343
Enclosures IV, ^ '
' 14AY 03 20A� 44
5804 Puna Drive
Loveland, CO 80538
P: 970-218-4020
www.residentialdampproofing.com
com
Date: 5/1/2012
Reg.: Verification of work completed by Residential Damp -Proofing, LLC
To whom it may concern,
This letter is to verify that Residential Damp -Proofing LLC installed the exterior foundation
dampproofing at 2302 Nancy Gray Ave. in Ft. Collins on 03/30/2012.
All work by Residential Damp -Proofing, LLC at this address is finished and complete; and has been done
according to the manufacturers specifications.
If you have any more questions or concerns, please contact us at the address or phone number
listed above.
Thank You,
Rod Griess, manager
rdp@skybeam.com
�j
• � � � •
BEDROCK:��
. .
• . . • • SLINGERS
6564 N. County Rd. 11 C
Loveland, CO 80538
Dispatch 970.817.0909 Fax 970.622.9755
www.bedrockslingers.com
Dear James,
This letter is to inform you that we installed a drain(4" socktile, rock, and fabric) with slope to an underdrain
and installed a sump pit on the inside with a small stub coming out from it for the following addresses:
2126 Nancy Grey
Fort Collins, CO
Sidehill Subdivision
2302 Nancy Grey
Fort Collins, CO
Sidehill Subdivision
Let us know if you have any questions.
Thanks,
Jordan Kamps, President
r