HomeMy WebLinkAbout2126 Nancy Gray Ave - Special Inspections/Engineering - 02/22/2012T2 Structural
Engineering LLc
February 22, 2012 1329 Fast Seventh Street, Loveland, Colorado 80537
Office. (970) 663-6016. Fax, (970) 622-9324
Jamestown Builders, LLC
3003 East Harmony Road, 4th Floor
Fort Collins, CO 80528
Foundation Reinforcement Observation
Lot 10, Block 9, Sidehill Subdivisoin
2126 Nancy Gray Avenue
Fort Collins, Colorado
Project Number: 11-108-32
Dear Mr. Everitt:
Today, a representative of this office visited the site referenced above to observe the foundation
wall reinforcement size, and location and to confirm the vertical reinforcement spacing in .
foundation forms for both the house and the detached garage. The reinforcement appeared to be
in general compliance with the foundation drawing and details by T2 Structural Engineering,
project number: 11-003, dated February 9, 2011.
There were two Ufer bars, one on each side of the foundation. The east Ufer bar was located
approximately two feet towards the north from the front foundation wall. The west Ufer bar was
located approximately two feet towards the north from the front basement foundation wall.
There was a Lifer bar in the garage. The Ufer bars were lapped and tied to the continuous bottom
row of reinforcing steel.
Protect freshly placed concrete from temperatures that will compromise the design strength of
the concrete. Concrete placement and reinforcement is to be installed in accordance with ACI
318 and the 2006 IRC.
Please contact this office if there are questions, or additional information that is required. Thank
you for the opportunity to work with you on this project.
Sincerely,
Russell T. Zoetewey, E.I.Ta,,
Susan Tagg, P.E.?--
40343
Enclosures � �,'•FEB 2 2 1UR '04-