HomeMy WebLinkAbout1669 Sprocket Dr - Disclosures/Mechanical - 07/15/2014City of Fort Collins Residential Mechanical Systems Performance Report Updated 3/1/2014
This form is a record of testing targets and results, with Pass/Fail outcomes. For information on measurement tools and testing techniques, see the
"Residential New Construction Mechanical Systems Testing Guide." The guide and this form may be periodically updated; check the Building
Services web site for the current version.
This form must be completed and signed by an "Approved Agency," and submitted to Building Services as a requirement for receiving a C.O.
Color
key
Measured value
Tar et
g
to compare with
Pass
Fail
Caution
Other
or limit
data
target or limit
ADCF = Air Density Correction Factor, based on tool,
ADCF altitude (5000'), air temperature through tool
Volumetric flow (CFM 5000') = ADCF x Indicated flow (CFM)
Address 1669 Sprocket Dr Date of "Residential
Mechanical Systems
Builder Cross creek builders Design Submittal"10-2-13
information referenced
HVACcontractor Academy heating and cooling inc by testing technicians
As -built changes vs
Relocate Furnace in Basement to area 10 from Original
mech design submittal De s i gn
Testingdate(s) 1 7-15-14
Bath exhaust
Testing tech (initials) GJ
Flow X Flow box _ Pilot tube duct traverse Air temp
ADCF
tool[— Passive flow hood _ Other (note below) through tool (F) 7 4
Measured Airflow
Design
Minimum Airflow Requirement
Indicated
Volumetric
Exhaust Pickup Location
Airflow
(CFM 5000')
Flow
Flow
Pass
Fail
(CFM
+ Type of 0
YP Operation
P
CFM
(CFM)
(CFM 5000')
5000')
Bath 1
65
_50Intermittent X20Continuous
72'
78
X-
❑,
Bath 2
64
X 50Intermittent—20Continuous
64
IX
❑`
Mater Bath
X 50Intermittent _20Continuous
64
XI
,❑
Master Toilet
X 50Intermittent—20Continuous
47
X
_ 50 Intermittent _20 Continuous
X I
❑s.
50Intermittent—20Continuous
❑
50Intermittent—20Continuous
❑
:,',❑
Testing
notes
Kitchen exhaust N/A - hood does not vent to outside El Testing tech (initials) FGJ
Oven fuel _Gas X Electric Minimum airflow requirement (CFM 5000') + operation[ X 100 Intermittent 25 Continuous
Measured airflow
Flow X Flow box — Pitot tube traverse Tool —Interior grille Air temp
Passive flow hood _ Flow grid Exhaust duct through ADCF
tool _Powered flow hood _Other (note below) location (Exterior termination not OK)
tool (F)174
Indicated flow 130 CFM Volumetric flow CFM 5000' L Pass Il 7 Fail
Testing
notes
Residential Mechanical Design Submittal V20140301 Page 1
r
Systems other than sub -structural floor exhaust
Cod ( minimum ventilation airflow CFM 5000' Design ventilationCFM 5000'
based on CFA and # of BR airflow
Target ventilation airflow range to CFM 5000'
(code -minimum) (120 % of design Flow)
Testing tech (initials)
System —Exhaust-only
_Supply -only
type Balanced
Measured Airflow
Air Temp
Indicated
Volumetric
Measurement Method
Tool Location
Through
ADCF
Flow
Flow
Pass
Fail
Tool (F)
(CFM)
(CFM 5000')
Total
_ N/A _ Passive flow hood
exhaust
— Flow box _ Pitol tube traverse
❑
airflow
Flow collar _ Other (note below)
Total
_ N/A _ Passive flow hood
supply
— Flow box _ Pilot tube traverse
❑
airflow,
Flow collar _ Other (note below)
When supply airflow is circulated by air handler fan, fan speed for measurement
_ Heating — Cooling — Continuous fan
Balanced airflow in balanced systems
Average of measured CFM Target flow range CFM �I
supply + exhaust flows 5000, (average +/- 15%) to 5000' ❑Pass )', Fail
Sub -structural floor exhaust ❑ N/A -- no sub -structural floor exhaust system Testing tech (initials)
Design exhaust airflow (based on CFM 5000' Target airflow, limits to CFM 5000'
approved design) (design +/- 15%)
Measured airflow
Flow
to,
—Flow box
— Passive flow hood
— Pitot tube traverse
— Flow collar
Tool
location
Air temp
through ADCF
— Powered flow hood
_ Other (note below)
tool (F)
Indicated flow
CFM
Volumetric flow
CFM 5000' ❑ Pass L Fail
J
N/A — No ductwork Testing notes
No ductwork outside conditioned space (incl multiple sys)
FTesting tech (initials):
Duct leakage _Energy rater (name,
data source I company, testing date):
House conditioned floor marea eat) f Air temp ADCF
�
(include full basement) through tool (F)
Residential Mechanical Design Submittal V20140301
Page 2
J
For multiple systems, attach one page per system
System #) Which parts of house does it serve? Whole HOU Se
Installed equipment (Be clear about which AC components are installed at time of testing) Testing tech (initials) g]
St
Furnace or Boiler
AC or Heat Pump Condenser
AC or Heat Pump Coil
Manufacturer
Heil
Model #
N9m8b0601716B1
X Basic fiberglass _ Electrostatic
Filter Type Basic pleated _Other: Thickness MERV❑
brand KOCh High-effic pleated (inches) (optional)
atic pressures
Setup
Speed: _ Heating _ Cooling X Cont. fan
High -stage for multi -stage equipment
Blower speed tap: Black
Humidifier damper: X N/A
Open (Heating)
_ Closed (Cooling)
X _ All registers open
Zone dampers open
sP1 155
AP Filter 2 9
(SP1 - SP2)
Cooling: Measured air flow through Indoor coil
Design cooling airflow CFM 5000'
(h)igh stage)
[I
SP2 4 5
Testing tech (initials) CJ]
(Same location
• SP4 . 13 for NSOP,
TFSOP)
AP Coil
(SP3-SP4) NA
• SP3 Dj0 C011
AP Total ESP . 5 8
(SP3-SP2)
Px N/A -- no AC installed Testing tech (initials) F9J
Target airflow limits to CFM 5000'
(design +/- 15%)
Measured airflow
Flow grid
platesze
14
20
Air temp
ADCFNSOP❑
TFSOP❑ Correctistance
on Factor
_
t000u(gF)❑
Measured airflow, no
adjustment/correction
CFM
Indicated
FRGF�CFM
Volumetric airflowCFMPass
5000'
x
Measured AF x FRCF
x
Indicated AF x ADCF
❑I Fdll
Heating: Gas manifold pressure (high stage) Testing tech (initials) gC_
Manifotd Iwc Iwc g pressure limits (spec +/- 5%) pressure 3, 6 IWc Target manifold P Measured [x lass
p 3.3 to 3 , 67
OEM spec @ 5000' 3 , 5 0 Fail
Heating: Temperature rise Testing tech (initials)
OEM temperature rise limits ""
(high stage) 4 0 to i7 0 F
Measured temps (F): Supply 12 5 _ Return 7 4 Temp cJ 1 [X Pass 7 Fail Caution: within 1 OF
air air — rise � .:_I E:of top of range
Residential Mechanical Design Submittal
V20140301
Page 3
Testing tech (initials)
Testing approach and targets
❑ N/A: No complete AC system I N/A: House completed November - April (installing contractor responsible for testing in warm weather)
❑ TXV: Subcooling + SH check ❑ Non-TXV: Superheat ❑ OEM -specific: Approach ❑ Other OEM -specific (documentation required)
Target Target
et
F: entering air wet -bulb temp perheat subcooling approachTargetTemperatures Condenser Non-TXV: Return
Subcooling
Discharge pressure
Condenser❑ LiquiP❑ Actual
ctuagl❑ ❑ TXV Pass: Actual SC within +/-
ressure saturation T F line F subcoolin F 3 F of target SC, 2 F min
PSI (5000' than) temp (Good 7 - li line T) QTXV Fail
Superheat
Suction
ratorSuction
-1
Actual❑
Non-TXV Pass: Actual SH
pressure
F-]Ev=
son T❑F
nn
superheat❑F
wthin +/- 5 F of target SH
(PSI)
(5000'chart)
temp
(suctline7-evapT)
Non-TXV Fail
TXV checks: ❑ Pass: Field -installed TXV installed in accordance with OEM instructions QICaution: Actual SH outside mfgr range
Approach
Liquid Imp Actual condenser
EAT)
F-IF ❑ Approach Pass: Actual approach within +/- 1 F of target approach
temp (Liq line T -condenser EAT) I❑ Approach Fail
Register air flows Testing tech (initials) Egj
All registers are cut through finish materials and moving air L Pass 10 Fail
(Remainder of register air flow section under development, not yet being enforced)
2nd floor delted regiter above landing and increased duct and
register at top of stairs
Pressure balance
Testing tech (initials)
Room
Room -to -Core
Measured
(match names on plans, include
Pressure Drop
Pressure
Pass
Fail
basement if there is a door)
Target Range (Pa)
Drop (Pa)
Master Bdr
-3to+3
.9
xl
Bdr 2
-3to+3
-1.8
x1
❑'':
Bdr 3
-3to+3
0
x
;:;,E]
office
-3to+3
0
x
-3 to +3
❑
JAG
-3 to +3
❑
kp:
-3 to +3
❑
; _❑
-3 to +3
❑
; D,r
-3 to +3
❑
-3 to +3
❑
_❑
Residential Mechanical Design Submittal V20140301 Page 4
X Combustion safety testing N/A -- no natural -draft combustion appliances
(Appliance Types table must be completed for every home)
Appliance types
Testing tech (initials)
Appliance
Combustion
pe
N/A
Draft -hood
Natural-drafl
Induced -draft
Natural -draft
Power-
vent
Direct-
vent
Powered sealed-
combustion
Electric
Furnace #1
❑
❑
❑
❑
❑
❑
❑
Furnace #2
❑
❑
❑
❑
❑
❑
❑
Boiler #1
❑
❑
❑
❑
❑
❑
❑
Boiler #2
❑
❑
❑
❑
❑
❑
❑
Water heater #1
❑
❑
❑
❑
❑
❑
❑
Water heater #2
❑
❑
❑
❑
❑
❑
❑
Fireplace #1
❑
❑
❑
❑
❑
❑
❑
Fireplace #2-
❑
❑
❑
❑
❑
❑
❑
Other:
❑
❑
❑
❑
❑
❑
❑
Worst -case depressurization performance
are
# of bath fans on
_ Vented range hood on
Clothes dryer on
Air handler on
Other fans on
Outdoor temperature = F
CAZ pressure
BPI depressurization limit
(Pa wrt outside)
Measured net CAZ depressurization
(Pa wrt outside)
OK (less negative) I Caution (more negative)
Spillage
BPI maximum limit
(seconds
Measured spillage duration
(seconds
Pass = duration not exceeding limit
Draft pressure
BPI limit
(Pa wrt CAZ
Measured
(Pa wrt CAZ
Pass = pressure more negative than limit
CO concentration in undiluted flue gas
BPI maximum limit
(ppm
Measured CO
(ppm
Pass = CO level not exceeding limit
Caution = CO level 25 to 100 ppm
Testing
notes
❑ OK ❑ Caution ❑ OK I ❑ I Caution ❑ OK I ❑ I Caution
60
60
60
❑
jPass I ❑ I Fail
❑
IPass 1 ❑-; Fail
❑
IPass
I ❑
IFail
❑ Pass I ❑. Fail ❑ Pass I ❑,`. Fail ❑ Pass ''❑ Fail
100
100
100
❑
Pass '.❑ I Fail
❑
Pass
I ❑.:
Fail
❑
Pass I ❑a Fail
❑
Caution
❑
Caution
❑
Caution
Residential Mechanical Design Submittal
V20140301 Page 5
System
Controls Operating
Per Design Intent
Local exhaust (all fans)
El
N/A
[IPass
�'❑
a
Fail
Whole -house ventilation
❑
N/A
ElPass
®"Fail
..a...,..;:.
Sub -structural floor exhaust
❑
N/A
❑
Pass
Fail
,s
Heating (all systems)
El
N/A
El
Pass
"�❑
Fail
n� W
Cooling (all systems)
El
N/A
El
Pass
�� %
Fail
Signatures
Testing tech (initials)
Testing Notes
Technician #1 performing inspection and testing documented on this report (Approved Agency)
1 certify that the tests referenced above, in sections bearing my initials, were performed in accordance with protocols specified by the
City of Fort Collins Building Services Department, and that the reported results are accurate to the best of my knowledge.
I
Name (print) Gary Jurgensmeier
i
Title Owner
)
Company Academy Heating and Cooling
Signature and Date 7 —17 —14
Technician #2 performing inspection nd t ing documented on this report (Approved Agency)
I certify that the tests referenced above, in sections bearing my initials, were performed in accordance with protocols specified by the
City of Fort Collins Building Services Department, and that the reported results are accurate to the best of my knowledge.
Na
Signature
HVAC Contractor (City of Fort Collins license holder)
I certify that I have reviewed this report and that the test results are an accurate representation of the performance of the installed mechanical
systems.
Name (print) Gary Jurgensmeier
Title Owner
E Company Academy heating and cooling inc
j Signature and Date 7 —17 —14
oro�
Residential Mechanical Design Submittal V20140301 Page 6