September 16, 2009
Jamestown Builders LLC
3003 East Harmony Road, 4th Floor
Fort Collins, CO 80528
Foundation Reinforcement Observation at the House and Detached Garage
Lot 23, Block 293, West Addition
830 Maple Street
Fort Collins, Colorado
Project Number 09-014-011-32
Dear Mr Everitt
On September 15 2009 this office visited the site referenced above to observe the foundation
wall reinforcement size, and location and to confirm the dowel spacing in foundation forms at
the house and detached garage The reinforcement appeared to be in general compliance with
the foundation drawing and details by T2 Structural Engineering, project number 09-14-011,
dated June 24, 2009
There were three Ufer bars The Ufer bar on the detach garage was on the east wall
approximately fourteen feet towards the south of the front garage wall The other two Ufer bars
were located on the east full height foundation wall on the house One Ufer bar was
approximately five feet towards the south of the northern wall and the other Uffer bar was
approximately four feet towards the north of the southern wall The Ufer bars were lapped and
tied to the continuous bottom row of reinforcing steel
Protect freshly placed concrete from temperatures that will compromise the design strength of
the concrete Concrete placement and reinforcement is to be installed in accordance with ACI
318 and the 2006 IRC
Please contact this office if there are questions, or additional information that is required Thank
you for the opportunity to work with you on this project
Sincerely, ospn0 VCF�
Susan Tagg, P E €P 1 6 2— a
0
Enclosures t��'S10"vAt.�'°
_- `' ' s
.� t.� �,•, _ ..
'L �'. �F
��
Y
e
T2Structural
Engineering
1329 Fast Seventh Street Loveland Coloiado 80937
Office (970) 663 6016 Fax (970) 622 9924
September 14, 2009
Jamestown Builders, LLC
3003 East Harmony Road, 4th Floor
Fort Collins CO 80528
Footing Observation at the House and Detached Garage
Lot 23, Block 293, West Addition
830 Maple Street
Fort Collins, Colorado
Project Number 09 014 011-31
Dear Mr Everitt
On September 11, 2009 this office visited the site referenced above to observe the footing form
widths, depths, and reinforcement at the house and the detached garage The continuous and
isolated footing widths and depths were in general compliance with the foundation drawing by
T2 Structural Engineering, project number 09-14 011, dated June 24 2009 The reinforcement
for the interior pad was tied and ready to be placed in the footing The dowel reinforcement was
on site and the spacing will be confirmed with the foundation wall observation
Protect freshly placed concrete from temperatures that will compromise the design strength of
the concrete Concrete placement and reinforcement is to be installed in accordance with ACI
318 and 2006 IRC
Please contact this office if there are questions or additional information that is required Thank
you for the opportunity to work with you on this project
Sincerely, pp G
Susan Ta P 40343
gg' —,' P 1 4 200
Enclosures �u'�1VAL
No Text
2Structural
Engineering
1 129 Fast Seventh Sheet Loveland Colorado 80F37
Office (970) 663 6016 Fax O70) 622 9324
September 25, 2009
Jamestown Builders, LLC
3003 East Harmony Road, 41h Floor
Fort Collins CO 80528
Perimeter Dram and Damp -proofing Observation
Lot 23, Block 293, West Addition
830 Maple Street
Fort Collins Colorado
Project Number 09-014 011-33
Dear Mr Everitt
On September 24, 2009 this office visited the site referenced above to observe the perimeter
drain and the damp -proofing of the exterior foundation walls that retain earth and enclose
habitable or usable spaces located below grade and the damp -proofing for the detached garage
The perforated pipe was bedded in gravel, with building paper over the pipe A sump pump was
located on the interior side of the foundation walls The exterior perimeter dram pipe should
dram towards and be connected to the subdivision under dram
The damp -proofing appeared to adequately cover the foundation walls The damp proofing
application is used to help reduce moisture that can permeate through the foundation wall
Damp -proofing is effective in the absence of hydrostatic pressure and cracks in the foundation
It is important to keep vegetation that requires watering out of the backfill area of the foundation
excavation
Please contact this office if there are questions, or additional information that is required Thank
you for the opportunity to work with you on this project