Loading...
HomeMy WebLinkAbout417 W Magnolia St - Special Inspections/Engineering - 03/03/2004Mar,30, 2004 8:58PM ALLER LINGLE ARCH No.6021 P- 2/2 Memo Ta Shaun Moscrip rnwm Michael P. Welenc CQ Pile Dato 3/30/2004 Ro Lincoln Center HVAC Project `{ir7 0. MaSrtc I, (k SX 44 Shaun: 4 I I t A-C Pe (4 C e " P ri--& I conducted a final construction observation visit at the Lincoln Center and had access to the areas where electrical work took place. The electrical installation followed the Construction documents very closely. All the materials were installed per the construction documents. The work was accomplished in a neat and workmanlike manner. I recorded no items that would require the further attention of the electrical contractor. Michael Welenc Project Manager Electrical Systems Consultants, Inc. • Page 1