HomeMy WebLinkAbout7439 Stonington Ct - Special Inspections/Engineering - 08/13/2003August 13, 2003
Melody Homes
11031 Sheridan Blvd.
Westminster, Colorado 80020
Attn: Mr. John Johnson
80307708
Re: Geotechnical Engineering Report
Ridgewood Hills 3rd Filing — Phase 8, Lot 291
7439 Stonington Court
Fort Collins, Colorado
Terracon Project No. 20005162
Irerracon
301 N. Howes P.O. Box 503
Fort Collins, Colorado 80521-0503
(970) 484-0359 Fax: (970) 484-0454
Terracon has completed a geotechnical engineering exploration for a proposed single family residence to be
located on the above referenced lot within the Ridgewood Hills 3rd Filing — Phase 8 residential development
project located in south Fort Collins, Colorado. The purpose of these services is to provide geotechnical-
engineering recommendations for design of foundations, slab on grade, and perimeter drainage systems.
Terracon performed a geotechnical engineering exploration for the 3rd Filing of Ridgewood Hills in October of
1997, which encompassed the above -referenced lot. For further information and additional geotechnical
engineering recommendations please refer to our "Geotechnical Engineering Report' for the Ridgewood Hills
3rd Filing Residential Development revised January 16, 2001, Project No. 20975149.
Terracon also performed a project specific geotechnical engineering subsurface exploration for the lots in
which blasting operations were performed to accommodate the ease for basement excavations for areas of
the site where very well cemented sandstone lenses were encountered. For further information and findings
thereof, please refer to our "Geotechnical Engineering Report — Ridgewood Hills 3rd Filing — Phases 5
through 8, Blasted Lots to Accommodate Basement Construction" dated June 5, 2003, Project No.
20005162.
We understand a blasting operation was conducted on this particular lot due to the relatively shallow depth to
the very well cemented sandstone bedrock formation. The blasting program was completed by Yenter of
Denver, Colorado to facilitate the ease for basement foundation excavation. We understand the blasted
zone extended to approximate depths of 8-feet below finished site grades. The blasted materials were then
over -excavated to the bottom of the blasted zone. The blasted template footprint was then backfifled with the
over -excavated materials.
FIELD EXPLORATIONS
The additional site exploration for this lot was conducted on July 10, 2003, which consisted of drilling one
test boring drilled near the central portion of the lot as requested. The purpose of the drilling activities was
to evaluate the subsurface soils and/or blasted zone of replaced sandstone bedrock materials and to
provide appropriate foundation design criteria for the lot. A Log of Boring describing the soil, bedrock and
groundwater profile conditions, along with the laboratory test results, are attached with this letter. The
materials analyzed for the above mentioned lot, based on the laboratory field and test results, are
generally classified as being low swelling according to the Colorado Association of Geotechnical
Engineers (CAGE) criteria.
Arizona ■ Arkansas ■ Colorado ■ Georgia ■ Idaho ■ Illinois ■ Iowa ■ Kansas ■ Kentucky ■ Minnesota ■ Missouri
Montana ■ Nebraska ■ Nevada ■ New Mexico ■ Oklahoma ■ Tennessee ■ Texas ■ Utah ■ Wisconsin ■ Wyoming
Quality Engineering Since 1965
Geotechnical Engineering Report — Melody Homes
Ridgewood Hills 3`d Filing
Fort Collins, Colorado
Page 2
Project No. 20005162
Terracon
The subsurface soils encountered on this lot generally consisted of approximately 13-feet of fill material
which was derived from the blasting operations, underlain by undisturbed sandstone bedrock at
approximate depths of 5-feet below site grades and extending to the depths explored, approximately 19-
feet.
It is our understanding the proposed residence will be constructed having a full depth basement. Therefore,
based on the properties of the soils/fill materials and cemented characteristics of bedrock present on this lot,
Terracon recommends the proposed structure be supported by conventional type spread footings, (Type B)
designed in accordance with the recommendation contained in the "project -specific' blasted lot geotechnical
engineering report.
Foundation Systems — Conventional Type Spread Footings
To reduce the potential for differential movement and to increase the structural integrity of the bearing
stratum within the blasted zone, we recommend overexcavating within the blasted template a minimum of 2-
feet beneath all foundations and slabs, and replace the materials as engineered controlled fill within this
zone. The controlled engineered fill material should extend laterally beyond the edges of all exterior footings
an additional distance of 12-inches for every 12-inches of depth. If engineered fill is placed beneath the
entire footprint, it should extend horizontally a minimum distance of 5-feet beyond the outside edge of
perimeter footings. Terracon recommends the 2-foot of over -excavated blasted sandstone materials beneath
all footings be stockpiled for re -use. The underlying subgrade layer beneath the removed section should be
scarified a minimum of 12-inches, moisture conditioned and recompacted to a minimum of 98-percent of
Standard Proctor Density ASTM D698. The over -excavated material should then be moisture conditioned to
plus or minus 2 percent of optimum moisture content, placed in uniform 8 to 12-inch lifts and mechanically
compacted to a minimum of 98-percent of Standard Proctor Density ASTM D698. A general schematic of
the over -excavated and replaced foundation -bearing stratum for use of conventional -type spread footings is
enclosed for your review.
Spread footings bearing upon a minimum of 2-feet of controlled engineered fill may be designed for a net
allowable bearing pressure of 2,500 psf. For this alternative, the footings should be sized to maintain a
minimum dead load pressure of 750 psf. The minimum of 2-feet of structural fill material placed beneath the
entire building footprint should create a more uniform bearing stratum and minimize the potential for
differential movement.
Footings should be proportioned to reduce differential foundation movement. Proportioning on the basis of
equal total movement is recommended; however, proportioning to relative constant dead -load pressure will
also reduce differential movement between adjacent footings. Total settlement resulting from the assumed
structural loads is estimated to be on the order of 1-inch or less assuming that the "blasted -zone" beneath the
2-foot replacement sections to the undisturbed sandstone is relatively consistent. Movement could exceed 1-
inch if water from any source infiltrates the foundation soils; therefore, proper drainage should be provided in
the final design and during construction.
Geotechnical Engineering Report — Melody Homes
Ridgewood Hills Td Filing
Fort Collins, Colorado
Page 3
Project No. 20005162
Terracon
Exterior footings should be placed a minimum of 30 inches below finished grade for frost protection and to
provide confinement for the bearing soils. Finished grade is the lowest adjacent grade for perimeter footings.
Basement Construction
Groundwater was not encountered on the lot to the maximum depths of exploration, 15-feet, during the
initial site exploration. Therefore full -depth basement construction is considered acceptable. To reduce
the potential for groundwater and/or surface water infiltration to enter the basement of the residence,
installation of a dewatering system is recommended. The drainage system should be constructed around
the exterior perimeter of the basement foundation, and sloped at a minimum 1/8 inch per foot to a suitable
outlet, such as a sump and pump system.
The drainage system should consist of a 4-inch diameter perforated pipe, embedded in free -draining
gravel, placed in a trench at least 12-inches in width. Gravel should extend a minimum of 3-inches
beneath the bottom of the pipe, and at least 1-foot above the bottom of the foundation wall. The gravel
should be covered with drainage fabric prior to placement of foundation backfill.
Backfill placed around the outside perimeter of the structure should be placed in uniform lifts; moisture
conditioned to optimum moisture content and mechanically compacted to 95% of Standard Proctor
Density ASTM 698, after the walls have been laterally braced.
Floor Slab Design and Construction
The variability of the existing soils at approximate slab subgrade elevation could result in differential
movement of floor slab -on -grade should the clay soils increase in moisture content. Based on the CAGE
criteria, the subsoils at the site have a slab performance risk category of 'low". Movement not likely to
exceed up to 2-inches or more is estimated if the subsoils below slabs become wetted for a zone of
approximately 10-feet below the basement. Slab -on -grade construction for the basement of this residence
should perform in accordance with the above criteria. The homeowner should be aware of the risk of this
slab movement and should take this into account prior to purchasing the residence. To reduce potential
slab movements, slabs should be constructed in accordance with the recommendations of the
Geotechnical Engineering Report.
Surface Drainage
Positive drainage should be provided during construction and maintained throughout the life of the
proposed residence. In areas where sidewalks or paving do not immediately adjoin the structure, we
recommend that protective slopes be provided with a minimum grade of approximately 10 percent for at
least 10-feet from perimeter walls. Backfill against foundations, exterior walls and in utility and sprinkler
line trenches should be well compacted and free of all construction debris to reduce the possibility of
moisture infiltration. Downspouts, roof drains or scuppers should discharge into splash blocks or
Geotechnical Engineering Report — Melody Homes
Ridgewood Hills 3`d Filing
Fort Collins, Colorado
Page 4
Project No. 20005162
Terracon
extensions when the ground surface beneath such features is not protected by exterior slabs or paving.
Sprinkler systems should not be installed within 5-feet of foundation walls.
Construction Observation
The following observations are recommended during construction:
• Foundation Excavation;
• Footing sizes and void form placement;
• Foundation Wall Steel/Reinforcement;
• Perimeter Drainage System; and
• Floor Slab for Basement and Garage
We appreciate the opportunity to be of service to you on this phase of your project. If you have any
questions, or if we may be of further service to you, please feel free to contact us.
Sincerely,tP�p
TERRACON off.;.....
277'
David A. Richer ss••••••°•°°G�'`
Geotechnical Engin t Manager
Copies to: Addressee (6)
Enclosures: Log of Boring (1)
LOG OF BORING NO. 291 Page 1 of 1
CLIENT
ARCHITECT/ENGINEER
Melody Homes
SITE Ridgewood Hills-3rd Filing
PROJECT
Fort Collins, Colorado
Ridgewood Hills-3rd Filing
SAMPLES
TESTS
o
W n
DESCRIPTION
O
F
r
1:
x
w
1
Ztn
KW
Z
LL
ZZ
CL
to
m
W
O
K
0
p
7
Z
F
K
ym
Qp
�0
�
Co.
Z�
Ito
FILL MATERIAL
Silty Clayey Sand with Sandstone Bedrock
Fragments
Tan, brown, moist, loose to medium dense
SS
12
4
5
SS
12
30
10
13
SILTSTONE/SANDSTONE
::
14.2 Tan, gray, moist, cemented to well
cemented
BOTTOM OF BORING
s
's
s
i
The stratification lines represent the approximate boundary lines
between soil and rock types: in -situ, the transition may be gradual.
WATER LEVEL OBSERVATIONS, ft
BORING STARTED 7-10-03
DRY WD
COMPLETED 7 -10-03
WL
T
Y
Ir �rr acon
-
-
R GRING
CME 75FFOREMAN
CMG
s WL
I INITIAL WATER LEVEL READING
APPROVED DAR I
JOB # 20005162