HomeMy WebLinkAbout620 Ebon Pica St - Special Inspections/Engineering - 07/02/2009Perimeter Drain / Assurance Observation Per the client's request, a representative of CTL has visually observed the perimeter drain t the site referenced above. The following summarizes our observations and opinions at the time of our visit. Client: Artcitar/ beyd ooQ,,meA4 Site Address: Fc,r4- W(!`i s, W Foyt �oilins, co Job. #: O /.eo. Lot: 33-37 Block: Filing: Date: G/2y 09 Contact: R 4ss - W611S Subdivision: Ravch V � 5u Protect Specifications Foundation Plan By: GTL Tlto. n Date J7/��� Job# SFD1396.> Geotechnical Report By: FCC Date 9-3o-oH Job# 04'01---W Recommended Drain type? 10 Exterior perimeter ❑ Interior ❑ other Observations Perimeter drain observed around: YBasement ❑ Crawlspace ❑ Other: Where does the perimeter drain discharge? ❑ Daylight W Sump pit ❑ Subdivision drain Dampproofing observed around: 0 Basement ❑ Crawlspace ❑ All backfill areas Comments A Ae 1i a, tr n6ief�4afcna �2hc11 in�as �A(u I a 114 y " Ier plbc wes i , p AC, , C�r-wr ctn� kw ri` In/dPl. Nni' on Si��, 1 � ShtGi-,fi,(' circ�n Gfw:l�eas I' b - ld ti l I ' N�-� .�.� :Indicates approxima a diamhocadon N Summary of Opinions It is our opinion that the foundation drain mtd}er daR4pp;oo€i-xg observed generally conform with the project referenced above. ❑ It is our opinion that the foundation drain and/or dampproofing observed differs significantly from the project specifications (2°d observation required). Corrective Action: Field Jeepresentative ate a.PpO UCF�. By CTL I Thompson, Inc. 1 351 Linden Street, Suite 140, Ft. Collins, CO 80524 / Dampproofing Quality Assurance Observation Per the client's request, a representative of CTL has visually observed the perimeter drain and/or dampproofing at the site referenced above. The following summarizes our observations and opinions at the time of our visit. Client: Job #: S�o�3�L.oati Date: Contact: /"s "// Proiect Specifications Foundation Plan By: G?Z ?�o..Oso•', Date cajAs/og Job# sFo�3�s,o� Geotechnical Report By: A4 �1 Date Job# .2y7 Recommended Drain type?,�V ❑ Exterior perimeter ❑ Interior ❑ other Observations Perimeter drain observed around: JA ❑ Basement (I Crawlspace ❑ Other: Where does the perimeter drain discharge? /%/f ❑ Daylight ❑ Sump pit ❑ Subdivision drain Dampproofing observed around: )(Basement ❑ Crawlspace ❑ All backfill areas Comments CTL I THOMPSON Site Address: 6.2o- g Viz+ Lot: 3a-s7Block: — Filing: Subdivision: /Z,,e. U... Summary of Opinions It is our opinion that the dampproofing observed generally conform with the project referenced above. ❑ It is our opinion that the dampproofing observed differs significantly from the project specifications (2nd observation required). Corrective Action: .40V,L' Field Representative Date b{ p N0� VV vr o Re ' w c Date C? CTL I Thompson, Inc. 1 1103 Old Town Lane, Suite 82009 Drilled Pier Ouality Assurance Observation Per the client's request, a representative of CTL has visually observed the drilling of the piers at the site referenced below. The following summarizes our observations and opinions at the time of our visit. Client: ti. Unzz fopthc..t n^P� 4. 11 133er C4.(n 17r . Job #: S FL3 7,:. - Date:— V /D2, Contact: i izlle Site Address: EZ, P, ., '54r,,•r Lot: '3 3 Block: Filing: Subdivision: _Rove„ Installation CContractor:. G«,. Weather: JuwI Foundation Plan: a-2- Date:_31gleri, Job: SoilReport: &411 Job #: Oyoi -246 Date: Drilled Pier Specifications Reinforcing Steel: 3 #4S 6f Pier Diameter Ib" Min. Pier Length: /6' Zz, Min. Penetration t2' Planned Support Stratum:< Other: Description, E=Elevation of top pier, D=Pier Diameter, L=Total Pier Length, P=Penetration, H20=Depth to Water Pier E D L P H2O 1 2 3 4 5 1Dn 7 a 9 (� i 7" if 13' -- lo Subsurfacer Conditions observed during drilling: e {14- ,+. K4 4ewo �a 41, �F Installation Methods Used ❑ Pumping ❑ Casing Af Drill & Pour ❑ Tremy Summary of opinions: JQ It is our opinion that the drilled piers observed were in general conformance with plans and specifications. ❑ It is our opinion that the drilled piers were not in general conformance with plans and specifications. Corrective Actions: Field Representative: Pier E D L P H2O I I C-) g e 14 t 1.'' 13 12 1pp7�� 9r?" 'O"f r3 13 / 14 15 ("A c f3t 16 '_3 17 is f3' — 19 O IU` �(a`%il 1. — 20 ��r,, �'Io"" Pam' — Reviewed By: CTL I Thompson, Inc. 1 351 Linden Street, Suite 140, Ft. Collins, CO Reinforcing Steel Quality Assurance Observation C T L I T H® M P S® N Per the client's request, a representative of CTL Thompson has visually observed the reinforcement within the formwork under construction at the site referenced below. The following summarizes our observations and opinions at the time of our visit. Client:, AGAr Dc_v,✓,.l Aai Site Address: 1338 CR+CIIol nrr'V/ eall,ns. co Job #: Fw4,0o Lot: •^,7 Block: Filing: Date: Contact: fuss m/14 Subdivision: Reinforcing Plan Information Plan By: CTL Date: 3 /flG�pg� Job#: t�- 4,oay Reinforcing Type(s): ❑ footing U foundation wall ❑ grade beam ❑ pier cap ❑ structural slab ❑ slab -on -grade ❑ column ❑ other Wall / Grade Beam Reinforcing Steel Grade Horizontal Vert./Ties 1 T ,Hd�l .d�,� *v Qz"o.r. 2 4fnr 3 4 Pier Cap / Slab Reinforcing Steel Grade Longitudinal Lateral A B C D LIFER Ground A Installed — Location ❑ Not Observed Max/Min wall height observed: If void forms are required, are they installed as recommended? Ayes Lino Required thickness: in Concrete on -site? ❑ yes A no (% poured = +/- Weather: SVohy 4 j '7n Notes: 44-Ae 41"141 Of AW14" 4 ll n S Y !lace I . Ain contrr t n1 � Summary of Opinions ( It is our opinion that the reinforcing steel observed was in general conformance with the plan. ❑ It is our opinion that the reinforcing steel observed was not in general conformance with the plan. (2"d observation required). Deficiencies noted: Field presenta[ive Date .�-'ADO Lir`�. UZ o•• 10 CTL I Thompson, Inc. 1 351 Linden Street, Suite 140, Ft. Collins, CO 80524 GARAGE GARAGE GARAGE 3 GARAGE GARAGE "CONCRETE BLAB W/ A sun. PORCH z U) 5N IL N�s _14' 1'-4- SN D. dui O _3N rr D I" AD �3 D �S3 3j /D anti 4r 4 TE 81-AS kb 09 6LA 4' -RE Q S�Cor UUF S E SLAB zo 4=TEW ll'lElIlR CONCRETE SLAB TE 4 0 ,= WIF b L4 W WL4-UM4 OVER 6 &x641.4-W..�t A- CLEAN GRAVEL 4" CLEAN GRAVEL 'j� A- CLEAN GRAVEL 4' CLEAN GRAVEL 4" CLEAN F 9 9 P Sim. S3 bs I A S s 3 * As3i_m. 1, b 40) "Ell L C d) m S3 U1,FNISHED BASEMENT W1 tl�FINISHED BASEMENT W/ d) NISHED BASEMENT W1 tk*rKj54ED BASEMEN W/ UNFINISHED BASEMENT W/ BASEMENT W` VER CONC.SLAB OVER 4" CONIC. SLAB OVER 4" CONC. SLAB OVER 4" CONC, SLAB OVER 4" CONIC. SLAB 0'] .5 AN CLEAN GRAVEL 4' CLEAN GRAVEL 4' CLEAN GRAVEL A- CLEAN GRAVEL 4" CLEAN GRAVEL ff4 4'� 0 3v,.# ADJ. 311-0 ADJ. 3V2'# ADJ. 3t',"* ADJ. 3tj NO ADJ. b /—STEEL COL. STEEL COL. COL. COL. STEEL COL. C -ki 0mvi 4'- Z V.117 13 '5 0 (TYPJ 69= 0 (TYPJ (TYPJ (TYPJ C (TYR) STEEL C STEEL r S3 t A 14'- 3'- 0 -1014 3.e/ 14'-*4' 3" NO 4' 4"l S3 0<0 0 0 7 F S3 S3 Hill13' -GRES G (D b'10 (D 0 O -21; 22 3--l" V-0. 31-51. Y-1. B.-ON B.-C. 31-1. 3--l' 14 -V IS.-ol DRILLED CAISSON SPECIFICATIONS FOUNDATION PLAN FMllL PENETRATION Pcr��:vr.' 44 FC a PIER DIAMETER REINFORCEI-ENT I MIN_ LENGTH SCALE IV - V-0' < 10. (IN) 60 16 N BASEMENT IT (FT) RECOMMENDED QUALITY A55URANCE IN NON FULL LENGTH IS' -B_&'NT RECOMMENDE12 =ESYAlI2&' OBSERVATION PEFZFO�D By, NOTE, < NOTES, OTHER OBSERVATIONS MAY EEC OR OTHER EW31NEER5 u 0,8 . 1 2.) A MINIVIUM OF 25% OF THE PIERS SHOULD BE OBSERVED. COMPACTION TESTING EEC WORKM C.N 71413 PROJECT- Z< 8A 1 3.) WATER MAY BE ENCOUNTERED. IT 15 ANTICIPATED THAT A -DRLL AND DRILLED PIER OBSERVATION CTL I THOMPXN • POUR" METHOD MAY BE UTILIZED. FOUNDATION REW-ORMMM4T CTL I THOMPSON WMDDOUN (HD) SCHEDULE 4J U14EN WATER 16 ENCOUNTERED PUMPING OF CONCRETE MAY BE �s 1 REQUIRED. PERIMETER DRAIN CTL I THOMPSON• ODEL NOTES .L ING CTL I T WVSON STHDWpj wD-S AS SWCm ARE IN APPROXIMATE LOCATIONS. FIELD LOCATE DAMP PROOFING S3 5J PIER CONCRETE SHOULD BE PLACED IMIEDIATELY AFTER DRILLING. 6) SUE GEO-TErHNICAl_ ENGINEERS REPORT FOR ADDITIONAL 101 HO'S AT CORERS, EDGE OF OPENWA ABOVE, OR ENDS OF OJL FNAL GRADW. CERTFICATION CTL 1 17 SPErIFICATICNE. E TRED CORER, (SEE ARCH PLANS FOR DIMEN PENETRATION OBSERVATIONS T' 0 0 L) OBSERVATION BY ENGINEER 15 REQUIRED. CONTRACTOR To CALL FOR BE REQUIRED BY THE CITY MO- 2S OBSERVATION MINIMUM 24 HR5 PRIOR TO START OF DRILLING. OPEN -HOLE 501L VERIFICATION z U) 5N IL N�s _14' 1'-4- SN D. dui O _3N rr D I" AD �3 D �S3 3j /D anti 4r 4 TE 81-AS kb 09 6LA 4' -RE Q S�Cor UUF S E SLAB zo 4=TEW ll'lElIlR CONCRETE SLAB TE 4 0 ,= WIF b L4 W WL4-UM4 OVER 6 &x641.4-W..�t A- CLEAN GRAVEL 4" CLEAN GRAVEL 'j� A- CLEAN GRAVEL 4' CLEAN GRAVEL 4" CLEAN F 9 9 P Sim. S3 bs I A S s 3 * As3i_m. 1, b 40) "Ell L C d) m S3 U1,FNISHED BASEMENT W1 tl�FINISHED BASEMENT W/ d) NISHED BASEMENT W1 tk*rKj54ED BASEMEN W/ UNFINISHED BASEMENT W/ BASEMENT W` VER CONC.SLAB OVER 4" CONIC. SLAB OVER 4" CONC. SLAB OVER 4" CONC, SLAB OVER 4" CONIC. SLAB 0'] .5 AN CLEAN GRAVEL 4' CLEAN GRAVEL 4' CLEAN GRAVEL A- CLEAN GRAVEL 4" CLEAN GRAVEL ff4 4'� 0 3v,.# ADJ. 311-0 ADJ. 3V2'# ADJ. 3t',"* ADJ. 3tj NO ADJ. b /—STEEL COL. STEEL COL. COL. COL. STEEL COL. C -ki 0mvi 4'- Z V.117 13 '5 0 (TYPJ 69= 0 (TYPJ (TYPJ (TYPJ C (TYR) STEEL C STEEL r S3 t A 14'- 3'- 0 -1014 3.e/ 14'-*4' 3" NO 4' 4"l S3 0<0 0 0 7 F S3 S3 Hill13' -GRES G (D b'10 (D 0 O -21; 22 3--l" V-0. 31-51. Y-1. B.-ON B.-C. 31-1. 3--l' 14 -V IS.-ol DRILLED CAISSON SPECIFICATIONS FOUNDATION PLAN FMllL PENETRATION Pcr��:vr.' 44 FC a PIER DIAMETER REINFORCEI-ENT I MIN_ LENGTH SCALE IV - V-0' < 10. (IN) 60 16 N BASEMENT IT (FT) RECOMMENDED QUALITY A55URANCE IN NON FULL LENGTH IS' -B_&'NT RECOMMENDE12 =ESYAlI2&' OBSERVATION PEFZFO�D By, NOTE, < NOTES, OTHER OBSERVATIONS MAY EEC OR OTHER EW31NEER5 u 0,8 . 1 2.) A MINIVIUM OF 25% OF THE PIERS SHOULD BE OBSERVED. COMPACTION TESTING EEC WORKM C.N 71413 PROJECT- Z< 8A 1 3.) WATER MAY BE ENCOUNTERED. IT 15 ANTICIPATED THAT A -DRLL AND DRILLED PIER OBSERVATION CTL I THOMPXN • POUR" METHOD MAY BE UTILIZED. FOUNDATION REW-ORMMM4T CTL I THOMPSON WMDDOUN (HD) SCHEDULE 4J U14EN WATER 16 ENCOUNTERED PUMPING OF CONCRETE MAY BE �s 1 REQUIRED. PERIMETER DRAIN CTL I THOMPSON• ODEL NOTES .L ING CTL I T WVSON STHDWpj wD-S AS SWCm ARE IN APPROXIMATE LOCATIONS. FIELD LOCATE DAMP PROOFING S3 5J PIER CONCRETE SHOULD BE PLACED IMIEDIATELY AFTER DRILLING. 6) SUE GEO-TErHNICAl_ ENGINEERS REPORT FOR ADDITIONAL 101 HO'S AT CORERS, EDGE OF OPENWA ABOVE, OR ENDS OF OJL FNAL GRADW. CERTFICATION CTL 1 17 SPErIFICATICNE. E TRED CORER, (SEE ARCH PLANS FOR DIMEN PENETRATION OBSERVATIONS T' 0 0 L) OBSERVATION BY ENGINEER 15 REQUIRED. CONTRACTOR To CALL FOR BE REQUIRED BY THE CITY MO- 2S OBSERVATION MINIMUM 24 HR5 PRIOR TO START OF DRILLING. OPEN -HOLE 501L VERIFICATION OBSERVATIONS T' 0 0 L) OBSERVATION BY ENGINEER 15 REQUIRED. CONTRACTOR To CALL FOR BE REQUIRED BY THE CITY MO- 2S OBSERVATION MINIMUM 24 HR5 PRIOR TO START OF DRILLING. OPEN -HOLE 501L VERIFICATION f' 1 I I I I 1 I b'-0' 24'-0' 6'-0. 12'-0' 6'-0' 11124'.0. 6'_0' 5' 5' P-4' S. 5' -0' I'-4' 5' 5' I'-4' I'-4' S. 5' 14' S'-3' 9'-3' 9'-3' All 'I I I I I I n u , FV D I, •' 6 — S3 GARAGE D GARAGE _ S3 GARAGE I YD D S3 — GARAGE i� GARACsE D S3 S3 4' CONCRETE BLAB W/ 6x6-WI.4-WI.4 UUF OVER 4' CLEAN GRAVEL 4' GCNCRETE BLAB W/ bxb-W.d-WA W1F OVER 4' CLEAN GRAVEL 4' CONGRETE-SLAB bxb-W.4-W1.4 WWF OVER 4' CLEAN GRAVEL 4' CONCRETE BLAB 6xb-WIA-WI.4 WlR OVE 4' CLEAN GRAVEL CONCRETE SLAB W/ xb-WI.4-WIA III OVER 4' CLEAN GRAVEL 0 9 9 9 0 6 9 Q 9 0 g 9 A sim. ob 0161 L A sim. S3 A sim. B O A sim. A s m. 'o, Z� �° 3 �, E c ._ 3.�z'. S3 { ` . I C UNFINISHED BASEMENT (IVS3 4' CONC. SLAB OVER -�-)• W 4' CLEAN GRAVEL q C UNFINISHED BASEMENT W/ 4' CONC, SLAB OVER 4' CLEAN GRAVEL UNFINISHED BASEMENT W/ 4' CONC. SLAB OVER 4' CLEAN GRAVEL III C, 63 I UNFINISHED BASEMENT W/ -D. `I 4' CLE SLAB OVER 11 , 4' GLEAN GRAVEL UNFINISHED BASEMENT W/ 4' CONC. SLAB OVER 4' CLEAN GRAVEL S3 11 w J NII ADJ. q.t2 { STEEL COL. •' �n4 _ (T7PJ —0. 3111 ADJ. 9 STEEL GOL �ITTF'J -v r 34'OIADJ. 9 /—STEEL COL. / (Tyr) 3111 ADJ. v STEEL COL.�� (TYF') ", g3111 ADJ. -G U6 STEEL COL I (TYPJ —o.zy v dddddd���� d( c 1 r ' In r In S3 m a �' ''+�4 3'-83� v 31- /' W'-4V4 3 r /' 14' 3y4 14'-3y4 3' �' 3'-0/' �' 4 1 r ' s s a 4c.7z -&qS F S3 _�,�' S3 -C�•�`f S3 �'. , �O t"•l S3 PIII F'ORGH 0 , 9 (ID4 s A7' loz _D;gy• 3'-T' B'-0' 3'-0' 3'-5' 3'-T' 8'-0' 3'-0' 3'-5' 3'-5' 3'-0' L3'-9' B'-0' 3'-T 3'--V W.O. W-0' S3 A S3 1 nlfll I rP'. /`AIGG/rl Clfllrl/� /.tl/`IC ;=r)i 1t%1n AT1r)X1 P1 A&I