HomeMy WebLinkAbout3815 Precision Dr - Special Inspections/Engineering - 09/05/2013Rid
q-5-13
EARTH ENGINEERING
COMPANY, INC.
February 6, 2013
LandMark Solutions, Inc.
1170 West Ash
Windsor, Colorado 80550
Attn: Mr. Bob Brex
Re: Foundation Bearing Observation 1d
3815 Precision Drive- 6 Plex 11� 1 �3 i hyu 1 U
Fort Collins, Colorado
EEC Project No. 12-01-190
Mr. Brex:
As requested, Earth Engineering Company, Inc. (EEC) personnel have completed an
observation of the foundation bearing materials for footing foundations for the referenced
project. The results of those observations along with site photos are included with this report.
On January 8, 2013, EEC personnel observed foundation bearing materials for the foundation
footings for the referenced multi -family residence. We understand the multi -family
residences will be lightly loaded wood frame structures constructed on full basements. At the
time of our field observations, the building area had been excavated to approximate
foundation -bearing elevation. Reddish brown sandy to very sandy clay soils were observed at
foundation bearing level at that location. A hand auger boring was excavated to a depth of
approximately 3 feet below the basement foundation bearing level revealed like materials to
the depths explored. Dynamic cone penetrometer tests indicated that the in -situ materials
were generally stiff to very stiff in consistency.
A swell/consolidation test was performed on a representative sample of the foundation
bearing materials at the basement foundation bearing elevation to determine swell potential
with variation in moisture content. The reddish brown sandy to very sandy clay soils at the
basement foundation bearing level showed low potential for swelling at present moisture and
density conditions.
P.O. Box 271428 P.O. Box 49322
FORT COLLINS, COLORADO 80527- 1 428 COLORADO SPRINGS, COLORADO 80949-9322
(970) 224- 1 522 (FAx) 663-0282 (7 19) 442-68 1 3 (FAx) 447-9635
Earth Engineering Company, Inc.
EEC Project No. 12-01-190
February 6,2013
Page 2
Areas of loose soil remained in the open excavation after excavating; therefore, any loose
soils beneath the foundation elements should be removed prior to placement of the
foundation concrete. The materials observed in the excavation were generally consistent with
those outlined in the soils report prepared by Earth Engineering Company, Inc., dated
September 21, 2012. Based on the results of the outlined field testing and observations, it is
our opinion the in -situ, natural sandy to very sandy clay materials could be used for support
of the footing foundations at the design maximum net allowable total load soil bearing
pressure of 1500 psf. Care should be taken to avoid placing any foundation footing
elements and floor slabs on areas of frozen soil prior to concrete placement.
We appreciate the opportunity to be of service to you on this project. If you have any
questions regarding this report, or if we can be of further service to you in any way, please do
not hesitate to contact us.
Very truly yours,
Earth Engineering Company, Inc.
RPp0 RIG/Sr
p ,.-•�oslH-..F
' 3 24' •
Michael J. Co ey, P. .
Principal Engineer
MJC/d1a
cc: Chris Douglass — LandMark Solutions, Inc.(gdouglass(iblandmarksolutionsinc.com)
SWELL / CONSOLIDATION TEST RESULTS
Material Description:
Reddish Brown Sandy to Very Sandy Clay
Sample Location:
S-2 @ 5.5' (Basement Foundation Bearing Level)
Liquid Limit: --
IPlasticity Index: -
% Passing #200: --
Beginning Moisture: 10.5%
1Dry Density: 105.3 pcf
Ending Moisture: --
Swell Pressure: <500 psf
% Swell @ 500 psf: None
10
8
3 6
4
c 2
m
E
d
0
0
c
m
2 Vf a t r dded
a -2
a -4
0
-0 a
�o
C
-6
O
U
-8
-10
0.01 0.1 1 10
Load (TSF)
Project: 3815 Precision Drive - 6 Plex
Fort Collins, Colorado
Project No.: 12-01-190
Date: January 2013
February 6, 2013
LandMark Solutions, Inc.
1170 West Ash
Windsor, Colorado 80550
Attn: Mr. Bob Brex
Re: Foundation Drain and Damp Proofing Observation
3815 Precision Drive
Fort Collins, Colorado
EEC Project No. 12-01-190
Mr. Brex:
EARTH ENGINEERING
COMPANY, INC.
As requested, Earth Engineering Company, Inc. (EEC) personnel have completed the construction
observation services you requested for the referenced project. Those services included observations of
the foundation drain placement and damp proofing at the referenced address. The results of those
observations are included with this report. Two site visits were needed to complete these observations.
On January 24t° and February 4`°, 2013, EEC personnel observed the foundation drain for the
referenced project. The foundation drain consisted of 6-inch perforated pipe bedded in gravel around
the below grade exterior perimeter of the structure which appeared to slope to drain towards two
basement sump pits located in the east and west end units. The gravel was covered with filter fabric.
The damp proofing consisted of a grey spray -on coating that appeared to cover all exterior below
grade living areas of the basement walls.
We appreciate the opportunity to be of service to you on this project. If you have any questions
regarding this report, or if we can be of further service to you in any way, please do not hesitate to
contact us.
Very truly yours,
Earth Engineering Company, Inc.
0 REG/S
v 3 724 m e
Michael J. Coldy, P
Principal Engineer
Chris Douglass — LandMark Solutions, Inc. —(couglass(a)landmarksolutionsinc.coni)
P.O. Box 271 428 P.O. Box 49322
FORT COLLINS. COLORADO 80527- 1 428 COLORADO SPRINGS. COLORADO 80949-9322
(970) 224-1522 (FAx) 663-0282 (719) 442-6813 (FAX) 447-9635
February 6, 2013
LandMark Solutions, Inc.
1170 West Ash
Windsor, Colorado 80550
Attn: Mr. Bob Brex
Re: Wall Steel Reinforcement Observation
3815 Precision Drive — 6 Plex
Fort Collins, Colorado
EEC Project No. 12-01-190
Mr. Brex:
EARTH ENGINEERING
COMPANY, INC.
Earth Engineering Company, Inc. (EEC) personnel have completed the construction
observation services you requested for the referenced project. Those services included an
observation of foundation wall reinforcement steel for the referenced multi -family
residence. The results of the observations completed by EEC personnel are included with
this report. Two site visits were needed to complete the observations.
On January 16t' and January 21 ”, 2013, EEC personnel observed the reinforcing steel for
the foundation walls for the referenced multi -family residence. The reinforcing steel
observed at the porch and basement walls consisted of two #5 bars placed horizontally at
the top and bottom of the foundation walls along with one #5 bar placed horizontally at
the approximate mid -height of the foundation walls. In addition, one #5 bar was placed
vertically at approximately 24 inches on -center throughout the length of the walls. Lap
lengths observed were checked and appeared to meet the minimum required lengths. In
addition to the reinforcing steel observed, the Uffer ground (a.k.a. concrete encased
electrode) was also observed. The Uffer grounding rod consisted of a single piece of #5
rebar tied to the bottom horizontal reinforcement within the forms and extended vertically
approximately 1 foot above the foundation wall at the northwest corner of the west unit
and at the northeast corner of the east unit.
P.O. BOX 271 428 P.O. BOX 49322
FORT COLLINS. COLORADO 80527- 1 428 COLORADO SPRINGS, COLORADO 80949-9322
(970) 224-1522 (FAX) 663-0282 (719) 442-6813 (FAX) 447-9635
Earth Engineering Company, Inc.
EEC Project No. 12-01-190
February 6, 2013
Page 2
At the time of our observations, it appeared that the wall reinforcing steel had been
placed in general accordance with the construction plans prepared by Realarchitecture,
Project No. 1107, dated October 8, 2012.
We appreciate the opportunity to be of service to you on this project. If you have any
questions regarding this report, or if we can be of further service to you in any way,
please do not hesitate to contact us.
Very truly yours,
Earth Engineering Company, Inc.
gyp, .•��osEFA,*-.
3 724
Michael J. C ley P.E.
Principal Engineer
MJC/dla
cc: Chris Douglass — LandMark Solutions —(cdout;lass(u)landmarksolutionsinc.com)
EARTH ENGINEERING
COMPANY, INC.
February 6, 2013
LandMark Solutions, Inc.
1170 West Ash
Windsor, Colorado 80550
Attn: Mr. Bob Brex
Re: Basement Foundation Footing Observation
3815 Precision Drive — 6 Plex
Fort Collins, Colorado
EEC Project No. 12-01-190
Mr. Brex:
Earth Engineering Company, Inc. (EEC) personnel have completed the construction
observation services you requested for the referenced project. Those services included an
observation of the foundation footing dimensions placed for the referenced address. The
results of the site observations completed by EEC personnel are included with this report.
On January 9, 2013, EEC personnel observed footing foundation widths for the
foundation footings for the above referenced single-family residence. The basement
footings were approximately 24, 26 and 30 inches wide by 8 inches thick at various
locations. Two #5 bars were placed horizontally and continuous along with one #5 bar
placed transversely at approximately 20 inches on -center throughout the length of the
footings.
At the time of our observations, it appeared that the foundation footing dimensions and
observed reinforcing steel had been placed in general accordance with the construction
plans prepared by Realarchitecture, Project No. 1107, dated October 8, 2012.
P.O. BOX 271428 P.O. Box 49322
FORT COLLINS, COLORADO 80527- 1428 COLORADO SPRINGS, COLORADO 80949-9322
(970) 224-1522 (FAX) 553-0282 (719) 442.6813 (FAX) 447-9635
Earth Engineering Company, Inc.
EEC Project No. 12-01-190
February 6, 2013
Page 2
We appreciate the opportunity to be of service to you on this project. If you have any
questions regarding this report, or if we can be of further service to you in any way,
please do not hesitate to contact us.
Very truly yours,
Earth Engineering Company, Inc.
0 REG
I
�O�•�ioseF,y TF,p
• 35 24 •
ASS. ...... •' G
Michael J. Coley, E.
Principal Engineer
MJC/dla
cc: Chris Douglass — LandMark Solutions —(couglassQlandmarksolutionsinc.com)