HomeMy WebLinkAbout1315 Vinson St - Disclosures/Final Energy - 02/27/2006THERMAL
ddmtk
CONCEPTS
oil, LENNOY
P.O. Box 270066•For[ Collins, CO 80527
MASCO CONTRACTOR SERVICES M� (970)223-7090•Fax (970)223-7098
February 27, 2006
RE: Lennar Homes
2695 W. Eisenhower Blvd
Suite 230
Loveland CO 80537
Project: 1315 Vinson '
Plan: N 104
Score: 85.4
The following is a list of the trade-offs used to achieve the 2005 energy code requirement.
The house has a Final HERS score of 85.4
Area
Value
Notes
House faces
North
Exterior walls
R-15
R-15 in 2x4
Basement walls
R-2.11
R-19 to rim joist space and no insulation to the exposed concrete exterior walls
Floors
R-30
R-30 fiberglass batt to cantilevered areas
Windows
2..45
Combined R-value for all windows used. All Low E units
Air infiltration
.35 ACH
The most allowed without fresh air ventilation.
Ceiling insulation
R-38
Blown Loose fill insulation for R-38 value
Heating System
92% AFUE
Effective AFUE
Cooling System
N/A
Water Heater
.59 EF
Assuming a standard water heater naturally vented with heat traps installed
Crawlspace
No crawlspace
Sincerely,
Paul Higman
Energy Rater
1/0 Summary Report
General Information
RatingID: 22583
Rating Type: Final
Certificate:
Ordered By: Lennar
1315 Vinson,
Ft. Collins, CO 80525
Rater: 158 Paul Higman
Date Rated: 2/24/2006
Total Area: 2824
Electric Utility = 60, Ft.Collins -
Energy
Gas Utility = 6, Xcel Energy
Output Summary
Topic
Ref Hse
St Code
AS -IS
UP 1
UP 2
UP 3
UP 4
UP 5
Rating Score
-
74.6
85.4
0
0
0
0
0
Total Electricity Cost
$484.0
$439.0
$436.0
Total Fuel Cost
$1221.0
$1520.0
$999.0
PV Cost Benefit
-
-
Total Electricity Use(kWh)
7612
6902
6854
0
0
0
0
0
Total Fuel Use(Therms)
1201
1495
982
0
0
0
0
0
Heating Electricity(kwh)
188
240
192
0
0
0
0
0
Cooling Electricity(kwh)
761
0
0
0
0
0
0
0
DHW Electricity(kwh)
0
0
0
0
0
0
0
0
Appliance Electricity(kwh)
6662
6662
6662
0
0
0
0
0
Heating Fuel(Therms)
831
1125
649
0
0
0
0
0
Hot Water Fuel(Therms)
370
370
332
0
0
0
0
0
Appliance Fuel(Therms)
0
0
0
0,
0
0
0
0
Electricity Savings(kWh)
-
-
48
Fuel Savings(Therms)
-
-
513
Electricity Cost Savings
-
-
$3.0
Fuel Cost Savings
-
-
$521.0
Total Cost Savings
-
-
$524.0
Design Heating Load(kBtu/h)
-
64.18
45.5
0
0
0
0
0
Design Cooling Load(kBtu/h)
-
0
0
0
0
0
0
0
Price Of Electricity($/kWh)
.064
.064
.064
.000
.000
.000
.000
.000
Price Of Fuel($/Therm)
1.017
1.017
1.017
.000
.000
.000
.000
.000
Electric Utility Service
-
-
$46.92
Gas Utility Service
-
-
$108.00
Total Upgrade Costs
-
-
$2067.00
Package Present Value
-
-
$6526.10
CO2 Reduction(tons)
-
-
3.02
.00
.00