Gentlemen:
On August 7 and 9, 2007, Weeks & Associates observed the footings and foundation wall steel
at the referenced site as requested. Observations indicate the footing sizes and foundation wall
steel reinforcing are in substantial accordance with the foundation plan for the project. In
addition, the electrode had been placed in accordance with the recommendations by NEC.
If I can be of further assistance please contact me.
Sincerely,
Weeks & Asso fates, Inc.
4
Connie . Schneider, E.I.T.
Staff Engineer
Weeks & Associates, Inc. 4700 S. College, Suite #1 FortCollins, CO 80525 (970) 225-2422
0 REG/
)'R G ' c STFq��
23012
?P.E.
Weeks & Associates, Inc.
Structural Engineers
August 29, 2007
Aspen Homes
3037 N. Taft Avenue
Loveland, Colorado 80538
Re: Lot 9, Block 25, Maple Hill
2263 Clear field Way
Fort Collins, Colorado
Project No. 27170
Gentlemen:
On August 17, 2007, Weeks & Associates observed the perimeter drain at the referenced site.
Observations indicated a 4" diameter perforated pipe had been placed around the exterior
perimeter of the basement foundation and sloped to the sump pit in the basement. The drain
pipe installation is in substantial accordance with the perimeter drain recommendations for the
project. In addition, the exterior of the basement foundation walls had been damproofed.
If I can be of further assistance please contact me.