HomeMy WebLinkAbout2262 Muir Ln - Special Inspections/Engineering - 05/31/2007May 31, 2007
Aspen Homes
3037 N.Taft Avenue
Loveland, Colorado 80538
Attn: Mr. Jammie Sabin
(3 OiWe:�At�?\
Irerracon
Consulting Engineers & Scientists
Re: Foundation Footing Sizes, Wall Steel and CEE Observations
Proposed Single Family Residences
2262 Muir Lane - Lot 8 Block 25
Fort Collins, Colorado
Terracon Project No. 20045204
Dear Mr. Sabin:
301 North Howes
Fort Collins, Colorado 80521
Phone 970.484.0359
Fax 970.484.0454
www.terracon.com
A representative from Terracon observed the interior and exterior footing sizes and wall steel
reinforcement, including the "concrete -encased electrode" (CEE), for the above referenced lot
on May 24 and 30, 2007, as requested.
Observations made during the foundation construction indicate that the interior and exterior
footing sizes, wall steel and CEE placement were in general accordance with the plans for this
project. nAflO UCH_
Sincerely,
TERRACON
fD le -
Nick M. Spencer, E.I.T.
Staff Engineer
Copies: Addressee (5)
�.,- ••.....�, -gyp `�
.a; 40208
aymond L. Denton, II, P.�ONAL��
Geotechnical Department Manager
Delivering Success for Clients and Employees Since 190
More Than 80 Offices Nationwide
June 6, 2007
Aspen Homes
3037 N. Taft Avenue
Loveland, Colorado 80538
Attn: Mr. Jammie Sabin
Re: Exterior Perimeter Drain Observation
Proposed Single Family Residence
Maple Hill Subdivision
2262 Muir Ln — Lot 8 Block 25
Fort Collins, Colorado
Terracon Project No. 20045204
Dear Mr. Sabin:
Irerracon
Consulting Engineers & Scientists
301 North Howes
Fort Collins, Colorado 80521
Phone 970.484.0359
Fax 970.484.0454
www.terracon.com
A representative from Terracon observed the exterior perimeter drain at the above referenced
address within the Maple Hill Subdivision on June 6, 2007, as requested. At the time of our site
visit, a flinch diameter, perforated pipe had been placed around the exterior perimeter of the
basement foundation and was observed to exhibit positive gravity flow toward a sump pit located in
the interior of the basement. The pipe was observed to have a layer of %-inch washed gravel
beneath the pipe. The waterproof dampening was also observed and in our opinion was uniformly
applied to the exterior foundations.
In our opinion the portion of the exterior perimeter drainage system observed was constructed in
general accordance with the plans and specifications for the project.
Sincerely,
TERRACON
H. Chris Tennant, E.I.T.
Field Project Manager
Copies to: (5) Addressee
d y L. enton, II, P.E.
Geotechnical Department M