Total Engineering Service, Inc.
3310 State Street • Evans, CO 80620
April 23, 2007
Dan Edesun
W Construction of Northern Colorado LL.0
7251 W. 20th St., Bldg L, Ste. 200
Greeley, CO 80634
RE: Foundation Subsurface Drainage System
2656 'Thoreau hive
Maple Hill, Ft. Collins, CO
Dear Mr. Ericson:
As requested, Total Engineering staff observed the fr
and sump system and found it to be completc and in ;
design drawings prepared for this structure at the dat,
subsurface drainage system was observed on April 2:
Please give me a call if you have any questions.
Sincerely,
!l�/�'1 4
Tom Cope, P.E.
President
06-299
1330-1071 • Fax (970) 330-1252
undation subsurface drainage pipe
substantial compliance with the
of the observation. The foundation
1.2007.
n rleQ,s,
970+330+8368 Journey Homes, LLC Journey Homes; LLC
Total Engineering Service, Inc.
� 5
3310 State Street • Evans, CO 80620
April 20, 2007
Dan Erickson
J & J Construction
7251 W. 20th St., Bldg L, Ste. 200
Greeley, CO 80634
RE: Foundation Damp Proofing
2656 Thoreau Drive
Maple Hill, Ft. Collins, CO
Dear Mr. Erickson:
As requested, Total Engineering staff observed the fc
it to be complete and in substantial compliance with
structure at the date of the observation, The foundati
April 20, 2007.
Please give me a call if you have any questions.
Sincerely,
/ ;n 40e
Tom Cope, P.E.
President