HomeMy WebLinkAbout1263 E Magnolia St - Special Inspections/Engineering - 09/29/2006September 29, 2006
Centennial Bank of the West
713 South Lemay Avenue
Fort Collins, CO 80524
Attn: Mr. Jim Miller
Re: Construction Materials Compliance Summary
Centennial Bank of the West
1263 East Magnolia Street t/
Fort Collins, Colorado
Project No. 20061064
Dear Mr. Miller:
Earthwork
Irerracon
Consulting Engineers & Scientists
301 North Howes
Fort Collins, Colorado 80521
Phone 970.484,0359
Fax 970.484.0454
www.terracon.com
At your request, we reviewed the earthwork materials placed and monitored during construction
activities by Terracon on an "as requested" basis. Our services on the project building have
included performing laboratory testing of the soils for suitability to the project specifications and
the Geotechnical Engineering Report recommendations performed by Earth Engineering
Consultants, Inc. (Project No. 105285; dated June 17, 2005). Terracon also performed in -place
field density testing during placement of the fill to check maximum density and moisture control.
As recommended in the soils investigation, on -site or approved imported soils were suitable for
placement during construction. Laboratory tests indicated fill material tested by Terracon met
the recommendations as outlined in the geotechnical report. The results of the field and
laboratory testing were forwarded for review. In addition, the on -site superintendent and
subcontractors were informed on a daily basis of the test results performed.
Terracon performed 25 in -place moisture-density/compaction tests for the building and parking
lot site subgrade and fill placement. The tests at the locations taken indicated the final material
either met or ultimately achieved (after retesting) compaction specification requirements.
Our test results represent only the materials at the location and time of testing. Terracon did
not direct nor control the fill placement and compaction at the site and does not assume
responsibility for the placement, compaction or control of the fill materials. Areas of fill which
are not representative of our testing may exist, particularly in common fill areas such as slopes
or landscaped outside of proposed construction. The foundation type and specific design for
the structure was recommended based on the particular characteristics of the soil type at
foundation depth, and on the basis of further evaluations and observations prior to construction.
Concrete
The Portland cement concrete placed and tested on -site consisted of 8 tests for physical
property and compressive strength tests of foundation footings, foundation walls, floor slab and
columns. The reports indicate the specified minimum compressive strength requirements for
the project have been achieved.
Delivering Success for Clients and Employees Since 1965
More Than 80 Offices Nationwide
Centennial Bank of the West 1rerracon
Compliance Summary
Project No. 20061064
Page 2
Reinforcing Steel
Terracon provided reinforcing steel placement observation in structural concrete placements as
requested. The observations were performed per the provided plans and specifications for the
project and have been formally reported to the client and designated parties. It is
recommended that the project structural engineer review the observation reports for
acceptance as meeting the project criteria.
Structural Steel
Inspex ndt. provided structural steel/weld site construction observation. Observations were
provided to on -site personnel at the time of the visit with a written report as documentation. The
observation report has noted observations as being acceptable per the provided plans. It is
recommended that the project structural engineer review the observation reports for
acceptance as meeting the project criteria.
Foundation
Terracon provided observation of the spread footing foundation and open -hole excavations/in-
place compaction testing of fill material as requested during construction. A summary of the
observations and structural review response items were provided in written reports upon
completion. Per EEC's geotechnical report and Terracon's observations performed, spread
footing foundation has been placed in general accordance with the plans and specifications and
were placed on the anticipated bearing material identified in the site specific geotechnical
report.
This report has been prepared for the exclusive use of providing test data and observations to
document the earthwork, concrete and structural steel operations conducted for the proposed
project. The opinions and conclusions presented have been derived in accordance with
generally accepted geotechnical and material engineering practice. No other warranty
expressed or implied is made. In the event that there are any changes in the nature or design
of the project, the conclusions contained in this report shall not be considered valid unless this
firm reviews such changes, and the conclusions of this report are modified or verified in writing.
This letter is prepared for the exclusive use and reliance of our client. Use or reliance by any
other party is prohibited without the written authorization of our client and Terracon.
Reliance on this letter by the client and all authorized parties will be subject to the terms,
conditions and limitations stated in the proposal, report and Terracon's Terms and Conditions.
The limitation of liability defined in the Terms and Conditions is the aggregate limit of Terracon's
liability to the client and all relying parties.
Centennial Bank of the West
Compliance Summary
Project No. 20061064
Page 3
1rerracon
It has been our pleasure to work with you on this project and to continue providing services
during your ongoing construction. Should you have any questions, or need additional
information, please contact us at your convenience.
Respectfully submitted,
TERRACON
MikIL alker, CET
Manager of Construction Services
David A. Richer, P
Geotechnical Enoii
Enc/Copies to: (2) Addressee
(1) Sanderson Architects
(1) Growling Bear Co. Inc. - Office
(2) City of Fort Collins Bldg. Dept. c/o Growling Bear - Onsite