Alternative Name Alignment P-0
Figure P.2 – Alternative P-0
Alternative
Location &
Description
Poudre Intake Alternative P-0 begins at the Poudre Diversion Pump Station
location, just southeast of the Timnath Canal. The alignment then stays north
of the Poudre River, passes through the garden center property before
crossing Timberline Rd. From there, it follows the curve between the backs of
residences and the ponds in the Fort Collins Natural Areas. The alignment then
follows the south side of the Cache la Poudre Inlet canal until it crosses to the
north side of the canal prior to crossing I-25. After crossing I-25, the alternative
veers south where it crosses the canal again, and follows the south side of the
canal until it crosses Prospect Road. From there, it continues along McLaughlin
Lane before it turns east and continues to follow another canal until intersecting
with CR 5. After intersecting at CR-5, the alignment heads due east, following
an existing powerline easement before intersecting with County Line Road,
where it ties in with the proposed County Line Alignment.
Criteria Ranking Comments
Capital Cost Green $ 11,464,000.00
Conduit Length Yellow 6.2 miles; 32,736 feet
Easement Difficulty Yellow 33 parcels crossed, 7 non-perimeter crossings
Right-of-Way Impact Green 400 LF in ROW
Land Owner Impact
Green
2 driveways crossed, minimal subjective landowner
impacts due to paralleling existing powerline easement
south of Prospect
Proximity to Occupied
Dwellings Red Within 100-feet of 51 dwellings
Environmental Impacts and
Floodplain Crossings Green
550 LF of wetlands/riparian areas crossed and 8,900 LF of
floodplain crossed
Existing Utilities Green Low utility density
Hazardous/Permitted
Crossings Green No hazardous/permitted crossings known
Surface and Street Impacts Green
100 LF in gravel roads (CR 3e) and 400 LF in paved roads
(Cherly St)
Traffic Impacts Green
1,000 LF of low, 100 LF of medium, 400 LF of high, traffic
impact score of 2800
Water Storage Reservoirs
Impacts Green No impacts expected
Construction Duration and
Relative Constructability Green 253 days of construction
Required Trenchless
Crossing Green
1 HW crossing (I-25), 1 CR crossing (CR 5), 3 other road
crossings (Summit View,Timberline, Prospect) and 1,000
feet total trenchless
Development Pressure Green 5000 LF of near term developments
Operation and
Maintenance Access Green
Convenient access with trail system and ditch road west of
I-25. East of I-25, proximity to existing powerline easement
makes for especially convenient access.
O&M Requirements Yellow 6 ARV and BO pairs
Natural Resources Impacts Yellow
5,700 LF in Fort Collins Natural Areas, 350 LF in riparian
corridor