HomeMy WebLinkAboutEAST RIDGE SECOND - Filed FDT-FIELD DENSITY TEST - 2019-06-05Soilogic, Inc. 3522 Draft Horse Court • Loveland, CO 80538 • (970) 535-6144 May 22, 2019 Bison Ridge Construction, LLC 3524 Draft Horse Court Loveland, Colorado 80538 Attn: Mr. Guillermo Hernandez Re: Construction Materials Testing and Observation Services Report East Ridge Phase 2 Fort Collins, Colorado Soilogic Project # 19-2026 Mr. Hernandez: During the period of April 25 through May 14, 2019, Soilogic Inc. (Soilogic) provided construction materials testing and observation services for the referenced project. Our services were provided on a part-time basis and included the observation and testing of utility backfill materials. Results of the observation and testing services completed during the referenced period are included with this report. During the referenced period, Soilogic personnel obtained one (1) representative sample of the excavated site soils for laboratory evaluation of the moisture density relationship of that material. The laboratory testing completed on the obtained sample included a standard Proctor (ASTM D-698) test. Results of the completed standard Proctor test were used to evaluate the percent compaction and moisture variability with reworked soils in the field and are included with this report. During the referenced period, Soilogic personnel performed field moisture/density tests on sewer and water utility backfill materials that had been placed and compacted prior to and during our site visits. The field moisture/density tests were completed at random locations and elevations within the backfill areas and were performed in general accordance with ASTM Specification D-2922. Results of the field moisture/density tests completed during the referenced period are included with this report. The field moisture/density test results met the project compaction requirement of at least 95% of the material’s standard Proctor maximum dry density and -1% to +3% of the material’s optimum moisture content. Construction Materials Testing and Observation Services Report East Ridge Phase 2 Fort Collins, Colorado Soilogic # 19-2026 2 We appreciate the opportunity to be of service to you on this project. If you have any questions concerning the enclosed information or if we can be of further assistance to you in any way, please do not hesitate to contact us. Very Truly Yours, Soilogic, Inc. Reviewed by: Jason Horner, E.I. Wolf von Carlowitz, P.E. Project Engineer Principal Engineer EAST RIDGE PHASE 2 Density Fort Collins, Colorado Project # 19-2026 April 2019 Field Moisture/Density Testing Summary Material Tested and Location Project Date Daily Depth Number Number ID Moisture Compaction Percent Compaction Test Test Proctor Moisture (Pass/Fail) Moisture Variability Field Results Dry 1 4/25 1 -6' Sewer Service Backfill - Block 1 - Lot 9 Pass 2 4/25 2 -6' Sewer Service Backfill - Block 1 - Lot 10 A 11.5% 115.0 -0.5% A 12.2% 110.8 0.2% 96% Pass 99% Pass Pass 96% Pass Pass 4 4/25 4 -6' Sewer Service Backfill - Block 1 - Lot 12 A 12.3% 114.2 0.3% 98% Pass Pass 3 4/25 3 -6' Sewer Service Backfill - Block 1 - Lot 11 A 12.3% 110.9 0.3% 5 4/25 5 -6' Sewer Service Backfill - Block 1 - Lot 13 A 13.0% 111.1 1.0% 96% Pass Pass 99% Pass Pass 7 4/25 7 -6' Sewer Service Backfill - Block 1 - Lot 15 A 12.8% 114.1 0.8% 98% Pass Pass 6 4/25 6 -6' Sewer Service Backfill - Block 1 - Lot 14 A 11.7% 114.8 -0.3% 95% Pass Pass 9 4/25 9 -6' Sewer Service Backfill - Block 1 - Lot 17 A 12.5% 113.4 0.5% 98% Pass Pass 8 4/25 8 -6' Sewer Service Backfill - Block 1 - Lot 16 A 15.0% 110.3 3.0% 10 4/25 10 -6' Sewer Service Backfill - Block 1 - Lot 18 A 14.4% 110.9 2.4% 96% Pass Pass 11 4/25 11 -6' Sewer Main Backfill - MH 1-4.11 - 1' S A 14.7% 111.1 2.7% 96% Pass Pass 97% Pass Pass 13 4/25 13 -6' Sewer Main Backfill - MH 1-4.10 - 80' S A 12.0% 112.2 0.0% 97% Pass Pass 12 4/25 12 -6' Sewer Main Backfill - MH 1-4.10 - 10' N A 13.0% 113.0 1.0% 96% Pass Pass 15 4/25 15 -4' Sewer Main Backfill - MH 1-4.11 - 35' S A 11.4% 115.0 -0.6% 99% Pass Pass 14 4/25 14 -6' Sewer Main Backfill - MH 1-4.11 - 70' S A 14.4% 110.9 2.4% 16 4/25 16 -4' Sewer Main Backfill - MH 1-4.10 - 50' N A 14.7% 110.8 2.7% 96% Pass Pass 17 4/25 17 -4' Sewer Main Backfill - MH 1-4.10 - 20' N A 12.0% 114.1 0.0% 98% Pass Pass 97% Pass Pass 19 4/25 19 -4' Sewer Main Backfill - MH 1-4.9 - 10' S A 11.7% 115.0 -0.3% 99% Pass Pass 18 4/25 18 -4' Sewer Main Backfill - MH 1-4.10 - 40' S A 11.9% 112.3 -0.1% 96% Pass Pass 21 4/26 2 Grade Sewer Service Backfill - Block 1 - Lot 10 A 13.0% 114.7 1.0% 99% Pass Pass 20 4/26 1 Grade Sewer Service Backfill - Block 1 - Lot 9 A 14.2% 111.7 2.2% 22 4/26 3 Grade Sewer Service Backfill - Block 1 - Lot 11 A 13.0% 111.9 1.0% 96% Pass Pass 23 4/26 4 Grade Sewer Service Backfill - Block 1 - Lot 12 A 12.4% 115.0 0.4% 99% Pass Pass 97% Pass Pass 25 4/26 6 Grade Sewer Service Backfill - Block 1 - Lot 14 A 14.5% 111.0 2.5% 96% Pass Pass 24 4/26 5 Grade Sewer Service Backfill - Block 1 - Lot 13 A 13.3% 112.4 1.3% 95% Pass Pass 27 4/26 8 Grade Sewer Service Backfill - Block 1 - Lot 16 A 11.1% 115.0 -0.9% 99% Pass Pass 26 4/26 7 Grade Sewer Service Backfill - Block 1 - Lot 15 A 15.0% 110.3 3.0% 28 4/26 9 Grade Sewer Service Backfill - Block 1 - Lot 17 A 12.2% 113.2 0.2% 98% Pass Pass 29 4/26 10 Grade Sewer Service Backfill - Block 1 - Lot 18 A 12.9% 114.8 0.9% 99% Pass Pass 96% Pass Pass 31 4/26 12 Grade Sewer Main Backfill - MH 1-4.10 - 15' N A 15.0% 110.8 3.0% 96% Pass Pass 30 4/26 11 -3' Sewer Main Backfill - MH 1-4.11 - 1' N A 14.2% 111.5 2.2% 96% Pass Pass Procedure D-698 Compaction Requirement 95% Min Moisture Content Requirement -1 to +3% Optimum Moisture Content (%) 12.0% Maximum Dry Density (pcf) 116.0 Compaction Requirement Proctor ID: A 113.9 1.0% 98% Pass Pass 97% Pass Pass 66 5/13 19 Grade Retest #62 A 13.0% Pass 65 5/13 18 Grade Water Service Backfill - Block 1 - Lot 9 A 12.7% 113.0 0.7% A 11.0% 115.0 -1.0% 99% Pass 111.2 2.4% 96% Pass Pass 64 5/13 17 Grade Water Service Backfill - Block 1 - Lot 8 92% Pass *FAIL* 63 5/13 16 Grade Water Service Backfill - Block 1 - Lot 7 A 14.4% Pass 62 5/13 15 Grade Water Service Backfill - Block 1 - Lot 6 A 12.2% 106.6 0.2% A 14.8% 112.6 2.8% 97% Pass 115.0 -0.8% 99% Pass Pass 61 5/13 14 Grade Water Service Backfill - Block 1 - Lot 5 99% Pass Pass 60 5/13 13 Grade Water Service Backfill - Block 1 - Lot 4 A 11.2% Pass 59 5/13 12 Grade Water Service Backfill - Block 1 - Lot 3 A 14.0% 114.4 2.0% A 14.5% 112.3 2.5% 97% Pass 112.7 2.3% 97% Pass Pass 58 5/13 11 Grade Water Service Backfill - Block 1 - Lot 2 99% Pass Pass 57 5/13 10 Grade Water Service Backfill - Block 1 - Lot 1 A 14.3% Pass 56 5/13 9 -2' Water Service Backfill - Block 1 - Lot 9 A 12.2% 115.0 0.2% A 12.3% 112.8 0.3% 97% Pass 112.2 0.2% 97% Pass Pass 55 5/13 8 -2' Water Service Backfill - Block 1 - Lot 8 98% Pass Pass 54 5/13 7 -2' Water Service Backfill - Block 1 - Lot 7 A 12.2% Pass 53 5/13 6 -2' Water Service Backfill - Block 1 - Lot 6 A 15.0% 113.7 3.0% A 12.7% 113.2 0.7% 98% Pass 114.9 -0.9% 99% Pass Pass 52 5/13 5 -2' Water Service Backfill - Block 1 - Lot 5 98% Pass Pass 51 5/13 4 -2' Water Service Backfill - Block 1 - Lot 4 A 11.1% Pass 50 5/13 3 -2' Water Service Backfill - Block 1 - Lot 3 A 12.9% 113.1 0.9% A 14.5% 111.8 2.5% 96% Pass 114.5 0.0% 99% Pass Pass 49 5/13 2 -2' Water Service Backfill - Block 1 - Lot 2 98% Pass Pass 48 5/13 1 -2' Water Service Backfill - Block 1 - Lot 1 A 12.0% Pass 47 5/3 9 Grade Water Main Backfill - Vicot - 300' N of Comet A 12.9% 114.2 0.9% A 11.1% 115.0 -0.9% 99% Pass 113.9 0.0% 98% Pass Pass 46 5/3 8 Grade Water Main Backfill - Vicot - 260' N of Comet 99% Pass Pass 45 5/3 7 Grade Water Main Backfill - Vicot - 110' N of Comet A 12.0% Pass Procedure D-698 Compaction Requirement 95% Min Moisture Content Requirement -1 to +3% Optimum Moisture Content (%) 12.0% Maximum Dry Density (pcf) 116.0 Compaction Requirement Proctor ID: A 96% Pass Pass Pass 84 5/14 18 Grade Water Service Backfill - Block 1 - Lot 18 A 14.4% 111.3 2.4% A 13.0% 112.7 1.0% 97% Pass 115.0 -0.3% 99% Pass Pass 83 5/14 17 Grade Water Service Backfill - Block 1 - Lot 17 98% Pass Pass 82 5/14 16 Grade Water Service Backfill - Block 1 - Lot 16 A 11.7% Pass 81 5/14 15 Grade Water Service Backfill - Block 1 - Lot 15 A 12.0% 113.2 0.0% A 14.8% 110.3 2.8% 95% Pass 111.1 2.5% 96% Pass Pass 80 5/14 14 Grade Water Service Backfill - Block 1 - Lot 14 96% Pass Pass 79 5/14 13 Grade Water Service Backfill - Block 1 - Lot 13 A 14.5% Pass 78 5/14 12 Grade Water Service Backfill - Block 1 - Lot 12 A 14.8% 110.9 2.8% A 12.7% 114.8 0.7% 99% Pass 115.0 0.0% 99% Pass Pass 77 5/14 11 Grade Water Service Backfill - Block 1 - Lot 11 97% Pass Pass 76 5/14 10 Grade Water Service Backfill - Block 1 - Lot 10 A 12.0% Pass 75 5/14 9 -2' Water Service Backfill - Block 1 - Lot 18 A 12.3% 113.0 0.3% A 11.3% 113.5 -0.7% 98% Pass 114.9 -0.5% 99% Pass Pass 74 5/14 8 -2' Water Service Backfill - Block 1 - Lot 17 98% Pass Pass 73 5/14 7 -2' Water Service Backfill - Block 1 - Lot 16 A 11.5% Pass 72 5/14 6 -2' Water Service Backfill - Block 1 - Lot 15 A 12.8% 114.2 0.8% A 12.0% 115.0 0.0% 99% Pass 112.0 1.9% 97% Pass Pass 71 5/14 5 -2' Water Service Backfill - Block 1 - Lot 14 98% Pass Pass 70 5/14 4 -2' Water Service Backfill - Block 1 - Lot 13 A 13.9% Pass 69 5/14 3 -2' Water Service Backfill - Block 1 - Lot 12 A 14.1% 114.2 2.1% A 15.0% 110.8 3.0% 96% Pass 114.7 0.4% 99% Pass Pass 68 5/14 2 -2' Water Service Backfill - Block 1 - Lot 11 Density Moisture Compaction 67 5/14 1 -2' Water Service Backfill - Block 1 - Lot 10 A 12.4% Number Number ID Test Test Proctor Moisture Moisture Variability Percent Compaction Field Results Dry (Pass/Fail) Material Tested and Location Project Date Daily Depth Fort Collins, Colorado Project # 19-2026 May 2019 Field Moisture/Density Testing Summary EAST RIDGE PHASE 2 44 5/3 6 Grade Water Main Backfill - Vicot - 45' N of Comet A 12.2% 115.0 0.2% A 14.5% 112.5 2.5% 97% Pass 112.7 2.3% 97% Pass Pass 43 5/3 5 -2' Water Main Backfill - Vicot - 315' N of Comet 99% Pass Pass 42 5/3 4 -2' Water Main Backfill - Vicot - 275' N of Comet A 14.3% Pass 41 5/3 3 -2' Water Main Backfill - Vicot - 140' N of Comet A 12.1% 115.0 0.1% A 13.0% 111.1 1.0% 96% Pass 110.8 2.3% 96% Pass Pass 40 5/3 2 -2' Water Main Backfill - Vicot - 85' N of Comet Density Moisture Compaction 39 5/3 1 -2' Water Main Backfill - Vicot - 15' N of Comet A 14.3% Number Number ID Test Test Proctor Moisture Moisture Variability Percent Compaction Field Results Dry (Pass/Fail) Material Tested and Location Project Date Daily Depth Fort Collins, Colorado Project # 19-2026 May 2019 Field Moisture/Density Testing Summary EAST RIDGE PHASE 2 33 4/26 14 Grade Sewer Main Backfill - MH 1-4.11 - 100' S A 12.8% 112.6 0.8% 97% Pass Pass 32 4/26 13 -0.5' Sewer Main Backfill - MH 1-4.10 - 95' S A 12.5% 111.9 0.5% 34 4/26 15 -2' Sewer Main Backfill - MH 1-4.11 - 25' S A 12.2% 111.9 0.2% 96% Pass Pass 35 4/26 16 -1' Sewer Main Backfill - MH 1-4.10 - 30' N A 15.0% 110.3 3.0% 95% Pass Pass 96% Pass Pass 37 4/26 18 Grade Sewer Main Backfill - MH 1-4.10 - 25' S A 12.8% 111.2 0.8% 96% Pass Pass 36 4/26 17 Grade Sewer Main Backfill - MH 1-4.10 - 50' N A 14.5% 111.2 2.5% 38 4/26 19 Grade Sewer Main Backfill - MH 1-4.9 - 5' S A 12.5% 113.7 0.5% 98% Pass Pass Compaction Requirement Proctor ID: A Moisture Content Requirement -1 to +3% Optimum Moisture Content (%) 12.0% Maximum Dry Density (pcf) 116.0 Procedure D-698 Compaction Requirement 95% Min