September 27, 2013
Chadrick Martinez
Fort Collins Housing Authority
1715 W. Mountain Ave.
Fort Collins, CO 80521
RESPONSE COMMENTS - CONSULTANT TEAM; OCTOBER 21, 2013
RE: Redtail Ponds Permanent Supportive Housing (Affordable Housing), PDP130030, Round Number 1
Please see the following summary of comments from City staff and outside reviewing agencies for your
submittal of the above referenced project. If you have questions about any comments, you may contact the
individual commenter or direct your questions through the Project Planner, Jason Holland, at 970-224-6126
or jholland@fcgov.com.
Comment Summary:
Department: Current Planning
Contact: Jason Holland, 970.224.6126, jholland D,fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 09/25/2013
In terms of building color, the project is in proximity to natural habitat and also must comply with
the multi -family design standards. Staffs recommendation to satisfy these standards is to utilize
a color palette that is warmer and more natural, in order to harmonize within the natural setting
and the existing office buildings to the south. A contrast of traditional materials/colors with the
contemporary building would be appropriate. [SC]: Colors modified per recommendation.
Comment Number: 2 Comment Originated: 09/25/2013
Building Materials: Please submit an exhibit showing an accurate depiction of all proposed
material colors and textures. This can be done with high resolution photographs of materials
and color samples as well as photographs of the materials on existing buildings. Include color
and material information for the HVAC units shown on the building elevations. The individual
HVAC units need to blend in and be as inconspicuous as possible. Recent approved Banner
Health plans are a good format example. Please incorporate color elevations directly in to the
2436 drawings instead of separate 11 x 17 pages. [SC]: Presentation provided per request.
shown. RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted. `
Comment Number: 14 Comment Originated: 09/24/2013
09/24/2013: Please label all properties surrounding this Plat. See redlines.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Comment Number: 15 Comment Originated: 09/25/2013
09/25/2013: Please label the right of way widths and how they were dedicated. See redlines.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Comment Number: 16 Comment Originated: 09/25/2013
09/25/2013: Please add a note addressing the offsite sight distance easement(per Retail
Subdivision) at the northwest corner of the property, to be vacated by separate document IF
this sight distance easement is no longer needed and IF it was ever dedicated to begin with.
See redlines. RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Comment Number: 17 Comment Originated: 09/25/2013
09/25/2013: Please show an additional tie distance for the 20' emergency access easement.
See redlines. RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Comment Number: 18 Comment Originated: 09/25/2013
09/25/2013: Please add the square footage and use to all Lots & Tracts. See redlines.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Comment Number: 19 Comment Originated: 09/25/2013
09/25/2013: Please make all bearings to read the same direction. See redlines.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Comment Number: 20 Comment Originated: 09/25/2013
09/25/2013: Please label the Point Of Beginning. See redlines.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Comment Number: 21 Comment Originated: 09/25/2013
09/25/2013: Please show and label all dimensions between the monuments shown. See
redlines. RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Comment Number: 22 Comment Originated: 09/25/2013
09/25/2013: Do calculated positions need to be shown along the east line of Section 2? See
redlines. RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Topic: Site Plan
Comment Number: 23 Comment Originated: 09/25/2013
09/25/2013: Please change the legal description to match the Subdivision Plat. See redlines.
[SC]: Revised.
Comment Number: 24 Comment Originated: 09/25/2013
09/25/2013: Please move all of the "date" text over to the date line on sheet 1. See redlines.
[SC]: Revised.
Comment Number: 25 Comment Originated: 09/25/2013
09/25/2013: Please correct the typos in the titles in the index on sheet 1. See redlines.
[SC]: Revised.
Comment Number: 26 Comment Originated: 09/25/2013
09/25/2013: There are 2 sheets in the Lighting Plans. Please add sheet E1.2 to the index on
sheet 1. See redlines. [SC]: Revised.
Comment Number: 27 Comment Originated: 09/25/2013
09/25/2013: There are line over text issues on sheets LS11 & LS12. See redlines.
WILL COMPLY
' Comment Number: 28 Comment Originated: 09/25/2013
09/25/2013: There are text over text issues on sheet LS11. See redlines.
WILL COMPLY
Department: Traffic Operation
Contact: Ward Stanford, 970.221.6820, wstanford(&-fcgov.com
Topic: Construction Drawings
Comment Number: 1 Comment Originated: 09/24/2013
09/24/2013: Please include an R1-1 (Stop) with street name sign above and a W44P warning
sign (Cross Traffic Does Not Stop) below.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Topic: Traffic Impact Study
Comment Number: 2
09/24/2013: TIS is accepted.
Department: Water Conservation
Contact: Eric Olson, 970.221.6704, eolson -fcgov.com
Topic: Landscape Plans
Comment Originated: 09/24/2013
Comment Number: 1 Comment Originated: 10/08/2013
10/08/2013: Russian Sage (Perovskia Atriplicifolia) is no longer on the Fort Collins Plant List -
Please find a suitable replacement.
PLANT WAS NOT USED AND HAS BEEN REMOVED FROM LIST
Department: Zoning
Contact: Peter Barnes, 970.416.2355, pbarnes(a0,fcpov.com
Topic: Building Elevations
Comment Number: 1 Comment Originated: 09/17/2013
09/17/2013: Label the height of the building from grade to the tallest point of the building.
[SC]: Dimension provided.
Comment Number: 2 Comment Originated: 09/17/2013
09/17/2013: Add a note to either the buidling elevation drawings or to the site plan indicating
that vents, flues, meters, conduit, PTAC units, mechanical equipment, etc., will be painted to
match the building or will be screened from view. [SC]: SC to comply.
Topic: General
Comment Number: 8 Comment Originated: 09/17/2013
09/17/2013: Provide a detail drawing of the fence and the bike chalet. [SC]: See building materials.
Topic: Landscape Plans
Comment Number: 7 Comment Originated: 09/17/2013
09/17/2013: Add a note to the 'Landscape Notes', stating something to the effect that all
landscape improvements are required to be completed prior to the issuance of a certificate of
occupancy, or financially guaranteed by a bond, letter of credit or escrow in the amount of
125% of the cost of a written estimate from the landscape contractor in the event the
landscaping isn't completed. WILL COMPLY
Topic: Site Plan
Comment Number: 3 Comment Originated: 09/17/2013
09/17/2013: Show the distance from the bike chalet to the south lot line. [SC]: Dimension provided.
Comment Number: 4 Comment Originated: 09/17/2013
09/17/2013: Show the parking stall and drive aisle dimensions. [SC]: Dimension provided.
Comment Number: 5 Comment Originated: 09/17/2013
09/17/2013: the site plan legend calls out a bike rack (BR) and light poles (LP), but I couldn't
find them on the plan. Please show the locations. [SC]: Labels provided.
Comment Number: 6 Comment Originated: 09/17/2013
09/17/2013: The conceptual review comment letter states that trash and recycling are stored
within the building. Please add a note to the "General Notes" explaining that. [SC]: Notes provided.
Q orf 51� o6ka;p .ems bc�
�c ►�.pr 6� �c � ►�Al1W r
Q rff e>u� V-W& V yU- � �,(� 11"o
0V fvvc� pro"�- �� qj�f
('i vo+?p
END OF COMMENTS
s; k
�
AP
i C
ffd,�
June 28, 2013
Steve Steinbicker
Architecture West, LLC
4710 South College Avenue
Fort Collins, CO 80525
Re: Redtail Ponds Affordable Housing
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6750
970.224.6134 - fax
fcgov.com
RESPONSES, AS NOTED, SEPTEMBER 10, 2013
Description of project: This is a request to construct a new multifamily affordable housing development
located between South College Avenue and the intersection of Fossil Boulevard and Conejos Road
(primary parcel# 96024-17-008). 60 units of affordable housing (permanent supportive housing) are planned
in a 4-story building. Recreation space in an interior courtyard and a community garden are also planned.
The site is located in the General Commercial (C-G) Zone District and the Transit Oriented Development
(TOD) Overlay Zone. Multifamily projects with more than 50 units are subject to Planning & Zoning Board
(Type 2) review.
Please see the following summary of comments regarding the project request referenced above. The
comments offered informally by staff during the Conceptual Review will assist you in preparing the detailed
components of the project application. Modifications and additions to these comments may be made at the
time of formal review of this project. If you have any questions regarding these comments or the next steps in
the review process, you may contact the individual commenter or direct your questions through the Project
Planner, Jason Holland, at 970-224-6126 or jholland@fcgov.com.
Comment Summary:
Department: Zoning
Contact: Noah Beals, 970.416-2313, nbeals0fcgov.com
1. Land Use Code (LUC) Section 4.21(B)(2)A. Residential use containing more than 50 dwelling units is
subject to a TYPE 2 Review.lf the supportive programming spaces are for the residents only than this a
Multi -Family project.
Mixed -else -dwelling— NIA, SUPPORTIVE PROGRAMMING SPACES ARE FOR THE
RESIDENTS ONLY AND THE PROJECT WILL BE DEFINED AS A MULTI -FAMILY PROJECT.
2. LUC 4.21(C) Maximum building height shall be 4 stories.
NOTED, BUILDING IS 4 STORIES, SEE ACHITECTURAL BUILDING ELEVATIONS.
3. LUC 3.10.3(A) Primary commercial and residential building entrances shall face streets, connecting
walkways, plazas, parks or similar outdoor spaces, but not parking lots. Buildings shall face all street
frontages to the maximum extent feasible, with highest priority given to east -west streets that lead from
transit stations to destinations.
It's not clear how this is being met
ALTHOUGH WE BELIEVE WE ARE MEETING THIS STANDARD WITH THE STREET LIKE PRIVATE
DRIVE DESIGN,A MODIFICATION REQUEST IS PROVIDED UNDER SEPARATE DOCUMENT.
LUC 3.10..3(B) At least one (1) prominent or central location within each transit station area shall include a
convenient outdoor open space or plaza with amenities such as benches, monuments, kiosks or public
art. This feature and its amenities shall be placed adjacent to a transit station, to the extent reasonably
feasible. NOTED, MULTIPLE OUTDOOR SPACES AND AMENITIES PROVIDED, REF; SITE PLAN.
LUC 3.10.3(C) To the extent reasonably feasible, buildings and extensions of buildings shall be
designed to form outdoor spaces such as courtyards, plazas, arcades, terraces, balconies and decks
for residents' and workers' use and interaction, and to integrate the development with the adjacent
physical context. To the extent reasonably feasible, a continuous walkway system linking such outdoor
spaces shall be developed, and shall include coordinated linkages between separate developments.
NOTED, SEE ARCHITECTURAL SITE PLAN.
4. LUC 3.10.4(A) Developments shall provide formal streetscape improvements which shall include
sidewalks having street trees in sidewalk cutouts with tree grates, planters or other appropriate treatment
for the protection of pedestrians, and shall provide seating and pedestrian light fixtures. Specific design
details shall be subject to approval by the City Engineer in accordance with the design criteria for streets.
COMMENT NOTED, REFER TO SITE PLAN AND LANDSCAPE PLANS
LUC 3.10.4(C) Off-street parking shall be located only behind, above or below street -facing buildings. No
parking will be allowed between the street and the front or side of a building.
NOTED. SEE ARCHITECTURAL SITE PLAN.
5. LUC 3.10.5(B) Flat -roofed buildings shall feature three-dimensional cornice treatment on all walls facing
streets or connecting walkways, or a rail at the top of the wall of a usable rooftop deck, unless the top
floor is stepped back to form a usable roof terrace area. A single continuous horizontal roofline shall not
be used on one-story buildings. Accent roof elements or towers may be used to provide articulation of
the building mass. To the maximum extent feasible, a minimum pitch of 6:12 shall be used for gable and
hipped roofs. Where hipped roofs are used alone, the minimum pitch shall be 4:12.
NOTED. SEE ARCHITECTURAL ELEVATIONS.
LUC 3.10.5(C)(5) Exterior building materials shall not include smooth -faced concrete block, untreated or
unpainted tilt -up concrete panels or prefabricated steel panels
NOTED. SEE ARCHITECTURAL ELEVATIONS.
6. LUC 3.10.50) Walls, fences and planters shall be designed to match or be consistent with the quality of
materials, style and colors of the development. COMMENT NOTED.
7. LUC 3.8.30(C) At least 90% of the dwellings shall be located within one -quarter mile of either a
neighborhood park, privately owned park or central feature or gather place that is at least 10,000 sq ft in
size, highly visible formed by street layout, accessible to pedestrians and open to the public, and no
conflicts with storm drainage grading. THE SITE PLAN WAS PURPOSEFULLY DESIGNED TO PROVIDE
ON -SITE, INTERNAL OPEN /RECREATION & URBAN FARMING SPACES FOR THE RESIDENTS.
IN ADDITION, THE MASON TRAIL. AFFORDS ACCESS TO THE REDTAIL GROVE NATURAL
AREA THE SOUTH TRANSIT CENTER ALSO PROVIDES A GATHERING PLACE.
LUC 3.8.30(F)(6) Each multi -family dwelling shall be articulated with projections, recesses, covered
doorways, balconies, covered box or bay windows and/or other similar features, dividing large facades
and walls into human -scaled proportions similar to the adjacent single- or two-family dwellings, and shall
not have repetitive, undifferentiated wall planes. Building facades shall be articulated with horizontal
and/or vertical elements that break up blank walls of forty (40) feet or longer. Facade articulation may be
accomplished by offsetting the floor plan, recessing or projection of design elements, change in
materials and/or change in contrasting colors. Projections shall fall within setback requirements.
NOTED. SEE ARCHITECTURAL ELEVATIONS.
8. LUC 3.2.1 A landscape plan is required this should include but not limited to foundation plantings, street
trees, parking lot perimeter and interior landscaping (see section for further details).
COMMENT NOTED, REFER TO LANDSCAPE PLANS
LUC 3.2.4 A lighting plan is required this should include photometric siteplan with catalog cut -sheets.
NOTED. REFER TO PHOTOMETRIC PLANS & SPEC. DATA INFORMATION.
LUC 3.2.5 An enclosure for both trash and recycling is required. Such enclosure shall be design with
walk-in access without having to open the main service gate and located on a concrete pad at least 20ft
from a public sidewalk.
NOTED. SEE ARCHITECTURAL SITE PLAN.
TRASH AND RECYCLING IS STORED WITHIN THE BUILDING.
9. LUC 3.5.1(I) Mechanical/utility equipment (vents, flues, meters, boxes, conduit, transformer, ac/rtu...)
locations shall be identified on the plans with notes on how such equipment is screened and painted.
NOTED. SEE ARCHITECTURAL DRAWINGS.
10. LUC 3.2.2(K)(1)(a)1. Multi -family residential has no maximum or minimum parking requirement in the TOD
overlay district. NOTED.
LUC 3.2.2(L) When off street parking is provide standard stall dimensions are 19'x9' and two-way drive
aisles are 24ft. NOTED. SEE ARCHITECTURAL SITE PLAN.
LUC 3.2.2(K)(5) Accessibility spaces are required and at least one should be van accessible (8ft wide
stall adjoined to 8ft wide loading area) NOTED AND PROVIDED. SEE ARCHITECTURAL SITE PLAN.
LUC 3.2.2(C)(4) Multi -family is required to provide one bicycle space per bedroom. At least 60% of
those spaces shall be enclosed and 40% fixed. NOTED. SEE ARCHITECTURAL SITE PLAN.
11. LUC 3.2.2(C)(5) Direct walkway access is required from pedestrian entrance to the public sidewalk.
COMMENT NOTED, REFER TO SITE PLAN AND LANDSCAPE PLANS
12. LUC 3.5.3 This section also applies if this is considered a Mixed -Use -dwellieg. NOT APPLICABLE.
Department: Water -Wastewater Engineering
Contact: Roger Buffington, 970-221-6854, rbuffingtonc&fcgov.com
Water and wastewater services for this site are provided by the Fort Collins -Loveland Water District and
the South Fort Collins Sanitation District. The Districts can be contacted at (970) 226-3104.
Comment noted.
Department: Stormwater Engineering
Contact: Glen Schlueter, 970.224-6065, gschlueter0fcgov.com
1. A drainage report, erosion control report, and construction plans are required and they must be prepared
by a Professional Engineer registered in Colorado. The drainage report must address the four -step
process for selecting structural BMPs. Standard operating procedures (SOPs) for all onsite drainage
facilities need to be prepared by the drainage engineer and there is a final site inspection required when
the project is complete and the maintenance is handed over to an HOA or another maintenance
organization. The erosion control report requirements are in the Fort Collins Stormwater Manual, Section
1.3.3, Volume 3, Chapter 7 of the Fort Collins Amendments. If you need clarification concerning this
section, please contact the Erosion Control Inspector, Jesse Schlam at 224-6015 or jschlam@fcgov.com.
Comment noted.
2. The same drainage concepts can be followed as in the approved Redtail Ponds drainage study as far as
detention and water quality treatment with the exception of the LID requirements in the next two
comments. Comment noted.
3. It doesn't appear the water quality pond is still part of the plan. Fifty percent of the site runoff is still
required to be treated using the standard water quality treatment as described in the Fort Collins
Stormwater Manual, Volume 3 - Best Management Practices (BMPs).
(http://www.fcgov.com/utilities/business/builders-and-developers/development-forms-guidelines-regulati
ons/stormwater-criteria) Extended detention is the usual method selected for water quality treatment;
however the use of any of the BMPs is encouraged. Permeable pavers and bioswele will be used to treat
for water quality. Additional runoff from the site will be conveyed to the existing pond to the East.
4. Low Impact Development (LID) requirements went into effect March 11, 2013. These require a higher
degree of water quality treatment for 50% of the new impervious area and 25% of new paved areas must
be pervious. Please contact Basil Hamdan at 224-6035 or bhamdan@fcgov.com for more information.
There is also more information on the EPA web site at: http://water.epa.gov/polwaste/green/bbfs.cfm?
goback=.gde 4605732_member 219392996. The bio-swale may meet some of the LID requirements but
please contact Basil Hamdan before submitting a PDP to confirm if all the water quality requirements are
being met. Project has been reviewed with Basil and LID requirements will be met with permeable
pavers and bioswales.
5. The drainage outfall for the site is still the curb and gutter of the frontage road. Since this is a new
proposal the street capacity will need to be verified in the drainage report. The majority of the site runoff will
be directed east to the existing curb and gutter along Frontage Rd. A stormwater detention pond is
proposed to capture a majority of the developed runoff and detain for the 100yr storm event with either a 5
or 10 year historic release rate. The developed flow to frontage Rd. will be less than existing, therefore we
see no need to analyze the street capacity. See preliminary drainage memo attached.
6. The city wide Stormwater development fee (PIF) is $6,390.00/acre ($0.1467/sq.-ft.) for new impervious
area over 350 sq.-ft., and there is a $1,045.00/acre ($0.024/sq.-ft.) review fee. No fee is charged for
existing impervious area. These fees are to be paid at the time each building permit is issued.
Information on fees can be found on the City's web site at
http://www.fcgov.com/utilities/business/builders-and-developers/plant-investment-development-fees or
contact Jean Pakech at 221- 6375 for questions on fees. There is also an erosion control escrow
required before the Development Construction permit is issued. The amount of the escrow is
determined by the design engineer, and is based on the site disturbance area, cost of the measures, or
a minimum amount in accordance with the Fort Collins Stormwater Manual. Comment noted.
7. The design of this site must conform to the drainage basin design of the Fossil Creek Basin Master
Drainage Plan as well the Fort Collins Stormwater Manual. Comment noted.
Department: Fire Authority
Contact: Jim Lynxwiler, 970-416-2869, jlynxwiler@poudre-fire.or4
1. GENERAL COMMENTS
The geographical limitations of the site combined with the current site plan, provides for fire access only
on the west side of the proposed building. This "out of access" condition will require further discussion
with the design team in order to resolve these concerns. The intent of the fire code shall prevail. Any
deviation from the code or offsetting measures proposed for the site shall be reviewed and approved by
the Fire Marshal. Comment noted.
2. FIRE LANES
Fire Lanes shall be provided to within 150' of all portions of the building, as measured by an approved
route around the exterior of the building. When fire lanes cannot be provided, the fire code official is
authorized to increase the dimension of 150 feet if the building is equipped throughout with an approved,
automatic fire -sprinkler system. 2006 International Fire Code 503.1.1 Comment noted.
FIRE LANE SPECIFICATIONS
A fire lane plan shall be submitted for approval prior to installation. In addition to the design criteria
already contained in relevant standards and policies, any new fire lane must meet the following general
requirements:
> Shall be designated on the plat as an Emergency Access Easement.
> Maintain the required 20 foot minimum unobstructed width* & 14 foot minimum overhead clearance.
> Be designed as a flat, hard, all-weather driving surface capable of supporting 40 tons.
> The required turning radii of a fire apparatus access road shall be a minimum of 25 feet inside and 50
feet outside.
> Be visible by painting or signage, and maintained unobstructed at all times.
2006 International Fire Code 503.2.3, 503.2.4, 503.2.5, 503.3, 503.4 and Appendix D; FCLUC 3.6.2(B)2006
and Local Amendments.
`STRUCTURES EXCEEDING 30' (OR THREE OR MORE STORIES) IN HEIGHT
In order to accommodate aerial fire apparatus access, required fire lanes shall be 30 foot wide minimum
on at least one long side of the building. At least one of the required access routes meeting this
condition shall be located within a minimum of 15 feet and a maximum of 30 feet from the building, and
shall be positioned parallel to one entire side of the building. 2006 International Fire Code Appendix D;
Poudre Fire Authority Administrative Policy 85-5 Comments noted.
3. TURNING RADII
The required turning radii of a fire apparatus access road shall be a minimum of 25 feet inside and 50 feet
outside. International Fire Code 503.2.4 and Local Amendments Comment noted.
4. ROOF ACCESS
New buildings four or more stories in height shall be provided with a stairway to the roof. Stairway access
to the roof shall be in accordance with IFC 1009.12. Such stairways shall be marked at street and floor
levels with a sign indicating that the stairway continues to the roof. 2006 International Fire Code 504.3
NOTED. SEE ARCHITECTURAL PLANS.
5. WATER SUPPLY
Hydrant spacing and flow must meet minimum requirements based on type of occupancy.
Commercial Hydrants to provide 1,500 gpm at 20 psi residual pressure, spaced not further than 300 feet
to the building, on 600-foot centers thereafter.
2006 International Fire Code 508.1 and Appendix B Comment noted.
6. RESIDENTIAL AUTOMATIC FIRE SPRINKLERS
An automatic sprinkler system installed in occupancies in accordance with Section 903.3 shall be
provided throughout all buildings with a Group R (Residential) fire area. Exceptions: Detached one and
two-family dwellings and multiple single-family dwellings (townhomes) not more than three stories above
grade plane in height with a separate means of egress. 2006 International Fire Code 903.2.7
NOTED. WILL COMPLY.
BALCONIES AND DECKS
Sprinkler protection shall be provided for exterior balconies, decks, and ground floor patios of dwelling
units where the building is of Type V construction.
2006 International Fire Code 903.3.1.2.1
NOTED. THERE ARE BALCONIES AND SPRINKLER PROTECTION WILL BE PROVIDED._ THERE
ARE NO GROUND FLOOR PATIOS OF DWELLING UNITS. BUILDING IS OF TYPE V
CONSTRUCTION.
FDC
Fire Department Connections shall be installed in accordance with NFPA standards. Fire departmen
full visible and recognizable from the street
connections shall be located on the street side of buildings, Y b the fire
or nearest point of fire department vehicle access. The location of the FDC shall be approvedY
department.
2006 International Fire Code 912.2 NOTED. WILL COMPLY.
KEY BOXES REQUIRED
Poudre Fire Authority requires at least one key box ("Knox Box") to be mounted in approved location(s)
on every new building equipped with a required fire sprinkler or fire alarm system. The top shall not be
higher than 6 feet above finished floor.
2006 International Fire Code 506.1 and Poudre Fire Authority Bureau Policy 88-20
NOTED. A KNOX BOX WILL BE PROVIDED IN AN APPROVED LOCATION IN CONSULTATION
WITH POUDRE FIRE AUTHORITY.
7. FIRE STANDPIPE SYSTEM
ildings and structures in accordance with Section 905 or
Standpipe systems shall be provided in new bu
the 2006 International Fire Code. Approved standpipe systems shall be installed throughout buildings
where the floor level of the highest story is located more than 30 feet above the lowest level of fire
department vehicle access. The standpipe system shall be capable of supplying at minimum of 100 psi
to the top habitable floor. An approve fire pump may be required to achieve this minimum pressure.
2006 International Fire Code Sections 905 and 913 NOTED. WILL COMPLY.
8. PREMISE IDENTIFICATION
New and existing buildings shall be plainly identified. Address numbers shall be visible from the street
fronting the property, plainly visible, and posted with a minimum of six-inch numerals on a contrasting
background.
2006 International Fire Code 505.1 NOTED.
9. PUBLIC -SAFETY RADIO AMPLIFICATION SYSTEM 000 square feet will
New buildings or building additionsthat
'Iding to be greater than systemevaIuation after the core/shell but prior to
require a fire department, emergency communication
final build out. For the purposes of this section, fire walls shall not be used to define separate buildings.
Where adequate radio coverage cannot be established within a building, public -safety radio amplification
systems shall be
rdance with criteria established by the Poudre Fire Authority. Poudre Fire
designed and installed in acco
Authority Bureau Admin Policy #07-01 NOTED.
10. FIRE PITS
Fire pits to be supplied by natural gas only. No burning of wood or wood products allowed. The
production of smoke is prohibited. NOTED.
Comment Number: 3 Comment Originated: 09125/201 S
Staff recommends that more masonry material be used on the building facade and that the
masonry be more evenly distributed around the building, both to further articulate the massing
and to further improve the residential character of the building. An additional material such as a
stained siding might also add a warmer appearance to the building; the Baker Townhomes at
4th and Cherokee would be an example. This could be used to enhance the
traditional/contemporary contrast.
[SC]: Masonry added to East/College Ave. Elevation. RE: Elevations.
Comment Number: 4 Comment Originated: 09/27/2013
West elevation: The projected design elements used to break up the main wall plane on this
elevation are repeated uniformly to the extent that the overall elevation could benefit from
additional elements to substantially break up this uniformity. In addition to substantial elements,
the west elevation would benefit from more material variation such as the addition of plank
siding used on the east elevation. Also, please also add a dashed line to the elevations
showing where main wall plane corners intersect. A plan key map would also be helpful
adjacent to each elevation.
[SC]: Key plan provided in drawings. Uniformity of elevation addressed. RE: Elevations.
Comment Number: 5
Comment Originated: 09/27/2013
Landscape and site plans: Please provide a detail for the site fence and retaining wall showing
design, material, and color. We recommend moving the fencing north off of the top of the 3'
retaining wall, so that the wall and fence are a more layered affect.
Fence has been moved from top of wall. See Sheet LS53 for fence detail.
Comment Number: 6 Comment Originated: 09/27/2013
Provide significant additional evergreen tree and shrub material along the south property
boundary in a naturalized, layered pattern to enhance screening, transition and softer / filtered
views toward the southern facing building elevations.
Project has added three evergreen trees, in addition to the planned 47 shrubs and trees
capable of screening year round. Included in this number are the Gambel Oaks which
retain their leaves through winter.
Comment Number: 7 Comment Originated: 09/27/2013
The MAF tree symbol on the plans -- can you please clarify, this is not on the plant list.
MAF refers to Mahonia fremontii, common name Desert Holly
Comment Number: 8
Comment Originated: 09/27/2013
Landscape and site plans: please incorporate the overall site plan into the set as a cover
page, and make the more detailed site and landscape plans more readable by eliminating the
existing topo and improving the line hierarchy. Label the locations of walls on the plans and
add a +/- wall height for general reference.
WILL COMPLY
Department: Engineering Development Review
Contact: Sheri Langenberger, 970.221.6573, slanoenberger jfcgov.com
Topic: General
Comment Number: 20
Comment Originated: 09/25/2013
09/25/2013: Additional information is needed on the project to be able to calculate the
TDR Fee's for the project. I need to know the amount of nonresidential space in the building
(office space, meeting space...). Common/programming space square footage = 4,436 sf
Department: Environmental Planning
Contact: Lindsay Ex, 970-224-6143, lex@fcaov.com
1. An Ecological Characterization Study is required by Section 3.4.1 (D)(1) as the site is within 500 feet of a
known natural habitat (wetlands). Please note the buffer zone standards range from 50 -100' for these
features, depending on the size of the wetlands, as identified in Section 3.4.1(E) of the Land Use Code,
as you proceed with your site design process. Please note that the Ecological Characterization Study is
due a minimum of 10 days prior to the PDP submittal. COMMENT NOTED, REFER TO SUBMITTED ECS.
2. Within the buffer zone, according to Article 3.4.1(E)(1)(g), the City has the ability to determine if the
existing landscaping within the buffer zone is incompatible with the purposes of the buffer zone. Please
ensure that your ECS discusses the existing vegetation and identifies potential restoration options. If it is
determined to be insufficient, then restoration and mitigation measures will be required.
COMMENT NOTED, REFER TO SUBMITTED ECS.
3. With respect to lighting, the City of Fort Collins Land Use Code, in Article 3.2.4(D)(6) requires that "natural
areas and natural features shall be protected from light spillage from off site sources." Thus, lighting from
the parking areas or other site amenities shall not spill over to the buffer areas. COMMENT NOTED, REFER TO
SUBMITTED PHOTOMETRIC PLAN.
4. With respect to landscaping and design, the City of Fort Collins Land Use Code, in Article 3.2.1(E)(2)(3),
requires that you use native plants and grasses in your landscaping or re landscaping and reduce bluegrass
lawns as much as possible. COMMENT NOTED, REFER TO LANDSCAPE PLANS.
5. The applicant should make note of Article 3.2.1(C) that requires developments to submit plans that "...(4)
protects significant trees, natural systems, and habitat". Note that a significant tree is defined as a tree
having DBH (Diameter at Breast Height)'of six inches or more. As several of the trees within this site may
have a DBH of greater than six inches, a review of the trees shall be conducted with Tim Buchanan, City
Forester (2216361) to determine the status of the existing trees and any mitigation requirements that could
result from the proposed development. COMMENT NOTED, REFER TO LANDSCAPE PLANS.
Department: Engineering Development Review
Contact: Tyler Siegmund, 970-221-6501, tsiegmund@fcgov.com
1. Larimer County Road Impact Fees and Street Oversizing Fees are due at the time of building permit.
Please contact Matt Baker at 224-6108 if you have any questions. Comment noted.
2. The City's Transportation Development Review Fee (TDRF) is due at the time of submittal. For additional
information on these fees, please see: httgJ/www.fcg0v-c0m/en ineeriin /dev-review.DhD Comment noted.
3. Any damaged curb, gutter and sidewalk existing prior to construction, as well as streets, sidewalks,
curbs and gutters, destroyed, damaged or removed due to construction of this project, shall be replaced
or restored to City of Fort Collins standards at the Developer's expense prior to the acceptance of
completed improvements and/or prior to the issuance of the first Certificate of Occupancy. Comment noted.
4. Please contact the City's Traffic Engineer, Joe Olson (224-6062) to schedule a scoping meeting and
determine if a traffic study is needed for this project. In addition, please contact Transportation Planning
for their requirements as well. Comment noted.
5. Any public improvements must be designed and built in accordance with the Larimer County Urban Area
Street Standards (LCUASS). They are available online at:
hftp://www.ladmer.org/en-gineedn-Q/GMARdStds/UrbanSt. Comment noted.
6. This project is responsible for dedicating any right-of-way and easements that are necessary for this
project. Comment noted.
7. Utility plans will be required and a Development Agreement will be recorded once the project is
finalized. Comment noted.
8. A Development Construction Permit (DCP) will need to be obtained prior to starting any work on the site.
Comment noted.
Department: Electric Engineering
Contact: Justin Fields, 970-224.6150, jfields0fcgov.com
1. Coordinate transformer and meter locations with Light and Power Engineering, 970-221-6700. Each unit
will need to be individually metered. Transformers need to be within 10 feet of an all-weather drive over
surface and need to have 3 feet of clearance on the back and sides, and 10 feet of clearance in the front.
The existing single phase transformer will need to be upgraded in order to serve the proposed
development. Location of utility transformer will be coordinated with Light and Power and will be located
within 10' of an accessible drive. Clearances around utility transformer will be maintained. Individual
metering will not be required for each unit per correspondence between SRB, Justin Fields and Brian
Janonis, P.E.
2. Electric development and system modifications charges will apply. An online estimator for these
charges is available at
http://www.fcgov.com/utilities/business/builders-and-developers/plant-investment-development-fees/elec
tdc-development-fee-estimator?id=2 (the charges for the clubhouse will need to be estimated under the
commercial tab). Estimate of development fees can be prepared if needed.
3. If a fire pump is required, contact Light and Power Engineering for the wiring requirements for the pump.
Fire pump size yet to be determined.
Current Planning
Contact: Jason Holland, 970-224-6126, 1hollandofcgov.com
1. Height review will be required if the building is over 40 feet in height, please refer to submittal criteria in
section 3.5.1(G). NOTED.
3. Please note the landscape standards that require tree spacing adjacent to walks and drives- 3.2.1(E).
COMMENT NOTED, REFER TO LANDSCAPE PLANS
3. The proposed development project is subject to a Type 2 (Planning and Zoning Board) review and public
hearing. The applicant for this development request is required to hold a neighborhood information
meeting prior to formal submittal of the proposal. Neighborhood meetings offer an informal way to get
feedback from your surrounding neighbors and discover any potential hiccups prior to the formal hearing.
Please contact me, at 221-6750, to assist you in setting a date, time, and location. I and possibly other
City staff, would be present to facilitate the meeting. NOTED.
4. Please see the Development Review Guide at www.fcgov.com/drg. This online guide features a color
coded flowchart with comprehensive, easy to read information on each step in the process. This guide
includes links to just about every resource you need during development review. NOTED.
5. This development proposal will be subject to all applicable standards of the Fort Collins Land Use Code
(LUC), including Article 3 General Development Standards. The entire LUC is available for your review on
the web at hftp://www.colocode.com/ftcollins/landusgALegin.htm,. NOTED.
6. If this proposal is unable to satisfy any of the requirements set forth in the LUC, a Modification of Standard
Request will need to be submitted with your formal development proposal. Please see Section 2.8.2 of
the LUC for more information on criteria to apply for a Modification of Standard. NOTED, MODIFICATION
REQUEST PROVIDED, SEE ATTACHED.
7. Please see the Submittal Requirements and Checklist at:
http://www.fcaov.com/developmentreview/agplications.php. NOTED.
8. The request will be subject to the Development Review Fee Schedule that is available in the Community
Development and Neighborhood Services office. The fees are due at the time of submittal of the required
documents for the appropriate development review process by City staff and affected outside reviewing
agencies. Also, the required Transportation Development Review Fee must be paid at time of submittal.
NOTED.
9. When you are ready to submit your formal plans, please make an appointment with Community
Development and Neighborhood Services at (970)221-6750. NOTED.
Pre -Submittal Meetings for Building Permits
Pre -Submittal meetings are offered to assist the designer/builder by assuring, early on in the
design, that the new commercial or multi -family projects are on track to complying with all of the
adopted City codes and Standards listed below. The proposed project should be in the early to
mid -design stage for this meeting to be effective and is typically scheduled after the Current
Planning conceptual review meeting.
Applicants of new commercial or multi -family proiects are advised to call 416-2341 to schedule a
pre -submittal meeting. Applicants should be prepared to present site plans, floor plans, and
elevations and be able to discuss code issues of occupancy, square footage and type of
construction being proposed.
Construction shall comply with the following adopted codes as amended:
2009 International Building Code (IBC)
2009 International Residential Code (IRC)
2009 International Energy Conservation Code (IECC)
2009 International Mechanical Code (IMC)
2009 International Fuel Gas Code (IFGC)
2009 International Plumbing Code (IPC) as amended by the State of Colorado
2011 National Electrical Code (NEC) as amended by the State of Colorado
Accessibility: State Law CRS 9-5 & ICC/ANSI Al17.1-2003.
Snow Load Live Load: 30 PSF / Ground Snow Load 30 PSF.
Frost Depth: 30 inches.
Wind Load:100- MPH 3 Second Gust Exposure B.
Seismic Design: Category B.
Climate Zone: Zone 5
Energy Code Use
1. Single Family; Duplex; Townhomes: 20091RC Chapter 11 or 2009 IECC Chapter 4
2. Multi -family and Condominiums 3 stories max: 2009 IECC Chapter 4.
3. Commercial and Multi -family 4 stories and taller: 2009 IECC Chapter 5.
Fort Collins Green Code Amendments effective starting 1-1-2012. A copy of these requirements
can be obtained at the Building Office or contact the above phone number.
NOTED, THE PROJECT WILL COMPLY WITH ALL APPLICABLE CODES & ABOVE DESIGN CRITERIA.
City of Fort Collins
Building Services
Plan Review
416-2341
y Contact: Tyler Siegmund, 970.221.6501, tsieomund fcgov.com
Topic: Construction Drawings
Comment Number: 8 Comment Originated: 09/25/2013
09/25/2013: An additional utility easement is needed where the water main and fire hydrant
extends onto the property. Currently they are in ROW but with vacation of the ROW an
easement will be needed. RESPONSE COMMENTS-JVA; OCTOBER 18, 2013 A utility easement has
been added for the watermain outside of ROW.
Comment Number: 9 , Comment Originated: 09/25/2013
09/25/2013: Please provide radii for the drive approach returns
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 A detailing grading and layout plan has been
created for the drive approach. Radii have been added.
Comment Number: 10 Comment Originated: 09/25/2013
09/25/2013: The variance request for the Fossil Blvd/Conejos intersection has been accepted
and a letter of acceptance will follow. Profile plan of the vertical alignment is needed and will
be reviewed at final plan.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Right, left and center profiles have been added for
the intersection.
Comment Number: 11 Comment Originated: 09/25/2013
09/25/2013: Please incorporate Construction Notes appendix E-1 and E-2 from the Larimer
County Urban Area Street Standards to the General Notes on sheet C0.1 of the utility plans
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Constructions notes have been added.
Comment Number: 12 Comment Originated: 09/25/2013
09/25/2013: Please show the new right of way along Conejos Rd- see redlines
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 ROW has been shown on all plans.
Comment Number: 13 Comment Originated: 09/25/2013
09/25/2013: Please label the 15ft utility easement along College Ave on sheet C2
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Easement has been labeled.
Comment Number: 14 Comment Originated: 09/25/2013
09/25/2013: Please add the standard asphalt repair note to sheets C0.2, CE1.0 in the Utility
Plans:
Limits of street cut are approximate. Final limits are to be determined in the field by the City of
Fort Collins Engineering Inspector. All repairs to be in accordance with city street repair
standards.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Note has been added.
Comment Number: 15 Comment Originated: 09/25/2013
09/25/2013: Please provide a detail for the retaining wall construction. Label the retaining wall
along College Ave on sheet C2
RESPONSE COMMENTS - JVA; OCTOBER 18,2013. See landscape plans for retaining wall detail.
Retaining wall labels have been added.
Comment Number: 16 Comment Originated: 09/25/2013
09/25/2013: Please note that the existing right-of-way on sheet C0.2 is to be vacated
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Note have been added.
Comment Number: 17 Comment Originated: 09/25/2013
09/25/2013: Sheet C2.0 references an existing light and power vault but is not shown on the
plan. Add existing vault location.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 The existing electric transformer has been added.
Topic: General
Comment Number: 1
Comment Originated: 09/25/2013
09/25/2013: The South College Corridor Plan identifies 144ft of right-of-way needed along
College Ave adjacent to this project. This development is responsible for % of the required
right-of-way, or a total of 72ft. 70.5ft currently exist so an additional 1.5ft of right-of-way is
needed along College Ave
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Additional ROW has been added.
Comment Number: 2 Comment Originated: 09/25/2013
09/25/2013: The site plan and the utility plan set are conflicting on the width of the existing
sidewalk along College Ave. The Utility plans show an existing 7ft sidewalk and this project
constructing an 8ft sidewalk for the remaining property frontage. The South College Corridor
Plan identifies 8ft sidewalk widths along College Ave. Further evaluation will be needed to
determine if the existing 7ft wide sidewalk along approximately 40ft of the property frontage will
need to be removed and replaced with an 8ft sidewalk. Please revise the site plan to show the
existing 7ft sidewalk and the new 8ft wide sidewalk to be installed with this project.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 The existing sidewalk at the southeast corner of the
site is concrete and transitions to asphalt to the north. The intention is to maintain the existing 7' wide
concrete sidewalk for approximately 40' along the property line and replace the entire section of asphalt
walk. The existing 7' wide concrete walk appears to be in good shape.
Comment Number: 3 Comment Originated: 09/25/2013
09/25/2013: A CDOT construction permit will be needed for the sanitary sewer service
connection in College Ave.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 JVA will coordinate with CDOT for a construction
permit.
Topic: Plat
Comment Number: 4
Comment Originated: 09/25/2013
09/25/2013: Please show the proposed vacation of Fossil Blvd right-of-way on the new plat. A
note will need to be added that references all easements on the original Redtail Subdivision
plat are vacated.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Comment Number: 5 Comment Originated: 09/25/2013
09/25/2013: Please reference the easement agreement recordation number for Tract I
detention pond on the plat.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Tract I is no longer required and will not be included
with the property.
Comment Number: 6 Comment Originated: 09/25/2013
09/25/2013: Add the following note to the plat: There shall be no private conditions, covenants
or restrictions that prohibit or limit the installation of resource conserving equipment or
landscaping that are allowed by Sections 12-120—12-122 of the City Code.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Comment Number: 7 Comment Originated: 09/25/2013
09/25/2013: Add the development name in the legal description on sheet 1 of the plat.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Topic: Site Plan
Comment Number: 18 Comment Originated: 09/25/2013
09/25/2013: Please add the following note to the site plan:
Any damaged curb, gutter and sidewalk existing prior to construction, as well as streets,
sidewalks, curbs and gutters, destroyed, damaged or removed due to construction of this
project, shall be replaced or restored to City of Fort Collins standards at the Developer's
expense prior to the acceptance of completed improvements and/or prior to the issuance of
the first Certificate of Occupancy. [SC]: Notes provided.
Comment Number: 19 Comment Originated: 09/25/2013
09/25/2013: Please label the retaining wall along College Ave. [SC]: Label provided.
Department: Environmental Planning
Contact: Lindsay Ex, 970.224.6143, Iex(ftc og v.com
Topic: General
Comment Number: 3
Comment Originated: 09/24/2013
09/24/2013: Please add the Natural Habitat Buffer Zone to the site, landscape and utility plans. I
am struggling to read the landscape plans, is there a way to simplify some of the linework and
details? WILL COMPLY RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Natural Habitat Buffer Zone
has been labeled.
Topic: Landscape Plans
Comment Number: 2 Comment Originated: 09/24/2013
09/24/2013: Per the ECS, additional shrubs and native trees need to be added to the
landscaping plan in order to achieve compliance with Section 3.4.1(E)(1)(g) of the Land Use
Code.
The referenced code states "The project shall be designed to enhance the natural ecological
characteristics of the site. If existing landscaping within the buffer zone is determined by the
decision maker to be incompatible with the purposes of the buffer zone, then the applicant
shall undertake restoration and mitigation measures such as regrading and/or the
replanting of native vegetation." The project boundary/property line only encroaches into
the buffer where the projects" site access connects to the City right-of-way at the northwest
portion of the site. The ECS discussion within the buffer area is actually an out parcel and
not a part of this project.
Topic: Reports - Soils, Subdrain
Comment Number: 1 Comment Originated: 09/24/2013
09/24/2013: The ECS needs to be updated to include the following information:
- Wildlife use of the area and not just the immediate site
- Any patterns of non-native vegetation on the site as described in Section 3.4.1(D)(1)(e).
ECS HAS BEEN UPDATED AND RE -SUBMITTED.
Department: Forestry
Contact: Tim Buchanan, 970.221.6361, tuchanan(&-fcgov.com
Topic: Landscape Plan
Comment Number: 1 Comment Originated: 09/25/2013
09/25/2013:
Schedule an on -site meeting with the City Forester to obtain information needed to develop an
existing tree inventory, protection and mitigation plan. WILL COMPLY
Comment Number: 2 Comment Originated: 09/25/2013
09/25/2013:
Add tree protection specifications found in LUC 3.2.1 G. WILL COMPLY
Comment Number: 3 Comment Originated: 09/25/2013
09/25/2013:
Species Changes:
Planting Ash is not recommended because of future impact from Emerald Ash Borer moving
into Colorado. REMOVED FROM LIST
Sugarberry has not proven reliably hardy in the Fort Collins area. REMOVED FROM LIST
Comment Number: 4 Comment Originated: 09/25/2013
09/25/2013:
In the plant schedule list percentages of each tree used and check that they are within the
minimum species Diversity standard. LUC 3.2.1 D 3. WILL COMPLY
Comment Number: 5 Comment Originated: 09/25/2013
09/25/2013:
Due to the utility line separation for the Sewer line some trees along College are placed in
back of the walk. Review with the utility if a small ornamental tree such as Autumn Brilliance
Serviceberry, which was used in the parkway between the sidewalks to the south of this
project, can be used on this project. If the parkway has a steep grade that could be limiting.
WILL COMPLY
Comment Number: 6 Comment Originated: 09/25/2013
09/25/2013:
The west most shade tree to the south on the entry to the parking lot does not appear to be
labeled. TREE LABELED QM, Quercus macrocarpa, common name Bur Oak
Comment Number: 7 Comment Originated: 09/25/2013
09/25/2013:
Add Standard landscape notes that address plant, quality, mulch selection and placement,
irrigation etc. In addition to those add these landscape notes. Include a note that incorporates
the separation standards in LUC 3.2.1 K.
• The soil in all landscape areas, including parkways and medians, shall be thoroughly
loosened to a depth of not less than eight (8) inches and soil amendment shall be thoroughly
incorporated into the soil of all landscape areas to a depth of at least six (6) inches by tilling,
discing or other suitable method, at a rate of at least three (3) cubic yards of soil amendment
per one thousand (1,000) square feet of landscape area.
• A permit must be obtained from the City forester before any trees or shrubs as noted on
this plan are planted, pruned or removed on the public right-of-way. This includes zones
between the sidewalk and curb, medians and other city property. This permit shall approve the
location and species to be planted. Failure to obtain this permit may result in replacing or
relocating trees and a hold on certificate of occupancy.
• The developer shall contact the City Forester to inspect all street tree plantings at the
completion of each phase of the development. All trees need to have been installed as shown
on the landscape plan. Approval of street tree planting is required before final approval of
each phase. Failure to obtain approval by the City Forester for street trees in a phase shall
result in a hold on certificate of occupancy for future phases of the development.
WILL COMPLY
Comment Number: 8
09/25/2013:
Comment Originated: 09/25/2013
Sizes of trees and shrubs should meet LUC size standards. Review with the City Planner.
ALL PLANT MATERIALS MEET OR EXCEED LUC SIZE STANDARDS FOR AFFORDABLE
HOUSING.
Department: Light And Power
Contact: Doug Martine, 970.224.6152, dmartin fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 09/23/2013
09/23/2013: The locations of the electric utility facilities will need to be coordinated with Light &
Power Engineering at (970)221-6700. The electric transformer (not shown on the utility plan) will
need to be located within 10 feet of an all-weather surface that is accessible to a utility line
truck. Also, the utility plan shows the electric line too close to the water lines. The minimum
lateral separation between water and electric is 10 feet. RESPONSE COMMENTS - JVA;
OCTOBER 18,2013 Water line has been shifted to proved 10' minimum separation.
Comment Number: 2 Comment Originated: 09/23/2013
09/23/2013: The developer will need to provide a completed Commercial Service Information
(C-1) form and a 1-line electric diagram to Light & Power Engineering. This form is available on
WWW.FCGOV.COM, or can be provided on request from Light & Power Engineering. NOTED.
Comment Number: 3
Comment Originated: 09/23/2013
09/23/2013: Electric development charges will apply. Light& Power Engineering can assist in
estimating these charges. City Code requires that individual apartments must have individual
electric meters for each unit. It also provides for the Utilities Director to grant an exception to
this requirement, which was granted on August 2, 2013. NOTED.
Comment Number: 4
Comment Originated: 09/23/2013
09/23/2013: It appears likely that a fire booster pump will be necessary. This pump must be
metered along with the main building meter. NOTED, REVIEWING WITH PFA AND ENGINEERING.
Comment Number: 5
Comment Originated: 09/23/2013
09/23/2013: After plans are final and approved, please send an AutoCad (version 2008)
drawing of the utility site plan to Terry Cox at TCOX _FCGOV.COM. NOTED.
Department: PFA
Contact: Jim Lynxwiler, 970.416.2869, lIynxwileApoudre-fire.org
Topic: General
Comment Number: 1 Comment Originated: 09/26/2013
09/26/2013: PFA continues to work off-line with the project team to resolve minor questions
and concerns. NOTED.
Comment Number: 2
Comment Originated: 09/26/2013
09/26/2013: As both stairwells will serve a roof access and areas of refuge, please be sure
that both stairwells are appropriately signed on the exterior for firefighter identification and use.
[SC]: SC to comply.
Department: Stormwater Engineering
Contact: Jesse Schlam, 970.218.2932, jschlam .fccov.com
Topic: Erosion Control
Comment Number: 1 Comment Originated: 09/17/2013
09/17/2013: The site disturbs more than 10,000 sq-ft, therefore Erosion and Sediment Control
Materials need to be submitted for FDP. The erosion control requirements are in the
Stormwater Design Criteria under the Amendments of Volume 3 Chapter 7 Section 1.3.3.
(Requirements added to the packet of Materials from Stormwater) Current Erosion Control
Materials Submitted does not meet requirements. Please submit; Erosion Control Plan, Erosion
Control Report, and an Escrow / Security Calculation. If you need clarification concerning this
section, or if there are any questions please contact Jesse Schlam 970-218-2932 or email @
jschlam@fcgov.COm RESPONSE COMMENTS - JVA; OCTOBER 18,2013 The drainage and erosion
control is still under design. The final drainage and erosion control report will be provided shortly.
Contact: Wes Lamarque, 970.416.2418, wiamarque aMcgov.com
Topic: General
Comment Number: 2 Comment Originated: 09/24/2013
09/24/2013: Per previous meetings and discussions, the development needs to meet the
detention, water quality, and LID requirements. These requirements need to be met while still
meeting the detention pond design and landscape standards.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 The drainage and LID requirements are still under
design. Water quality variance is being requested to be included with the detention volume and will be
further explained in the drainage report which will be provided shortly.
Department: Technical Services
Contact: Jeff County, 970.221.6588, 'coun_y(c0fcgov.com
Topic: Building Elevations
Comment Number: 1
09/24/2013: No comments.
Topic: Construction Drawings
Comment Originated: 09/24/2013
Comment Number: 2 Comment Originated: 09/24/2013
09/24/2013: Please change the sub -title on sheet C0.00 to match the Subdivision Plat. See
redlines. RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Comment Number: 3 Comment Originated: 09/24/2013
09/24/2013: Please change the numbering of sheet C0.00 to C0.0, to be consistent with the
rest of the plan set. See redlines. RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Comment Number: 4 Comment Originated: 09/24/2013
09/24/2013: There are line over text issues on sheets C0.2, C1.0, CD1.2, CE1.0, CE1.1, C2.0,
C3.0, CD1.0 & Figure 2. See redlines.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted
Comment Number: 5 Comment Originated: 09/24/2013
09/24/2013: There are text over text issues on sheets C1.0. See redlines.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Topic: Landscape Plans
Comment Number: 6 Comment Originated: 09/24/2013
09/24/2013: There are line over text issues on sheets LP11 & LP12. See redlines.
WILL COMPLY
Comment Number: 7 Comment Originated: 09/24/2013
09/24/2013: The title on sheet LP11 does not match the index on sheet 1 of the Site Plans.
See redlines.
WILL COMPLY
Topic: Lighting Plan
Comment Number: 8
09/24/2013: No comments.
Comment Originated: 09/24/2013
Topic: Plat
Comment Number: 9 Comment Originated: 09/24/2013
09/24/2013: Please correct the typos in the Statement Of Ownership And Subdivision. See
redlines. RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Comment Number: 10 Comment Originated: 09/24/2013
09/24/2013: Please add the Plat name to the Statement Of Ownership And Subdivision. See
redlines.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Comment Number: 11 Comment Originated: 09/24/2013
09/24/2013: Are there any Lienholders? If you are uncertain whether there are, please add a
signature block as a placeholder. There are no Lienholders
Comment Number: 12 Comment Originated: 09/24/2013
09/24/2013: Please add the note: Unless shown otherwise, all easements depicted on the
Retail Subdivision are hereby vacated with this plat.
RESPONSE COMMENTS - JVA; OCTOBER 18,2013 Comment noted.
Comment Number: 13 Comment Originated: 09/24/2013
09/24/2013: Please provide the current acceptable monument records for the aliquot comers