Cellar and Malt Storage Expansion
I have no comments on the utility plans. They look good to me, but if any changes are
made to the utility plans for any other departments need I want to see them when they are
routed again.
I verified this with Roger Buffington.
The portion of easement to be vacated that is for the private line can be vacated and
processed now. The portion to be vacated for the realignment can not be vacated until
the realignment is completed. Each easement vacation request has a TDRF of $400 for
the processing of the easement. The recording fees will also need to be provided, but that
amount will not be known until we know how many pages the document is. I would
suggest getting legals to me for both of these items now. That way the vacation for the
private line can be processed right away and the other can be prepared and ready to go
when ever the line is relocated. It will take at least 2 weeks or more for the vacation
process once I receive the legals. Time is needed for review of the legals, drafting and
review of the ordinance and approval.
The vacations do not need to be processed prior to plan approval, but will need to be
processed prior to obtaining a building permit for the structures that are located over the
easement that is to be vacated. This will mean that the permit for the Malt Storage
building can not be issued until after the sewer line is moved.
A deed of dedication for the relocated sewer line needs to be provided prior to approval
of the plans and the minor amendment. The easement dedication request has a TDRF of
$250 for the processing and review of the dedication. As with the vacations the recording
fees will also need to be provided once we know how many documents and pages there
are. Dedication language was changed and updated within the last year, so please let me
know if you need the current language.
An excavation permit will need to be issued for the public sewer work. Once the plans
are approved the contractor will need to make an application to Engineering Inspection
and get the permit approved prior to starting any work on the public portion of the
sanitary sewer.
archistructionR
June 25, 2012
www.neenan.com
Gary Lopez
City of Fort Collins
281 N. College Ave.
Fort Collins, CO 80522-0580
Subject: Response to comments for MA 120039 (bldg. permit #s B 1203125 and B 1203164)
Dear Gary,
Please see below our responses to the comments from the city regarding the New Belgium
Brewery Cellar and Malt Storage expansion. Please contact me if you have further questions or
need additional clarity.
Department: Engineering Development Review
Contact: Sheri Langenberger, 970-221-6573, slangenberger fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 05/22/2012
05/22/2012: 1 have no comments on the utility plans. They look good to me, but if any
changes are made to the utility plans for any other departments need I want to see them when
they are routed again.
Response: Plans are attached here to for reference and include sewer line slope changes
and manhole location per review with Roger Buffington.
Comment Number: 2
Comment Originated: 05/22/2012
05/22/2012: 1 verified this with Roger Buffington.
The portion of easement to be vacated that is for the private line can be vacated and
processed now. The portion to be vacated for the realignment can not be vacated until the
realignment is completed. Each easement vacation request has a TDRF of $400 for the
processing of the easement. The recording fees will also need to be provided, but that
amount will not be known until we know how many pages the document is. I would suggest
getting legals to me for both of these items now. That way the vacation for the private line can
be processed right away and the other can be prepared and ready to go when ever the line is
relocated. It will take at least 2 weeks or more for the vacation process once I receive the
legals. Time is needed for review of the legals, drafting and review of the ordinance and
approval.
Response: Application and fees were provided.
Comment Number: 3
0
Comment Originated: 05/22/2012
05/22/2012: The vacations do not need to be processed prior to plan approval, but will
need to be processed prior to obtaining a building permit for the structures that are located over v�
the easement that is to be vacated. This will mean that the permit for the Malt Storage building §v
y�
cannot be issued until after the sewer line is moved. a�
ter`
2620 E. Prospect Road, Suite 100 1 Fort Collins, CO 80525 1970.493.8747 1 Fax: 970.493.5869
��
Response: No action required.
Comment Number: 4
archistructionx
www.neenan.com
Comment Originated: 05/22/2012
05/22/2012: A deed of dedication for the relocated sewer line needs to be provided prior to
approval of the plans and the minor amendment. The easement dedication request has a
TDRF of $250 for the processing and review of the dedication. As with the vacations the
recording fees will also need to be provided once we know how many documents and Pages
there are. Dedication language was changed and updated within the last year, so please let
me know if you need the current language.
Response: Deed of Dedication information, application and fee provided.
Comment Number: 5
Comment Originated: 05/22/2012
05/22/2012: An excavation permit will need to be issued for the public sewer work. Once the
plans are approved the contractor will need to make an application to Engineering Inspection
and get the permit approved prior to starting any work on the public portion of the sanitary
sewer.
Response: Application for permit will be submitted and will be pending MA approval.
Department: Water -Wastewater Engineering
Contact: Roger Buffington, 970-221-6854, rbuffington(bfcgov.com
Topic: Construction Drawings
Comment Number: 1
Comment Originated: 05/17/2012
05/17/2012: Adjust the sewer alignment to provide 10' clear separation from the electic duct
bank. The duct bank is concrete encased but is not reinforced and not self supporting. This
will result in the sewer being offset in the easement.
Response: See attached plans confirming manhole location in reference to electric duct.
Manhole is 12' from the existing electric duct line
Topic: Easements
Comment Number: 2 Comment Originated: 05/17/2012
05/17/2012: Provide documents for the new easement for the realigned sewer.
Response: Drawings attach and legal description provided to Engineering office.
Please let me know if you need additional information or clarity.
Sincerely,
Dan Dirksen
The Neenan Company
Enc. Revised M.A. drawings