DATE: October 28, 2004 TO: Engineering Pavement
PROJECT: #29-OOJ Maple Hill Recreational Center PDP -
Type I (LUC)
All comments must be received by Ted Shepard no later than the staff
review meeting:
November 24, 2004
Note - PLEASE identify your redlines for future reference
k
Name (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
_Plat _Site _Drainage Report _Other
_Utility _Redline Utility _Landscape
9.50
PROJECT
COMMENT SHEET
Citv of Fort Collins
Current PlanninE
DATE: October 28, 2004 TO: Transp. Ping
PROJECT: 929-OOJ Maple Hill Recreational Center PDP -
Type I (LUC)
All comments must be received by Ted Shepard no later than the staff
review meeting:
November 24, 2004
Note - PLEASE identify your redlines for future reference
lCL
Name (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
I —Plat \'Site _Drainage Report _Other
Utility Redline Utility Landscape
PROJECT
COMMENT SHEET
Current Planning
DATE: October 28, 2004 TO: Technical Services
REM 'B9NOU
PROJECT: #29-OOJ Maple Hill Recreational Center PDP -
Type I (LUC)
All comments must be received by Ted Shepard no later than the staff
review meeting:
November 24, 2004 jk
Note - PLEAsE identlfv your redfi—nes for future reference
/, Bo-u�✓v�QY LcasES.
Name (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
_Plat _Site _Drainage Report _Other
_Utility _Redline Utility _Landscape
9:59 '
Project Comments Sheet
Selected Departments
City of Fort Collins
Date: November 29, 2004
Project: MAPLE HILL RECREATION CENTER PDP - TYPE I
All comments must be received by Ted Shepard in Current Planning, no later than
the staff review meeting:
November 24, 2004
Note - Please identify your redlines for future reference
Issue Contact: Katie Moore
Topic: Landscape plan
Number: 7 Created: 11/16/2004
[11/16/04] It appears that shrubs and trees are too close to the sewer and water services.
Please revise.
Topic: Phasing
Number: 28 Created: 11/29/2004
If the pool is planned to be built prior to phase 5, then re -phasing is needed so that all
adjacent streets are built with this pool, and the DA will need to be amended as well.
Topic: PI t
Number: 1 Created: 11/16/2004
[11/16/041 P 4e provide a signature line for the City Clerk
Number: 11 Created: 11/16/2004
[11/16/041 Tract A is labeled as future development, but is also dedicated in its entirety as a
drainage easement, so any future development would necessitate vacating at least a portion
of that easement. Was this the intention?
Topic: Site Plan
Number: 8 Created: 11/16/2004
[11/16/04] Why are 2 fences needed? There's one fence close to the pool and another on
the property line, with no apparent way of getting to the area in between. Was this the
intent?
The fence on the property line should be moved a minimum of 2' from the back of the walk
on Maple Hill Road.
!! 2?10Y
Date
/J CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat v, Site Drainage Report Other
-- Utility l/ Redline Utility >✓ Landscape
Page 1
Number: 9 Created: 11/16/2004
[11/16/04] Please label the ROW widths on the site plan for Maple Hill and Bar Harbor.
Topic: Utility Plans
Number: 12 Created: 11/16/2004
[11/16/04] Please include the plat as (for reference only) and do not include it in the
numbering of the sheets for the utility plan set.
Number: 13 Created: 11/16/2004
[11/16104] There are 2 options for handling the utility plans. If you want the new sheets to
form a separate new set of utility plans, that's ok, but the revised sheets need to be a part of
the original plan set, and a note on the new plans added to refer to the original Maple Hill
plans for more information. Or the new sheets could be added as new sheets to the original
Maple Hill plans along with the revised sheets and no new separate plan set would be
created.
Number: 14 Created: 11/16/2004
[11116/04] Two benchmarks are required on the cover sheet.
Number: 15 Created: 11/1612004
[11/16/04] Please review appendix E6 in LCUASS for scanability requirements and revise
plans accordingly.
Number: 16 Created: 11/16/2004
[11/16/04] The proposed mid -block ramp makes sense only if a handicapped parking stall is
designated on -street. Please show signing/striping for the stall.
Number: 17 Created: 11/1612004
[11/16/04] Grading is shown on City property. An easement might be required for this
offsite grading. Please obtain a letter of intent from Craig Foremen of Parks prior to hearing.
Once this is cleared up, then I'm ok with the project going to hearing.
Number: 18 Created: 11/16/2004
[11/16/04] The ramp proposed is for mid -block use with 'attached' walks. Please use a
standard directional ramp and include interim detail 1606 and enlarge interim detail 1607.
Number: 19 Created: 11/16/2004
[11/16/04] See redlines and utility plan checklist for any additional comments.
Number: 27 Created: 11/29/2004
Please revise phasing plans (again) to show the pool as Phase 8 to match the DA.
Page 2
REVISION
COMMENT SHEET
DATE: December 3, 2004 TO: Engineering
PROJECT: #29-OOJ Maple Hill Recreation Center, PDP —
Type I (LUC)
All comments must be received by Ted Shepard no later than the staff
review meeting:
December 15, 2004
No Comment
® Problems or Concerns (see below or attached)
**PLEASE IDENTIFY YOUR REDLINES FOR FUTURE
SCaffLot)p 14 L REFERENCE**
• 5WON old wc'� S
16I'd A+ feMvC,y" (04
P
of- (air atci�
Name (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
_Plat Site _Drainage Report _Other
_Utility _Redline Utility _Landscape
Date
9a
City of Fort Collins
Project Comments Sheet
City of Fort Collins Selected Departments
Department:
Date: December 16, 2004
Project: MAPLE HILL RECREATION CENTER PDP - TYPE I
All comments must be received by Ted Shepard in Current Planning, no later than
the staff review meeting:
December 15, 2004
Note - Please identify your redlines for future reference
Issue Contact: Katie Moore
Topic: Phasing
Number: 29 Created: 12/16/2004
[12/16/041 Please show old revision bubbles on previously revised utility plan sheets.
Topic: Utility Plans
Number: 12 Created: 11/16/2004
[12/16/041 Didn't receive a revised plat or plat redlines.
[11/16/04] Please include the plat as (for reference only) and do not include it in the
numbering of the sheets for the utility plan set.
Number: 15
[12116/04] See redlines.
[11/16/041 Please review appendix E6 in
plans accordingly.
Created: 11/16/2004
LCUASS for scanability requirements and revise
Number: 19
[12/16/04] Created: 11/16/2004
[11/16/041 See redlines and utility plan checklist for any additional comments.
«. Ile. oy
Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
✓ Plat a Site Drainage Report Other
Utility _ V Redline Utility Landscape
Page 1
Selected Issues Report
Cih, of Fori Collins
4/16/2008 Date:
MAPLE HILL 2ND REPLAT - TYPE I (LUC) AND FINAL PLAN
SELECTION CRITERIA: Status = All
ISSUES:
Department: Engineering Issue Contact: Dave Stringer
Topic: Civil Plans
Number:5 Created:1/30/2004 Resolved
[1/30/041 Need to provide more detail on Final Compliance Plans. See Redlined Bluelines,
show existing utilities as existing and/or make reference to what plans they are to be
constructed with
Topic: General
Number:9 Created:3/29/2004 Pending
[3/29/04] [3/29/04] I'm confused. Why two sets of plans, one for alley work which are
revisions to original approved plans and then another set for drainage storm water. Prefer
to have all sheets as revisions to approved plans. No additional comments
Topic: Plat
Number:4 Created:1/30/2004 Resolved
[1/30/041 Ready for hearing. Need to show corner cut in right-of-way of alley as depicted on
LCUASS detail 7-12F
Department: Traffic Operations Issue Contact: Eric Bracke
Topic: Traffic
Number:I Created:1/22/2004 Unresolved
[1/22/04] No problem from Traffic Engineering
Department: Transportation Planning
Topic: General
Number: 7
[2111/041 No comments
Issue Contact: Tom Reiff
Created:2/11/2004 Unresolved