Project Comments Sheeti.'I Selected Departments
City of Fort Collins
Department: Engineering
Date: October 13, 2004
Project:
OAKRIDGE BUSINESS PARK, 37TH FILING, HOMEWOOD SUITES -
TYPE II(LUC)
All comments must be received by Steve OR in Current Planning, no later than the
staff review meeting:
October 13, 2004
Note - Please identify your redlines for future reference
Issue Contact: Katie Moore
Topic: General
Number: 15 Created: 10/11/2004
110/11/041 Please use LCUASS Figure 7-16 to calculate the sight distance easements
needed from the street intersection and the drive intersections with Oakridge. The shading
currently shown falls far short of the required sight distance. Please revise, remove the
shading, and show the sight distance easements (areas of sight distance triangles that fall
outside of the ROW) needed on all of the plans and add the sight distance easement
restriction language to all plans and the plat.
Number: 16 Created: 10/11/2004
[10/11/041 Please provide a temporary turnaround at the end of the public street to be
partially constructed with Phase 1. This is a requirement of the LUC.
Number: 17 Created: 10/11/2004
[10/111041 On the site and utility plans and plat, please clearly show, label, and dimension
all ROW and easements.
Number: 16 Created: 10/11/2004
[10/11/04] In order to meet the ODP for this area, Tract B will have to come in (in the future)
with a public street aligning with Innovation and connecting to the shown unnamed street.
Number: 19 Created: 10/11/2004
[10/11/04] Please match all plans and the titles on the plans. This is the 37th Filing of
Oakridge Business Park.
Signature
inl�G
Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat _� ' Site Drainage Report Other
Utility _ �[_ Redline Utility = Landscape
Page 1
FINAL PLAN
6a COMMENT SHEET
City of Fort Collins
Current Planning
DATE: June 22, 2005 TO: Engineering
PROJECT: #13-82CX Oakridge Business Park, 37th Filing,
Homewood Suites, Final Plans
These new plans are to replace plans sent out on
June 2, 2005. Note that an additional week has been given to
review these plans.
All comments must be received by Steve Olt no later than the staff
review meeting:
July 6, 2005
Note - Please identify your redlines for future reference
No Problems
❑ Problems or concerns (see below or attached)
j , 6&V tj D Pr+-- y t I- E-e 4 I- C t.o_<C .
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
,Plat _Site _Drainage Report _Other
_Utility _Redline Utility Landscape
Project Comments Sheet
Selected Departments
City of Fort Collins
Department: Engineering
Date: July 11, 2005
Project:
OAKRIDGE BUSINESS PARK, 37TH FILING, HOMEWOOD SUITES PDP
AND FINAL PLANS
All comments must be received by Steve Olt in Current Planning, no later than the
staff review meeting:
July 06, 2005
Note - Please identify your redlines for future reference
Issue Contact: Katie Moore
Topic: General
Number: 15 Created: 10/11/2004
(714105] Please add this variance to the list of approved variances in the utility plans, and
add to the plans that curbs will be painted red and no parking signs will be added along
OakRidge.
[3/15/05] A variance request was approved for the sight distance easements needed on
Oakridge. Please list this approval in the general notes, show the easement on all plans,
add the sight distance easement restrictions to the site and landscape plans, and clarify on
all plans that no parking will be allowed on Oak Ridge for the project's frontage on Oak
Ridge.
The sight distance easements shown still do not appear to match the requirements, even
the one on Oak Ridge. The 310' distance required is measured along the street centerline,
then a straight line connects the spot on the driveway 10' from flowline or the spot on the
street 13' from flowline to that location on the curb. All area not within ROW must be
dedicated as a sight distance easement and everything within that easement must meet the
restrictions of the SDE. No parking lots are allowed within SDE's. See sheet 6, utility plan.
[10/11104] Please use LCUASS Figure 7-16 to calculate the sight distance easements
needed from the street intersection and the drive intersections with Oakridge. The shading
currently shown falls far short of the required sight distance. Please revise, remove the
shading, and show the sight distance easements (areas of sight distance triangles that fall
outside of the ROW) needed on all of the plans and add the sight distance easement
restriction language to all plans and the plat.
Number: 16
Signature
Created: 10/11 /2004
Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
` Plat Site Drainage Report Other .
Utility Redline Utility Landscape
Page 1
[7/4/05] How will construction of the turnaround in phase 1 work with the construction of the
detention pond? Does the turnaround need to be off -set to the east to avoid grading
problems?
(3115/051 Please have the Phase 1 line include this turnaround.
[10/11/04] Please provide a temporary turnaround at the end of the public street to be
partially constructed with Phase 1. This is a requirement of the LUC.
Number: 17 Created: 10/11/2004
[7/4/05] Please label the sight distance easments on all plans.
[3/15/05] This includes the sight distance easements.
(10/11/04] On the site and utility plans and plat, please clearly show, label, and dimension
all ROW and easements.
Number: 20 Created: 10/11/2004
[7/4/05] The sidewalk is shown to meander on the southwest corner of OakRidge and
McMurray. Why? Also, an easement dedicated to the City for public access is required for
construction of the sidewalk in that location.
13/15/051 Repeat:
[10/11/04] Please show the street sidewalks on Oakridge and McMurry.
Number: 33 Created: 10/11/2004
[7/4/05]
[3/15105]
(10/11/04] Please refer to redlines and utility plan checklist for additional comments.
Number: 35 Created: 10/11/2004
[7/4/05]
(3/15/051 Phasing of grading still needs some clarification.
[10/11104] At final compliance, please provide additional clarification regarding the phasing
of the areas contained within the plat.
Number: 67
[7/4/05]
Created: 3/15/2005
(3/15/05] Please include a copy of the plat in the utility plan set.
Number: 68 Created: 3/15/2005
[7/4/05]
[3/15/05] All plans still need work to meet the scanability requirements under LCUASS
appendix E-6. Please revise.
Number: 83 Created: 7/4/2005
[7141051 1 did not receive a landscape plan to review this round.
Number: 84 Created: 7/4/2005
[7/4/05] Site plan: please add a legal description of the property to the site plan.
Number: 85 Created: 7/4/2005
[714/051 Grass -pave is not allowed within the ROW. Please remove.
Number: 86
Created: 7/4/2005
Pagel
[7/4/05] Please ensure that the plat matches the utility plans - ROW locations, easement
dimensions, etc. (temp turnaround easement dimension doesn't match)
Number: 87 Created: 7/4/2005
[7/4/05] Please label all retaining walls on all plans and provide a detail in the utility plans.
Any walls 3' or taller must have separate building permits.
Number: 89 Created: 7/4/2005
[7/4/05] It appears that the detention pond has grown. Shouldn't the drainage easement
grow, too?
Topic: Utility Plans
Number: 88 Created: 7/4/2005
[7/4105] Please label driveway widths on the utility plans.
Number: 90 Created: 7/4/2005
[7/4/05] Please provide intersection spot elevations for Pleasant Oak design.
Number: 91 Created: 7/4/2005
[7/4/05] Something is off between the plat and the Pleasant Oak design - the centerline radii
don't match. The plat is correct - the dimensions shown on the utility plans don't meet
standard.
Number: 92 Created: 7/4/2005
[7/4/05] Why does the flowline design for Pleasant Oak end at the end of phase 1? These
plans need to show the complete design of Pleasant Oak from Oak Ridge to McMurray.
Number: 93 Created: 7/4/2005
[7/4/05] Please add the pavement transition detail at cross -pans to the detail sheet.
Number: 94 Created: 7/4/2005
[7/4/05] Please provide specific details of all ped ramps including spot elevations to ensure
code -compliant construction.
Number: 95 Created: 7/4/2005
[7/4/05] Please label all curb return radii.
Number: 96 Created: 7/4/2005
[7/4/05] Please provide stations and elevations at all pc's, driveway intersections and
roadway intersections in both plan and profile views.
Number: 97 Created: 7/4/2005
[7/4/05] Please use centerline stationing, not a mix of centerline and flowline stationing.
Number: 107 Created: 7/11/2005
[7/11/05] There may be some future issues with the road construction if property changes
hands prior to the road construction being complete. Consolidation of the road construction
(building the road from beginning to end all at once) is highly recommended to avoid issues
with possibly needing grading easements at time of construction.
Number: 108
Created: 7/11 /2005
Page 3
[7/11/051 Please remove the street name of Innovation from the plans - the entire new road
is Pleasant Oak.
Page 4
FINAL PLAN
REVISION COMMENT
SHEET
DATE: August 12, 2005
TO: Technical Services
PROJECT PLANNER: Steve Olt
#13-82CX Oakridge Business Park, 37th Filing, Homewood
Suites - Final Plans
Please return all comments to the project planner no later than the staff
review meeting:
August 31, 2005
Note -.Please identify your redlines for future reference
❑Problems
❑ Problems or Concerns (see below or attached)
3ov KY 5 LFG/+& CHOSE
Z /_ &,/ <.vr7- /f rlN )-S kVef A r,
Name (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
_Plat _Site _Drainage Report _Other
Utility _Redline Utility _Landscape
-.®
City of Fort Collins
imProject Comments Sheet
Selected Departments
Citv of Fort Collins
Department: Engineering
Date: September 7, 2005
Project:
OAKRIDGE BUSINESS PARK, 37TH FILING, HOMEWOOD SUITES PDP
AND FINAL PLANS
All comments must be received by Steve Olt in Current Planning, no later than the
staff review meeting:
August 31, 2005
Note - Please identify your redlines for future reference
Issue Contact:
Topic: General
Number: 86 Created: 7/4/2005
[9/7/05] The site and landscape plans need to have the temporary turnaround design offset
to coordinate with the plat and utility plan set.
[7/4/05] Please ensure that the plat matches the utility plans - ROW locations, easement
dimensions, etc. (temp turnaround easement dimension doesn't match)
Issue Contact: Marc Virata
Topic: General
Number. 120 Created: 9/7/2005
[917/051 It appears some additional information should be specified regarding the
construction of the temporary turnaround. Will it be gravel? How will the water drain across
the turnaround in the interim? What are the contours/spot elevations?
Topic: Subdivision Plat
Number: 121 Created: 9/7/2005
[917/05] With the development not fully designing Pleasant Oak Drive out to McMurry, the
platted boundary of Pleasant Oak Drive needs to be reduced to the extent in which Pleasant
Oak Drive is to be rebuilt. The remaining portion of Pleasant Oak Drive will be dedicated
with the plat of the senior housing project.
_y D s
Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
_Plat _Site _ i Drainage Report Other
_Utility Redline Utility Y Landscape
Page I
Issue Contact:
Topic: Utility Plans
Number: 90 Created: 7/4/2005
[9/7/05) This doesn't appear to have been provided (show transition point to remove crown
as it approaches the intersection).
[7/4/05) Please provide intersection spot elevations for Pleasant Oak design.
Issue Contact: Marc Virata
Topic: Utility Plans
Number: 122 Created: 9/7/2005
[9/7/05] Remove the "Innovation Drive" indication from sheet 5 and correct the spelling of
"McMurry" on sheet 8.
Page 2
FINAL PLAN
REVISION COMMENT
SHEET
DATE: September 26, 2005
TO: Technical Services
M
PROJECT PLANNER: Steve Olt
#13-82CX Oakridge Business Park, 371h Filing, Homewood
Suites Final Plans
Please return all comments to the project planner no later than the staff
review meeting:
October 12, 2005
Note - Please identify your redlines for future reference
❑ No Problems
❑ Problems or Concerns (see below or attached)
au�Y#1-t:c-ac- cure.
Z, moVE 114.o-r z" iAiro 4r"1 GuR�� Trr3�£ oN Sr4"_rZ.
CAk
Name (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
_Plat _Site _Drainage Report _Other
_Utility _Redline Utility _Landscape gg
PROJECT
COMMENT SHEET
REC. D
Current PlanninLy
DATE: September 22, 2004 TO: Engineering Pavement
PROJECT: #13-82CV Oakridge Business Park, 361h Filing,
Homewood Suites — Type II (LUC)
All comments must be received by Steve Olt no later than the staff
review meeting:
October 13, 2004
Note -PLEASE identify vour redlines for future reference
Name (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat Site _Drainage Report _Other
_Utility _Redline Utility _Landscape
City of Fort Collins
1:20
Number: 20 Created: 10/11/2004
[10/11/04] Please show the street sidewalks on Oakridge and McMurry.
Number: 21 Created: 10/11/2004
✓[10111/04] Is there adequate existing ROW on McMurry and Oakridge, or does more need
to be dedicated with this project?
McMurry and Oakridge are collectors on the Master Street Plan, both also have parking and
should have total ROW of 76 feet.
Number: 23 Created: 10/11/2004
[10/11/04] Depending on future access locations onto the new street, additional sight
distance easements may be required.
Number: 24 Created: 10/11/2004
./[10/11/04] Please provide typical cross -sections for McMurry and Oakridge.
Number: 30 Created: 10/11/2004
[10/11/04] Emergency access easements adjacent to 3+ story buildings are required to be
30' wide. These easements should not overlap any curb, landscaping, walks, or parking.
Please revise plans to accommodate this. Also, turns in EAE's are required to have 25'
interior and 50' exterior radii measured from the same centerpoint.
Number: 31 Created: 10/11/2004
)(10/11/04] Please add standard street cut note to sheets showing street cut:
Limits of street cut are approximate. Final limits are to be determined in the field by the City
Engineering Inspector. All repairs to be in accordance with City street repair standards.
Number: 32 Created: 1011112004
V[10/11/04] ROW dedicated at street corners needs to be enough to locate the ramps and
walks within it. Please see attached detail and dedicate additional ROW as necessary.
Number: 33 Created: 10/1112004
[10/11/04] Please refer to redlines and utility plan checklist for additional comments.
Number: 34 Created: 10/1112004
[10/11/04] There are a number of items that are missing from the list of items required prior
to hearing (on the utility plan checklist). Another round of review will be needed prior to
hearing.
Number: 35 Created: 10/1112004
[10/11104] At final compliance, please provide additional clarification regarding the phasing
of the areas contained within the plat.
/? Number:43 Created:10/13/2004
[10/13/041 The variance request for driveway separations on Oakridge has not yet been
approved or disapproved. An email was sent to Traffic Operations regarding the request,
but an answer has not yet been received. Once the variance has been processed,
NorthStar engineering will be contacted with that information.
Topic: Street Design
Number: 25
Created: 10/11/2004
Page 2
PROJECT
COMMENT SHEET
Citv of Fort Collins
Current Plannints
DATE: September 22, 2004 TO: Technical Services
REC. D
PROJECT: #13-82CV Oakridge Business Park, 361h Filing,
Homewood Suites — Type II (LUC)
All comments must be received by Steve Olt no later than the staff
review meeting:
7\ H
October 13, 2004
Note - PLEAsE identify your redlines for future reference
/, ✓r`<tn1e4't,56'.
Z, A/[I1rac"R z,rs r /8m0 (✓%J1+ eZ-"D) /N Tt/L"
3 Tilc ZC L7/2A lntR� cA_vom>r'T AcRw_ + T/2.�__� 15 ti'c7 C 41c4iA13Lcr.
t/
w c ,,J1 T-rs� U,n Ac-wcC%2Ac-r�c"
14AT IS -T t-4� 30
5. 07,e> 4,� o= -rHu Tn,4�r A Ai%,!-r Nic Ma�krx�/ /
tj
k�5 r{T c: F �
Oil !S T1fv 30 Gl / o MTh' /� - Se?e/L/d TT 4,2CE La
Sf�e�-u e u
LUi2Qw'C7.
v
ttArnc," �rlLFcT P >7c1<<ti P'.icrA.�C_-I3
a
�F T/?7� rS . Ee-
r /14 cpX1S71ti%
Id
GLc'�
Name (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
/Plat _Site _Drainage Report _Other
_Utility _Redline Utility _Landscape c ty of Fes°
0
Project Comments Sheet
Selected Departments
City of Fort Collins
Department: Engineering
Date: October 14, 2005
Project:
OAKRIDGE BUSINESS PARK, 37TH FILING, HOMEWOOD SUITES PDP
AND FINAL PLANS
All comments must be received by Steve Olt in Current Planning, no later than the
staff review meeting:
October 12, 2005
Note - Please identify your redlines for future reference
Issue Contact: Marc Virata
Topic: General
Number: 126 Created: 10/10/2005
(10/10/051 I'd greatly suggest that the sidewalk on the east side of Pleasant Oak Drive not
be constructed at this time as inidicated and instead be constructed with the Senior Campus
project. By installing the sidewalk at this time, it runs the risk of being damaged by the
Senior Campus construction and also may not work out well with sequencing utility
construction (Light and Power would prefer to install their facilities for the Senior Campus
before sidewalk is installed).
Topic: Subdivision Plat
Number: 124 Created: 10/7/2005
[10/7/05] The plat has the turnaround for Pleasant Oak Drive dedicated as right-of-way,
which is reflected as -an access easement on the other documents. From a processing
standpoint, it would be easier to vacate an access easement rather than right-of-way. In
addition, operating under the assumption that fees are enacted for vacation of right-of-way
and vacation of easement, the fee for a vacation right-of-way will likely be twice as costly,
which would be required to be paid for by the Senior Campus developer.
Topic: Utility Plans
Number: 125 Created: 10/10/2005
[10110/051 On Sheet 8, edit the note regarding future construction/extension of Pleasant
Oak Drive as it seems to state the entire sheet is not for construction.
Number: 127 Created: 10/1112005
Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat Site Drainage Report Other_
Utility Redline Utility Landscape
Page I
[10/11/051 There is a storm sewer proposed with the 38th Filing that is shown to be
constructed across Pleasant Oak Drive which is located such that the road would need to be
torn up and reconstructed, which potentially has emergency access implications. Perhaps
this can be coordinated to minimize having to reconstruct the rod by the 38th Filing?
Page 2
,/f10111/04] Please provide minimum vertical curve lengths per LCUASS Fig 7-17 and 7-18.
Number: 26 Created: 10/11/2004
✓[10/11/04] Please show the intersection grades through Oakridge and McMurry.
✓ Number: 27 Created: 10/11/2004
[101111041 The grade approaching Oakridge exceeds the maximum of 4.0%. Please revise.
Number: 28 Created: 10/11/2004
✓[10/11/04] Please provide additional ramps at t-intersections as required by LCUASS.
Number: 29 Created: 10/11/2004
J [10/11/04] Please use min. 8' crosspans at the intersections with McMurry and Oakridge.
Topic: Utility Plans
Number: 22 Created: 10/11/2004
[10/11/04] Where drainage over public walks is currently shown to occur, please re -grade .
and/or add an under -walk drain to divert water under the walks (D-10, stormwater manual).
Page 3
x
REVISION ti
COMMENT SHEET
Current Planning
DATE: March 2, 2005 TO: Engineering Pavement
PROJECT: #13-82CW Oakridge Business Park, 37th Filing,
Homewood Suites PDP
All comments must be received by Steve Olt no later than the staff
review meeting:
March 16, 2005
Note - Please identify your redlines for future reference
No Problems
X Problems or Concerns (see below or attached)
Peaj S o ) 5 P'g-p�
Name (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
_Plat Site _Drainage Report _Other
_Utility Redline Utility _Landscape
Aft
City of Fort Collins
s
l[7
REVISION
COMMENT SHEET
Current Planning
DATE: March 2, 2005 TO: Technical Services
PROJECT: #13-82CW Oakridge Business Park, 37"' Filing,
Homewood Suites PDP
All comments must be received by Steve Olt no later than the staff
review meeting: `
March 16, 2005 ,/'`�
Note - Please identify your redlines for future reference
❑ No Problems
< Problems or Concerns (see below or attached)
I, %IIN DJ1 e4 � i-ec'pi'
Z, -rHCP_£ 11 R P'eoE"c E,• i11� I 'Tiaf" gLuizT'�'rua U�
� fr/�E .dw ORCRii7GE
Tazl✓£ PLrA:ANr OAK L2.1V/c-CAC /41/U'K �T /S C�LI2/es �-!v
G�-7
�. l / �c 26 Di?l+ / AJI �"' 1 m l , del LcrT j % / c 17 i2:5 % . $ nr 7 <TI o
Gc7- Z �J2� CJni Cv�ttT,a I3�. _ L•'%NEr2J 7i'
I
E S,"7- I S Na i L.uC.¢ T-.�t-
/s iT %c /LrnNly e,nr - % �Cc 1 %7" Jt'T /"-cs47" rnt 714
Name (please print)
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
V/Plat _Site _Drainage Report _Other
_Utility _Redline Utility _Landscape
/Adt Oft Project Comments Sheet
S
City of Fort Collins elected Departments
Department: Engineering
Date: March 18, 2005
Project:
OAKRIDGE BUSINESS PARK, 37TH FILING, HOMEWOOD SUITES -
TYPE II(LUC)
All comments must be received by Steve Olt in Current Planning, no later than the
staff review meeting:
March 16, 2005
Note - Please identify your redlines for future reference
Issue Contact: Katie Moore
Topic: General
Number: 15 Created: 10/11/2004
(3/15/05] A variance request was approved for the sight distance easements needed on
Oakridge. Please list this approval in the general notes, show the easement on all plans,
add the sight distance easement restrictions to the site and landscape plans, and clarify on
all plans that no parking will be allowed on Oak Ridge for the project's frontage on Oak
Ridge.
The sight distance easements shown still do not appear to match the requirements, even
the one on Oak Ridge. The 310' distance required is measured along the street centerline,
then a straight line connects the spot on the driveway 10' from flowline or the spot on the
street 13' from flowline to that location on the curb. All area not within ROW must be
dedicated as a sight distance easement and everything within that easement must meet the
restrictions of the SDE. No parking lots are allowed within SDE's. See sheet 6, utility plan.
[10/11/04] Please use LCUASS Figure 7-16 to calculate the sight distance easements
needed from the street intersection and the drive intersections with Oakridge. The shading
currently shown falls far short of the required sight distance. Please revise, remove the
shading, and show the sight distance easements (areas of sight distance triangles that fall
outside of the ROW) needed on all of the plans and add the sight distance easement
restriction language to all plans and the plat.
Number: 16 Created: 10/11/2004
[3/15/051 Please have the Phase 1 line include this turnaround.
[10/11/04] Please provide a temporary turnaround at the end of the public street to be
partially constructed with Phase 1. This is a requirement of the LUC.
Signature
3.((.v5
Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
✓ Plat ✓ Site Drainage Report ✓ Other ✓I—'3t-
✓ Utility —Redline Utility _„/Landscape
Page 1
Number: 17 Created: 10/11 /2004
[3/15/051 This includes the sight distance easements.
[10111/04] On the site and utility plans and plat, please clearly show, label, and dimension
all ROW and easements.
Number: 19 Created: 10/1112004
[3/15/05] Titles still do not match.
[10/11/04] Please match all plans and the titles on the plans. This is the 37th Filing of
Oakridge Business Park.
Number: 20
Created: 10/11 /2004
[3/15/05] Repeat:
[10/11/04] Please show the street sidewalks on Oakridge and McMurry.
Number: 23 Created: 10/11 /2004
[3/15105] Please see comment 15.
[101111041 Depending on future access locations onto the new street, additional sight
distance easements may be required.
Number: 24 Created: 10/1112004
[3/15/05] Please provide accurate typical cross -sections.
[10111/04) Please provide typical cross -sections for McMurry and Oakridge.
Number: 33
[3/15/05]
Created: 10/11 /2004
[10/11/04] Please refer to redlines and utility plan checklist for additional comments.
Number: 34 Created: 10/11 /2004
[3115/051 This comment can be disregarded, assuming the median is removed:
There is no information provided for the proposed median, and this information is required
prior to hearing. Other items are still inadequate as well.
[10/11/04] There are a number of items that are missing from the list of items required prior
to hearing (on the utility plan checklist). Another round of review will be needed prior to
hearing.
Number: 35 Created: 10/11 /2004
[3/15/05]
[10/11/041 At final compliance, please provide additional clarification regarding the phasing
of the areas contained within the plat.
Number: 43 Created: 10/13/2004
[3/15/05] The variance request for driveway separations on Oakridge only, for this project
only, has been approved.
[10/13/04] The variance request for driveway separations on Oakridge has not yet been
approved or disapproved. An email was sent to Traffic Operations regarding the request,
but an answer has not yet been received. Once the variance has been processed,
NorthStar engineering will be contacted with that information.
Number: 67 Created: 3/15/2005
[3/15/05] Please include a copy of the plat in the utility plan set.
Page 2
Number: 68 Created: 3/15/2005
[3/15/05] All plans still need work to meet the scanability requirements under LCUASS
appendix E-6. Please revise.
Number: 70 Created: 3/15/2005
[3/15/05] Since Pleasant Oak Drive has been downgraded to a Connector Local, all
driveways must use the standard drive cut (not radius) unless they serve over 350 trip ends
per day. If radius drive cuts are desired, please show that they will meet the definition of
high -volume.
Number: 71 Created: 3/15/2005
[3/151051 Please match the ROW shown for Pleasant Oak Drive on all plan sets and plat.
Number: 72 Created: 3/15/2005
[3/15/05] This comment can be removed assuming the driveways are removed from the
plans:
Driveways newly shown on the north side of Pleasant Oak opposite the hotel driveways do
not align or meet separation requirements. Please align.
Number: 74
Created: 3/15/2005
13/15/05] Interim Drawing 1606 - somehow the dimensions got off, please correct.
Number: 75 Created: 3/15/2005
[3/15/051 Please include detail for standard drive cut.
Page 3
lAocom ! FINAL PLAN
COMMENT SHEET
City of Fort Collins
Current Planning
DATE: June 22, 2005 TO: Engineering
PROJECT: #13-82CX Oakridge Business Park, 37 h Filing,
Homewood Suites, Final Plans
These new plans are to replace plans sent out on
June 2, 2005. Note that an additional week has been given to
review these plans.
All comments must be received by Steve Olt no later than the staff
review meeting:
July 6, 2005
Note - Please identify your redlines for future reference
;!g--No Problems
❑ Problems or Concerns (see below or attached)
f , 9 uNr7A'+v-Y' t 4-E&14L CLOS5C.
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
,Plat _Site _Drainage Report _Other
_Utility _Redline Utility _Landscape