HomeMy WebLinkAboutEVERGREEN PARK REPLAT BLOCK 4 LOT 1 - Filed CS-COMMENT SHEETS - 2005-10-28z Project Comments Sheet
ity of Fort Collins Selected Departments
C
Department: Engineering
Date: March 19, 2004
Project: EVERGREEN PARK, BLOCK 4, LOT 13 PDP
All comments must be received by Steve Olt in Current Planning, no later than the
staff review meeting:
March 17, 2004
Note - Please identify your redlines for future reference
Issue Contact: Marc Virata
Topic: General
Number: 9 Created: 3/15/2004
[3115/041 The owner of the transmission line easement will need to provide a letter
of intent agreeing in principle to the development proposal. In general, having the
driveway access within this easement seems to be unusual, will the developer
secure permanent legal right for the operation of the driveway?
Number: 10 Created: 3/15/2004
[3/15/04] The slope easement directly north of the site requires a letter of intent from
both the Food Bank and the power line easement holder.
Number: 11
Created: 3/15/2004
[3/15/04] The development illustrates a radius style driveway approach on the
plans. The Street Standards allow for the radial access in cases where there are
more than 350 tripes a day. The traffic report states that the site will generate less
than 200 daily trips, thus the use of a radius style driveway is not to standards.
Number: 25
Created: 3/16/2004
[3/16/041 Not required at this time but just as an FYI, provide legal descriptions for
the additional utility easement, emergency access easement and slope easement for
review. The applicant will be required to provide the necessary deeds of dedication
and recording fees for these easements.
Signature
Iz Drrte `i c;
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat _ ✓ Site Drainage Report Other_
Utility _%Redline Utilit�r —Landscape
Page 1
Number: 29 Created: 3/17/2004
[3/17/04] In further discussion with PFA, the fire lane required specified in #12
consists of a 20' emergency access easement to be dedicated around the entire
building connecting to the driveway and out to Blue Spruce Drive
Topic: Utility
Number: 22 Created: 3/16/2004
[3/161041 The amount of drainage directed over the sidewalk exceeds LCUASS
criteria. In general the City Engineer has ruled that an area of up to 750 sq.ft. is
allowed to drain over the sidewalk which is exceeded in the present design.
Number: 23 Created: 3/16/2004
[3/16/04] ADS is not allowed in right-of-way. Specify C900 or other City approved
pipe.
Number: 24 Created: 3/16/2004
[3/16/041 Is an asphalt swale at .6% sufficient to carry drainage flow? It seems that
the amount of slope isn't sufficient for asphalt and standing water degrading the
pavement is likely. (thought or suggestion, not a requirement)
Page 2
Project Comments Sheet
-= Selected Departments
Department: Engineering
Date: May 12, 2004
Project: EVERGREEN PARK, BLOCK 4, LOT 13 PDP
All comments must be received by Steve Olt in Current Planning, no later than the
staff review meeting:
May 12, 2004
Note - Please identify your redlines for future reference
Issue Contact: Marc Virata
Topic: General
Number: 9 Created: 3/15/2004
[5/11/041 The addition of the signature block for PRPA is of benefit for their signature on the plans. A letter if intent was
not received and still required prior to a hear'. ng.
[3/15/04] The owner of the transmission line easement will need to provide a letter of intent agreeing in principle to the
development proposal. In general, having the driveway access within this easement seems to be unusual, will the
developer secure permanent legal right for the operation of the driveway?
Number: 10 Created: 3/15/2004
[5/11/041 A letter of intent was not received.
[3/15/041 The slope easement directly north of the site requires a letter of intent from both the Food Bank and the
power line easement holder.
Number: 25 Created: 3/16/2004
[5/11/041 Carried over for reference.
(3/16/04] Not required at this time but just as an FYI, provide legal descriptions for the additional utility easement,
emergency access easement and slope easement for review The applicant will be required to provide the necessary
deeds of dedication and recording fees for these easements.
Number. 87 Created: 5/12/2004
[5/12/041 A "Memorandum of Agreement and Notice" will be required as the project is not being (re)platted. Attached is
a sample blank version of the document. After a public hearing, information will be required for Engineering to fill this
out and the owner/developer will need to sign and provide a check for recording fees.
Signature -
Date
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
Plat Site Drainage Report Other_
Utility _ Redline Utility Landscape
Page I
Project Comments Sheet
Selected Departments
City of Fort Collins
Department: Engineering
Date: May 17, 2004
Project: EVERGREEN PARK, BLOCK 4, LOT 13 PDP
All comments must be received by Steve Olt in Current Planning, no later than the
staff review meeting:
May 12, 2004
Note - Please identify your redlines for future reference
Issue Contact: Marc Virata
Topic: General
Number: 9 Created: 3/15/2004
(5/11/04] The addition of the signature block for WAPA is of benefit for their signature on the plans, A letter if intent
was not received and still required prior to a hearing.
[3/15/041 The owner of the transmission line easement will need to provide a letter of intent agreeing in principle to the
development proposal. Ian general, having the driveway access within this easement seems to be unusual, will the
developer secure permanent legal right for the operation of the driveway?
Number: 10
(5/11/041 A letter of intent was not received.
Created: 3/15/2004
[3115/04] The slope easement directly north of the site requires a letter of intent from both the Food Bank and the
power line easement holder.
Number: 25
[5/111041 Carried over for reference.
Created: 3/16/2004
[3/16/041 Not required at this time but just as an FYI, provide legal descriptions for the additional utility easement,
emergency access easement and slope easement for review. The applicant will be required to provide the necessary
deeds of dedication and recording fees for these easements.
Number: 87 Created: 5/12/2004
[5112/041 A "Memorandum of Agreement and Notice" will be required as the project is not being (re)platted. Attached is
a sample blank version of the document. After a public hearing, information will be required for Engineering to fill this
out and the owner/developer will need to sign and provide a check for recording fees.